Client Alert

Energy Law: Month in Review - June 2024

July 2, 2024

Download as a PDF

Share this page

AUTHORS

Welcome to Dorsey’s Energy Law: Month in Review. We provide this update to our clients to identify significant developments in the previous month. Please reach out to any of the authors, listed above, to discuss these issues.

Table of Contents

REGULATORY AND STATUTORY DEVELOPMENTS

Maryland Public Service Commission Rejects Exelon Utility’s $213.6 Million Multiyear Rate Plan
The Maryland Public Service Commission (“Maryland PSC”) rejected Exelon subsidiary Potomac Electric Power Co.’s (“PEPCO”) proposal for a $213.6 million rate increase over approximately four years. Instead of approving the multi-year rate plan, the Maryland PSC authorized a $44.6 million rate hike for one year, down from the $117.2 million the utility was seeking in the first year of its four-year proposal. PEPCO had asked for a 10.5% return on equity (“ROE”). The Maryland PSC instead approved a 9.5% ROE. In support of its rate proposal, PEPCO argued that the multi-year plan would give the utility predictable revenue to make needed reliability and safety-related investments. PEPCO also argued that the proposed rate plan would allow customers to know what their rates would be for several years instead of facing annual changes. The Maryland Office of People’s Counsel opposed the plan, however, arguing that multi-year rate plans benefit utilities but hurt customers. 


U.S. Senate Approves Three Federal Energy Regulatory Commission Nominees
On June 12–13, 2024, the U.S. Senate confirmed three nominees to fill vacant commissioner positions at the Federal Energy Regulatory Commission (“FERC”). FERC staffer David Rosner and Massachusetts Undersecretary for Energy and Climate Solutions Judy W. Chang were confirmed to fill the two Democratic vacancies. West Virginia Solicitor General Lindsay S. See was confirmed to fill the Republican vacancy. The confirmed nominees give FERC a full slate of five commissioners. Commissioner Rosner was a FERC energy-industry analyst who had been temporarily assigned to the Democratic staff on the Senate Energy Committee. Commissioner Chang, an energy economist and policy expert who is a managing principal at economic consulting firm Analysis Group, was Massachusetts Undersecretary of Energy and Climate Solutions from 2020 to 2023. Commissioner See had been West Virginia Solicitor General and handled oral arguments before the U.S. Supreme Court for Republican-led states in West Virginia v. E.P.A., limiting the U.S. Environmental Protection Agency’s authority to regulate greenhouse gas emissions from power plants. 

FERC Concludes that Utility Self-Funding Rules for Interconnection Upgrades May Unfairly Increase Costs
In a show-cause order issued June 13, 2024, FERC questioned four regional transmission providers’ rules concerning transmission owners’ right to pay for, and to profit from, network upgrades needed to connect generation and energy storage to the grid. According to FERC, rules for “initial funding” may increase interconnection costs without corresponding improvements to that service, may block interconnection, and may allow transmission owners to discriminate in favor of themselves and their affiliates. FERC required Midcontinent Independent System Operator (“MISO”), PJM Interconnection, Southwest Power Pool, and ISO New England to respond to the show-cause order within 90 days. FERC’s order requires the operators to respond to a series of questions concerning: (1) whether their rules had protections to prevent transmission owners from boosting their rate base by unjustly increasing network-upgrade costs paid for through initial funding, (2) the rules’ impact on potential discrimination in favor of themselves, and (3) proposals to establish new network-upgrade funding rates that could be used if FERC ultimately rejects the initial-funding paradigm but finds that transmission owners face uncompensated risks from the upgrade projects.

U.S. Senate Approves Bipartisan Nuclear Energy Legislation 
Following its May 8, 2024, passage by the House of Representatives, on June 20, 2024, the U.S. Senate approved bipartisan legislation streamlining the Nuclear Regulatory Commission’s (“NRC”) oversight of the existing U.S. nuclear-reactor fleet and potentially accelerating the permitting and deployment of advanced nuclear reactors. The bill would require the NRC to update its mission statement to include that licensing and regulation of the civilian use of radioactive materials and nuclear energy be conducted in an efficient manner that does not unnecessarily limit their use. The bill also directs the NRC to: (1) reduce certain licensing application fees, (2) study and develop licensing-review processes for nuclear facilities located on brownfields sites, (3) create expedited procedures for combined reactor-license applications for already-certified commercial reactor sites on or adjacent to existing or previous commercial-reactor sites, (4) establish risk-informed and performance-based guidance for micro-reactor licensing, and (5) coordinate with the U.S. Department of Energy on advanced nuclear-fuel qualification and licensing. 

NV Energy Seeks New Tariff to Supply Google with 24/7 Power from the Fervo Geothermal Plant
On June 7, 2024, Google and NV Energy asked the Nevada Public Utilities Commission for permission to enter into a power-supply agreement based on a proposed “Clean Transition Tariff” that would allow large energy users to pay a premium for 24/7 clean energy from new resources. Under the proposed supply agreement, NV Energy would buy electricity from Fervo Energy’s 115-MW Corsac Station Enhanced Geothermal Project, which remains under development, and sell it to Google for a premium set rate. Google would, in turn, receive credit for the project’s energy and generation capacity on electric bills for its data centers in Storey County, Nevada, offsetting demand charges associated with those facilities. Google also argues that the tariff is needed to incent the deployment of more carbon-free dispatchable energy resources (like geothermal and nuclear generation) by allowing users to make up the difference between the cost of these capital-intensive resources and low-cost options like solar or natural gas. While the agreement, if approved, will only provide enough energy to supply its data center, Google argues that it will model a framework that other customers and other states could replicate to the benefit of users and suppliers alike. 

New York Public Service Commission Adopts Energy Storage Framework Detailing Path to 6 GW by 2030
On June 20, 2024, the New York Public Service Commission (“New York PSC”) approved a new framework for deploying 6 GW of new energy storage by 2030. The 6 GW target represents at least 20% of New York’s peak electricity load and could trim nearly $2 billion from projected future statewide electric-system costs as New York transitions to generating 70% of its electricity needs from renewable sources by 2030. The approved framework will require an additional 4.7 GW in new storage deployments to complement 1.3 GW of existing storage assets already procured or under contract. New York’s framework aims for 3 GW of new utility-scale storage to be procured under the state’s new competitive Index Storage Credit mechanism and 1.5 GW of new retail storage, both for assets with discharge durations up to four hours. Retail storage includes commercial, industrial, and community-scale installations. The framework also envisions 200 MW of new residential storage assets with durations up to two hours. 

LITIGATION AND DISPUTES

D.C. Circuit Court of Appeals Rejects New York Electricity Rate Challenge
On June 14, 2024, a D.C. Circuit Court of Appeals panel rejected the New York PSC's attempt to unravel FERC’s approval of the state grid operator’s wholesale electricity rates, leaving in place an estimated 17-year lifespan for new fossil-fueled power plants. The New York Independent Systems Operator (“NYISO”) initially filed its proposed rates for electricity-generating entities in 2020 for the 2021–2025 period, shortening the estimated power plant amortization period from 20 years to 17 years. NYISO justified the shortened amortization period, which is intended to reflect the number of years an investor in a new plant should expect to recover the costs of developing the plant, on the ground that a 2019 climate law—known as the New York Climate Leadership and Community Protection Act—requires the statewide electrical-demand system to be emission-free by 2040. In an earlier case, the D.C. Circuit overturned FERC’s rejection of the proposed rates with respect to the amortization period. On remand, FERC initially reasserted its determination that the shorter life span was inappropriate because the New York PSC had yet to enact a plan to reach a zero-emission electricity system by 2040. On rehearing, however, FERC concluded that NYISO made reasonable assumptions about the impact of the climate, leading the New York PSC to turn to the D.C. Circuit in September.

On the second appeal, the D.C. Circuit stated that, because FERC approved NYISO’s proposal, the issue before the court was simply whether the agency reasonably concluded the 17-year amortization period fell within “the zone of reasonableness.” The court noted that its “prior judgment vacating FERC’s original decision held that NYISO needed to show that it had chosen a ‘reasonable estimate’ of how long an investor would expect a new gas-fired plant to remain ‘commercially viable.’” Emphasizing the climate law’s “open-ended language,” which “gives no indication whether each plant must generate zero emissions, or whether zero net statewide emissions will suffice,” the court held that a reasonable investor could predict that a new fossil-fueled power plant would not “remain commercially viable” past 2039. Accordingly, FERC was obligated to accept the NYISO’s reasonable interpretation of the act.


Firm Highlights

Insights

Ninth Circuit Splits California’s Climate Disclosure Laws: Scope 1 and 2 Reporting Proceeds; Scope 3 and SB 261 Likely Unconstitutional

Key Takeaways On November 9, 2026, the Ninth Circuit in Chamber of Commerce v. Sanchez allowed Scope 1 and Scope 2 greenhouse gas (GHG) emissions reporting under SB 253 to proceed but held that SB 253’s Scope 3 requirement, and SB 261 in its entirety, likely violate the First Amendment.1 U.S.-formed entities with total annual revenues above $1 billion that do business in California remain subject to Scope 1 and 2 reporting. First reports (or, for eligible entities, statements of non-reporting) were due November 10, 2026.2 Scope 3 reporting (scheduled to begin in 2027) and SB 261 climate-risk reporting are effectively on hold. Entities with revenues between $500 million and $1 billion, which were covered only by SB 261, currently have no reporting obligation under either law.3 The ruling addresses only preliminary injunctive relief; it is not a final judgment on the merits. If the district court finds the Scope 3 requirement non-severable, it could also enjoin Scope 1 and 2 reporting.4 Background SB 253 (the Climate Corporate Data Accountability Act) requires U.S.-formed entities with total annual revenues above $1 billion that do business in California to report Scope 1 and 2 emissions starting in 2026 and Scope 3 emissions starting in 2027, with penalties of up to $500,000 per reporting year.5 SB 261 (the Climate-Related Financial Risk Act) requires U.S.-formed entities with total annual revenues above $500 million that do business in California to publish biennial climate-related financial risk reports consistent with the Task Force on Climate-related Financial Disclosures (TCFD) framework, with penalties of up to $50,000 per reporting year.6 Business groups led by the U.S. Chamber of Commerce challenged both laws as compelled speech that violates the First Amendment. In August 2025, the district court denied their motions for preliminary injunctions. On November 18, 2025, the Ninth Circuit enjoined SB 261 pending appeal but declined to enjoin SB 253.7 The implementing regulation adopted by the California Air Resources Board (CARB) took effect on October 12, 2026, and set November 10, 2026, as the first Scope 1 and 2 reporting deadline.8 The Court’s Decision Scope 1 and Scope 2: Upheld for Now The panel held that Scope 1 and 2 disclosures are commercial speech because they compel disclosure of factual information about emissions from a company’s own operations and purchased energy—information that bears on capital transactions. Applying intermediate scrutiny, the court concluded that the requirements advance California’s substantial interests in reducing information asymmetries for investors and in reducing emissions and are no more extensive than necessary.9 The panel split 2–1 on this issue.10 Scope 3: Likely Unconstitutional The court held that Scope 3 disclosures concern diffuse third-party conduct across the value chain and are “insufficiently tethered” to the reporting entity’s own operations to qualify as commercial speech. Applying strict scrutiny, the court concluded that the requirement likely fails because (1) SB 253 does not require primary data, (2) the record did not show that companies’ proxy-based estimates would be more reliable than estimates the State could generate itself, and (3) the link to investor-relevant risk was too remote.11 SB 261: Likely Unconstitutional in Its Entirety The court held that SB 261 compels noncommercial speech because it requires “predictive and normative judgments” about a “politically fraught subject.” Even assuming California’s interests are compelling, the court reasoned that the law is likely not narrowly tailored because California could use less restrictive alternatives, such as incentives for voluntary disclosure.12 The panel was unanimous on Scope 3 and SB 261.13 Remand and Severability The Ninth Circuit did not enter injunctions itself. It reversed the denials of preliminary injunctive relief and remanded with instructions for the district court to enter relief consistent with the opinion and, for Scope 3, to decide severability first.14 SB 253 contains an express severability clause. If the district court nevertheless finds the Scope 3 requirement non-severable, it could also enjoin Scope 1 and 2 reporting.15 Current Status at a Glance Requirement Status after the Ruling Practical Effect SB 253 – Scope 1 and 2 emissions (entities with revenues above $1 billion) In effect; denial of preliminary injunction affirmed First reports were due November 10, 2026; CARB fee notices expected by December 10, 202616 SB 253 – Scope 3 emissions (scheduled to begin in 2027) Likely unconstitutional; remanded for severability ruling and entry of injunctive relief Not required while remand is pending; scope of CARB’s 2027 rulemaking uncertain17 SB 261 – climate-related financial risk reports (entities with revenues above $500 million) Likely unconstitutional in its entirety; enjoined pending appeal since November 18, 2025 No current reporting obligation; voluntary reports permitted18 What to Watch Any petition for panel rehearing or rehearing en banc (due 14 days after entry of judgment) and any petition for a writ of certiorari to the U.S. Supreme Court.19 The district court’s severability ruling and the scope of any preliminary injunctions it enters as to Scope 3 and SB 261.20 CARB’s response. As of the date of this alert, CARB has not issued a formal statement on the opinion.21 CARB had been developing a second rulemaking for reporting years 2027 and later, addressing Scope 3, assurance, deadlines, and reporting templates, and had proposed retaining November 10 as the annual deadline.​​​​​​​22 Recommended Actions Confirm coverage entity by entity. Revenue (gross receipts, based on the lesser of the two prior fiscal years) and “doing business in California” are determined separately for each entity; affiliates are not aggregated. Retain supporting California tax records for five years.23 If a covered entity has not filed, file promptly. Submit the Scope 1 and 2 report (or, if eligible, a statement of non-reporting) and document good-faith compliance efforts, which CARB must consider in assessing penalties.24 Calendar the fee cycle. CARB expects to issue fee notices by December 10, 2026, with payment due within 60 days after the notice; each day of nonpayment is a separate violation.​​​​​​​25 CARB’s August 2025 proposal set flat fees at $3,106 per SB 253 entity and $1,403 per SB 261 entity.26 Confirm the final amount when the CARB notice arrives. Prepare for 2027 Scope 1 and 2 reporting. Third-party assurance was not required for 2026, but CARB has signaled that it will require limited assurance of Scope 1 and 2 data for 2027 and later years.27 Engage assurance providers and strengthen internal data controls now. Pause, but preserve, Scope 3 and SB 261 workstreams. Maintain existing data and processes: the ruling is preliminary, and many multinational companies will still need Scope 3 and product-level emissions data under the EU’s Corporate Sustainability Reporting Directive (CSRD) and Carbon Border Adjustment Mechanism (CBAM).28 Companies may still publish SB 261 reports voluntarily.29 Review public statements. Continue to review voluntary climate disclosures for consistency with CARB filings and other regulatory reports. Considerations for Real Estate and Infrastructure Clients The following are practice recommendations, not statutory requirements: Control boundaries. Whether emissions from a building or data center fall within a landlord’s or a tenant’s Scope 1 or 2 inventory depends on the control approach applied under the GHG Protocol. Leases, colocation agreements, and powered-shell arrangements should specify which party has operational control for GHG reporting purposes. Data cooperation. Include obligations to deliver utility and energy data (with specified timing and format) and to cooperate with assurance providers, particularly where the landlord or operator holds the utility accounts. Transactions. In acquisitions and financings, diligence the target’s or borrower’s SB 253 compliance and fee payments, and consider representations and covenants on the accuracy of emissions data. Value-chain requests. Counterparty requests for Scope 3 data may slow, but those subject to CSRD will likely continue to make them. This alert is for general information only and is not legal advice. The law in this area is changing rapidly, and developments after November 18, 2026, may affect this analysis.  1 Chamber of Commerce v. Sanchez, No. 25-5327 (9th Cir. Nov. 9, 2026) 2 White & Case, California Climate Disclosure Laws: Ninth Circuit Finds SB 253 Scope 3 Requirements and SB 261 Likely Unconstitutional (Nov. 2026) 3 Legal 500, Ninth Circuit Approves California’s Core Carbon Emissions Reporting Rules (Nov. 2026) 4 White & Case, supra note 2. 5 Kirkland & Ellis, Ninth Circuit Rules on California’s Climate Disclosure Laws (Nov. 2026) 6 Simpson Thacher, California Climate Reporting Laws: Ninth Circuit Issues Partial Injunction (Nov. 2025) 7 White & Case, supra note 2. 8 Vinson & Elkins, OAL Approves CARB’s Initial Regulation (Oct. 2026) 9 White & Case, supra note 2. 10 Foley & Lardner, California Climate Disclosure Laws (Nov. 2026) 11 White & Case, supra note 2. 12 Chamber of Commerce, No. 25-5327. 13 Kirkland & Ellis, supra note 5. 14 Troutman Pepper Locke, Ninth Circuit Rules on Challenge to California’s Climate Disclosure Laws (Nov. 2026) 15 White & Case, supra note 2. 16 Davis Polk, Getting Ready for California SB 253’s November 10 Reporting Deadline (Oct. 2026) 17 Troutman Pepper Locke, supra note 14. 18 White & Case, supra note 2. 19 Id. 20 Troutman Pepper Locke, supra note 14. 21 Morgan Lewis, Ninth Circuit Reverses Lower Court (Nov. 2026) 22 Simpson Thacher, CARB Provides New Guidance on SB 253 Reporting (July 2026) 23 Davis Polk, supra note 16. 24 Id. 25 Id. 26 CARB, SB 253/261 Public Workshop Slides (Aug. 2025) 27 Vinson & Elkins, supra note 8. 28 O’Melveny, Is Your Company Still Required to Report Under California’s Climate Laws? (Nov. 2026) 29 White & Case, supra note 2.

News

Dorsey Practices and Attorneys Recognized by Legal 500 Greater China 2027

Legal 500 Greater China 2027 recognized Dorsey & Whitney LLP in five practice areas across China (Mainland) and Hong Kong SAR and recommended six Dorsey attorneys. The Firm’s litigation practice in China advanced from Tier 4 to Tier 3 among foreign firms. Dorsey received the following practice recognitions in the 2027 edition: China — Leading Firm: Dispute Resolution: Litigation (Foreign Firms) China — Leading Firm: Insurance (Foreign Firms) China — Leading Firm: Regulatory/Compliance (Foreign Firms) Hong Kong — Leading Firm: Intellectual Property Hong Kong — Firms to Watch: Capital Markets (Equity) Leading Firm in China for Dispute Resolution: Litigation (Foreign Firms) Recommended Lawyers: Ray Liu and Janet Wong Dorsey’s litigation team excels in managing high-stake China-related cross-border disputes and legal proceedings in the United States, Hong Kong, Europe, and other jurisdictions. Its work spans an extensive array of industries including banking and finance, insurance, TMT, manufacturing, biotechnology, and life sciences. The improved ranking this year highlights the continued market recognition, the strength of our team, the quality of our client service, and our continued commitment to deliver exceptional results. Leading Firm in China for Insurance (Foreign Firms) Recommended Lawyer: Ray Liu Dorsey’s Beijing-based insurance team works with colleagues in the United States and Europe on a broad range of insurance-related disputes, with a particular focus on general liability and product liability litigation. The team also frequently advises on war risk insurance, all-risk insurance, insurance regulatory matters, and reinsurance issues, and assists major Chinese insurance companies with outbound investments, and regulatory compliance related disputes. Leading Firm in China for Regulatory/Compliance (Foreign Firms) Recommended Lawyers: Ray Liu and Karen Yiqin Fan Dorsey’s China team regularly advises on export controls, economic sanctions, national security/CFIUS, trade compliance, capital markets, and financial regulatory compliance. The team also counsels clients on data privacy, employment compliance, corporate investigations, and foreign entity of concern (FEOC) requirements under the Inflation Reduction Act (IRA) and the One Big Beautiful Bill Act (OBBBA). Leading Firm in Hong Kong for Intellectual Property Recommended Lawyers: Janet Wong and Lilian Shi Dorsey’s Greater China IP team advises multinational and local clients on the protection, management, enforcement, and commercialization of intellectual property assets across Greater China and globally. The team develops and manages global IP portfolios, advises on brand protection and anti-counterfeiting strategies, and handles contentious IP matters, including trademark infringement, copyright, trade secret, company name, and domain name disputes. The team also advises on IP-related transactions and commercialization, including IP due diligence, acquisitions and divestitures of IP rights, technology transfers, licensing and franchising arrangements, and supply, distribution, and manufacturing arrangements. Firms to Watch in Hong Kong for Capital Markets (Equity) Recommended Lawyers: Rachel Han and Megan Penick Dorsey’s Hong Kong and U.S. capital markets teams work seamlessly together on initial public offerings and placings in Hong Kong, along with initial public offerings, follow-on and secondary offerings, cross-border financings, and PIPE investments in the United States, and transactions in other international financial centers. The team also advises listed companies on ongoing compliance and regulatory matters in both Hong Kong and the United States. Drawing on Dorsey’s multidisciplinary capabilities, the Hong Kong capital markets team provides complementary advice on international sanctions and U.S. export control regulations.