Client Alert

Contractual Implications of the COVID-19 Pandemic – Can it Excuse a Business from Performance of Contractual Obligations Under Contracts Governed by English Law?

March 27, 2020

by Joseph Lewin

Download as a PDF

Share this page

The continuing COVID-19 pandemic is causing significant disruption across the globe with governments implementing a variety of measures, including travel restrictions, nationwide lockdowns and the cancellation of large-scale events, in an attempt to curb the spread of the virus.  Such unprecedented measures mean that businesses around the world are now faced with the question of whether they will be able to perform their contractual obligations.

In this article, we consider the circumstances under which the COVID-19 crisis may either (i) constitute a force majeure event under a contract; or (ii) lead to a contract being discharged by frustration, and therefore allow one or more of the parties to avoid contractual performance.

Force Majeure

Purpose

A force majeure clause is a clause designed to excuse a party from the performance of its obligations under a contract upon the occurrence of certain specified events which are beyond that party’s reasonable control.  A classic example would be in the event of a natural disaster.

An example of a force majeure clause is as follows:

A party shall not be in breach of this agreement, nor liable for any failure or delay in performing any of its obligations under this agreement arising from or attributable to matters beyond its reasonable control. If such circumstances arise, the party concerned shall be granted a reasonable extension of time for performing its obligations. If the period of non-performance persists for 30 days, either party may terminate this agreement by giving 14 days' written notice to the other party.

If a contractual force majeure event occurs, then a contracting party may be excused from its contractual obligations without incurring any liability, and it may be able to suspend, or in certain circumstances, terminate, the contract.

Interpretation

The key determinant of whether an event can allow a party to be excused from performance is whether that event is in the drafting of the clause itself.

  • Scope – The wording of a force majeure clause will determine whether the COVID-19 pandemic fall within its scope.  The force majeure clause may refer specifically to a pandemic, or to other events which have occurred as a result of the pandemic, for example, an act of government which has prevented contractual performance.  A party seeking to rely on a force majeure clause will need to carefully consider whether the COVID-19 pandemic constitutes a force majeure event, something that will ultimately depend on the precise wording of the clause.
  • Trigger event – It will also be necessary for a party seeking to rely on a force majeure clause to demonstrate that the COVID-19 pandemic has caused that party’s failure to perform its contractual obligations, often by hindering or preventing performance.  Again, this will depend on the wording of the clause and the particular factual circumstances.  However, the mere fact that a contract becomes more expensive to perform as a result of a force majeure event is generally insufficient to constitute a force majeure allowing that party to be excused from its obligations.

Mitigation and notification

Force majeure clauses often require the party seeking to rely on the clause to (i) give the other party notice of anticipation or occurrence of a force majeure event; and (ii) take reasonable steps to prevent or mitigate the effects of a force majeure event.

For example, prevention of a force majeure event in a supply of goods contract may require finding an alternative method of transportation for the goods if the desired method becomes unavailable.

Even if a force majeure clause does not expressly include an obligation to mitigate, the obligation may be implied by law, so it is prudent for parties to take steps to mitigate the impact of a force majeure in any event.

It is important that any notification and/or mitigation requirements are complied with correctly, as failure to do so may prevent a party from relying on a force majeure clause.

Consequences

If a valid force majeure event is established, the party relying on it may be entitled to:

  1. temporary suspend contractual obligations with an extension of time to perform those obligations;
  2. relief from liability for non-performance or delayed performance for the duration of the force majeure event; and 
  3. terminate the contract if the force majeure event continues for a specified period of time.

Frustration

If there is no force majeure clause in a contract, a party that is unable to perform its obligations will need to consider other possibilities.

In some circumstances, it may be possibly for a party to rely on the doctrine of frustration, which can allow termination of the contract and discharge all parties from future obligations.

Frustration applies if an unforeseen event occurs after the contact was entered into, which renders performance of the contract impossible or radically different from what was agreed by the parties when the contract was formed.

Frustration is, in normal times, difficult to establish.  Generally, a contract will only be frustrated in extreme circumstances.

In previous cases, the Courts have found that the destruction of the subject matter of the contract by fire or a change in the law making the contract illegal to perform were frustrating events. Generally, a contract will not be frustrated if (i) the event renders the contract more expensive or difficult to perform; (ii) an alternative method of performance is available; or (iii) the event is the fault of one of the contracting parties.

Although frustration requires a high threshold to be established, we are living in unprecedented times and it is possible that the COVID-19 pandemic may lead to the frustration of contracts which have become impossible to perform.

Practical considerations

Businesses that are faced with contractual obligations which have been significantly disrupted by the COVID-19 pandemic should:

  • identify whether any key contracts contain a force majeure clause, and determine whether the COVID-19 pandemic, or any events relating to the pandemic, might fall within the definition of a force majeure event;
  • ensure strict compliance with any notice or mitigation requirements set out in the force majeure clause itself.  Even if a force majeure clause does not contain a mitigation obligation, steps to mitigate the impact of a force majeure event should be taken in any event as the duty may be implied by law, and records of any steps taken should be kept; and
  • if a contract does not contain a force majeure clause, consider whether frustration may be available.

Dorsey are experts on the matters discussed in this article and have advised clients on force majeure and frustration previously.  For more information, please contact Timothy Maloney or Matthew Blower in our European Arbitration, Dispute Resolution and Commercial Litigation Practice.

This article is intended for general information purposes only and should not be construed as legal advice or legal opinions on any specific facts or circumstances.  Members of Dorsey & Whitney are here to help and we will be pleased to provide further information regarding the matters discussed in this article. We have also created a Coronavirus Resource Center containing other briefings and information related to the current crisis: www.dorsey.com/coronavirus.

 

Firm Highlights

News

Dorsey Practices and Attorneys Recognized by Legal 500 Greater China 2027

Legal 500 Greater China 2027 recognized Dorsey & Whitney LLP in five practice areas across China (Mainland) and Hong Kong SAR and recommended six Dorsey attorneys. The Firm’s litigation practice in China advanced from Tier 4 to Tier 3 among foreign firms. Dorsey received the following practice recognitions in the 2027 edition: China — Leading Firm: Dispute Resolution: Litigation (Foreign Firms) China — Leading Firm: Insurance (Foreign Firms) China — Leading Firm: Regulatory/Compliance (Foreign Firms) Hong Kong — Leading Firm: Intellectual Property Hong Kong — Firms to Watch: Capital Markets (Equity) Leading Firm in China for Dispute Resolution: Litigation (Foreign Firms) Recommended Lawyers: Ray Liu and Janet Wong Dorsey’s litigation team excels in managing high-stake China-related cross-border disputes and legal proceedings in the United States, Hong Kong, Europe, and other jurisdictions. Its work spans an extensive array of industries including banking and finance, insurance, TMT, manufacturing, biotechnology, and life sciences. The improved ranking this year highlights the continued market recognition, the strength of our team, the quality of our client service, and our continued commitment to deliver exceptional results. Leading Firm in China for Insurance (Foreign Firms) Recommended Lawyer: Ray Liu Dorsey’s Beijing-based insurance team works with colleagues in the United States and Europe on a broad range of insurance-related disputes, with a particular focus on general liability and product liability litigation. The team also frequently advises on war risk insurance, all-risk insurance, insurance regulatory matters, and reinsurance issues, and assists major Chinese insurance companies with outbound investments, and regulatory compliance related disputes. Leading Firm in China for Regulatory/Compliance (Foreign Firms) Recommended Lawyers: Ray Liu and Karen Yiqin Fan Dorsey’s China team regularly advises on export controls, economic sanctions, national security/CFIUS, trade compliance, capital markets, and financial regulatory compliance. The team also counsels clients on data privacy, employment compliance, corporate investigations, and foreign entity of concern (FEOC) requirements under the Inflation Reduction Act (IRA) and the One Big Beautiful Bill Act (OBBBA). Leading Firm in Hong Kong for Intellectual Property Recommended Lawyers: Janet Wong and Lilian Shi Dorsey’s Greater China IP team advises multinational and local clients on the protection, management, enforcement, and commercialization of intellectual property assets across Greater China and globally. The team develops and manages global IP portfolios, advises on brand protection and anti-counterfeiting strategies, and handles contentious IP matters, including trademark infringement, copyright, trade secret, company name, and domain name disputes. The team also advises on IP-related transactions and commercialization, including IP due diligence, acquisitions and divestitures of IP rights, technology transfers, licensing and franchising arrangements, and supply, distribution, and manufacturing arrangements. Firms to Watch in Hong Kong for Capital Markets (Equity) Recommended Lawyers: Rachel Han and Megan Penick Dorsey’s Hong Kong and U.S. capital markets teams work seamlessly together on initial public offerings and placings in Hong Kong, along with initial public offerings, follow-on and secondary offerings, cross-border financings, and PIPE investments in the United States, and transactions in other international financial centers. The team also advises listed companies on ongoing compliance and regulatory matters in both Hong Kong and the United States. Drawing on Dorsey’s multidisciplinary capabilities, the Hong Kong capital markets team provides complementary advice on international sanctions and U.S. export control regulations.

Insights

Ninth Circuit Splits California’s Climate Disclosure Laws: Scope 1 and 2 Reporting Proceeds; Scope 3 and SB 261 Likely Unconstitutional

Key Takeaways On November 9, 2026, the Ninth Circuit in Chamber of Commerce v. Sanchez allowed Scope 1 and Scope 2 greenhouse gas (GHG) emissions reporting under SB 253 to proceed but held that SB 253’s Scope 3 requirement, and SB 261 in its entirety, likely violate the First Amendment.1 U.S.-formed entities with total annual revenues above $1 billion that do business in California remain subject to Scope 1 and 2 reporting. First reports (or, for eligible entities, statements of non-reporting) were due November 10, 2026.2 Scope 3 reporting (scheduled to begin in 2027) and SB 261 climate-risk reporting are effectively on hold. Entities with revenues between $500 million and $1 billion, which were covered only by SB 261, currently have no reporting obligation under either law.3 The ruling addresses only preliminary injunctive relief; it is not a final judgment on the merits. If the district court finds the Scope 3 requirement non-severable, it could also enjoin Scope 1 and 2 reporting.4 Background SB 253 (the Climate Corporate Data Accountability Act) requires U.S.-formed entities with total annual revenues above $1 billion that do business in California to report Scope 1 and 2 emissions starting in 2026 and Scope 3 emissions starting in 2027, with penalties of up to $500,000 per reporting year.5 SB 261 (the Climate-Related Financial Risk Act) requires U.S.-formed entities with total annual revenues above $500 million that do business in California to publish biennial climate-related financial risk reports consistent with the Task Force on Climate-related Financial Disclosures (TCFD) framework, with penalties of up to $50,000 per reporting year.6 Business groups led by the U.S. Chamber of Commerce challenged both laws as compelled speech that violates the First Amendment. In August 2025, the district court denied their motions for preliminary injunctions. On November 18, 2025, the Ninth Circuit enjoined SB 261 pending appeal but declined to enjoin SB 253.7 The implementing regulation adopted by the California Air Resources Board (CARB) took effect on October 12, 2026, and set November 10, 2026, as the first Scope 1 and 2 reporting deadline.8 The Court’s Decision Scope 1 and Scope 2: Upheld for Now The panel held that Scope 1 and 2 disclosures are commercial speech because they compel disclosure of factual information about emissions from a company’s own operations and purchased energy—information that bears on capital transactions. Applying intermediate scrutiny, the court concluded that the requirements advance California’s substantial interests in reducing information asymmetries for investors and in reducing emissions and are no more extensive than necessary.9 The panel split 2–1 on this issue.10 Scope 3: Likely Unconstitutional The court held that Scope 3 disclosures concern diffuse third-party conduct across the value chain and are “insufficiently tethered” to the reporting entity’s own operations to qualify as commercial speech. Applying strict scrutiny, the court concluded that the requirement likely fails because (1) SB 253 does not require primary data, (2) the record did not show that companies’ proxy-based estimates would be more reliable than estimates the State could generate itself, and (3) the link to investor-relevant risk was too remote.11 SB 261: Likely Unconstitutional in Its Entirety The court held that SB 261 compels noncommercial speech because it requires “predictive and normative judgments” about a “politically fraught subject.” Even assuming California’s interests are compelling, the court reasoned that the law is likely not narrowly tailored because California could use less restrictive alternatives, such as incentives for voluntary disclosure.12 The panel was unanimous on Scope 3 and SB 261.13 Remand and Severability The Ninth Circuit did not enter injunctions itself. It reversed the denials of preliminary injunctive relief and remanded with instructions for the district court to enter relief consistent with the opinion and, for Scope 3, to decide severability first.14 SB 253 contains an express severability clause. If the district court nevertheless finds the Scope 3 requirement non-severable, it could also enjoin Scope 1 and 2 reporting.15 Current Status at a Glance Requirement Status after the Ruling Practical Effect SB 253 – Scope 1 and 2 emissions (entities with revenues above $1 billion) In effect; denial of preliminary injunction affirmed First reports were due November 10, 2026; CARB fee notices expected by December 10, 202616 SB 253 – Scope 3 emissions (scheduled to begin in 2027) Likely unconstitutional; remanded for severability ruling and entry of injunctive relief Not required while remand is pending; scope of CARB’s 2027 rulemaking uncertain17 SB 261 – climate-related financial risk reports (entities with revenues above $500 million) Likely unconstitutional in its entirety; enjoined pending appeal since November 18, 2025 No current reporting obligation; voluntary reports permitted18 What to Watch Any petition for panel rehearing or rehearing en banc (due 14 days after entry of judgment) and any petition for a writ of certiorari to the U.S. Supreme Court.19 The district court’s severability ruling and the scope of any preliminary injunctions it enters as to Scope 3 and SB 261.20 CARB’s response. As of the date of this alert, CARB has not issued a formal statement on the opinion.21 CARB had been developing a second rulemaking for reporting years 2027 and later, addressing Scope 3, assurance, deadlines, and reporting templates, and had proposed retaining November 10 as the annual deadline.​​​​​​​22 Recommended Actions Confirm coverage entity by entity. Revenue (gross receipts, based on the lesser of the two prior fiscal years) and “doing business in California” are determined separately for each entity; affiliates are not aggregated. Retain supporting California tax records for five years.23 If a covered entity has not filed, file promptly. Submit the Scope 1 and 2 report (or, if eligible, a statement of non-reporting) and document good-faith compliance efforts, which CARB must consider in assessing penalties.24 Calendar the fee cycle. CARB expects to issue fee notices by December 10, 2026, with payment due within 60 days after the notice; each day of nonpayment is a separate violation.​​​​​​​25 CARB’s August 2025 proposal set flat fees at $3,106 per SB 253 entity and $1,403 per SB 261 entity.26 Confirm the final amount when the CARB notice arrives. Prepare for 2027 Scope 1 and 2 reporting. Third-party assurance was not required for 2026, but CARB has signaled that it will require limited assurance of Scope 1 and 2 data for 2027 and later years.27 Engage assurance providers and strengthen internal data controls now. Pause, but preserve, Scope 3 and SB 261 workstreams. Maintain existing data and processes: the ruling is preliminary, and many multinational companies will still need Scope 3 and product-level emissions data under the EU’s Corporate Sustainability Reporting Directive (CSRD) and Carbon Border Adjustment Mechanism (CBAM).28 Companies may still publish SB 261 reports voluntarily.29 Review public statements. Continue to review voluntary climate disclosures for consistency with CARB filings and other regulatory reports. Considerations for Real Estate and Infrastructure Clients The following are practice recommendations, not statutory requirements: Control boundaries. Whether emissions from a building or data center fall within a landlord’s or a tenant’s Scope 1 or 2 inventory depends on the control approach applied under the GHG Protocol. Leases, colocation agreements, and powered-shell arrangements should specify which party has operational control for GHG reporting purposes. Data cooperation. Include obligations to deliver utility and energy data (with specified timing and format) and to cooperate with assurance providers, particularly where the landlord or operator holds the utility accounts. Transactions. In acquisitions and financings, diligence the target’s or borrower’s SB 253 compliance and fee payments, and consider representations and covenants on the accuracy of emissions data. Value-chain requests. Counterparty requests for Scope 3 data may slow, but those subject to CSRD will likely continue to make them. This alert is for general information only and is not legal advice. The law in this area is changing rapidly, and developments after November 18, 2026, may affect this analysis.  1 Chamber of Commerce v. Sanchez, No. 25-5327 (9th Cir. Nov. 9, 2026) 2 White & Case, California Climate Disclosure Laws: Ninth Circuit Finds SB 253 Scope 3 Requirements and SB 261 Likely Unconstitutional (Nov. 2026) 3 Legal 500, Ninth Circuit Approves California’s Core Carbon Emissions Reporting Rules (Nov. 2026) 4 White & Case, supra note 2. 5 Kirkland & Ellis, Ninth Circuit Rules on California’s Climate Disclosure Laws (Nov. 2026) 6 Simpson Thacher, California Climate Reporting Laws: Ninth Circuit Issues Partial Injunction (Nov. 2025) 7 White & Case, supra note 2. 8 Vinson & Elkins, OAL Approves CARB’s Initial Regulation (Oct. 2026) 9 White & Case, supra note 2. 10 Foley & Lardner, California Climate Disclosure Laws (Nov. 2026) 11 White & Case, supra note 2. 12 Chamber of Commerce, No. 25-5327. 13 Kirkland & Ellis, supra note 5. 14 Troutman Pepper Locke, Ninth Circuit Rules on Challenge to California’s Climate Disclosure Laws (Nov. 2026) 15 White & Case, supra note 2. 16 Davis Polk, Getting Ready for California SB 253’s November 10 Reporting Deadline (Oct. 2026) 17 Troutman Pepper Locke, supra note 14. 18 White & Case, supra note 2. 19 Id. 20 Troutman Pepper Locke, supra note 14. 21 Morgan Lewis, Ninth Circuit Reverses Lower Court (Nov. 2026) 22 Simpson Thacher, CARB Provides New Guidance on SB 253 Reporting (July 2026) 23 Davis Polk, supra note 16. 24 Id. 25 Id. 26 CARB, SB 253/261 Public Workshop Slides (Aug. 2025) 27 Vinson & Elkins, supra note 8. 28 O’Melveny, Is Your Company Still Required to Report Under California’s Climate Laws? (Nov. 2026) 29 White & Case, supra note 2.