Welcome to Dorsey’s Energy Law: Month in Review. We provide this update to our clients to identify significant developments in the previous month. Please reach out to any of the authors, listed above, to discuss these issues. 

Table of Contents

LITIGATION AND DISPUTES

United States Sues SoCal Edison for Negligence in 2019 Saddleridge Wildfire
On October 7, 2025, the federal government sued Southern California Edison (SoCal Edison) for allegedly causing the 2019 Saddleridge Fire in Los Angeles County, California. The complaint alleges that the utility’s negligent maintenance of its powerlines caused a transmission tower to fail and an attached powerline to fall onto a lower arm of the tower, resulting in a wildfire that damaged over 800 acres of federal land and miles of U.S. Forest Service roads, among other damages to the Angeles National Forest System. The U.S. Attorney’s Office for the Central District of California brought this suit and similar suits filed last month seeking a combined $77 million in damages for alleged negligence related to the 2022 Fairview Fire and 2025 Eaton Fire.

Michigan Appeals Court Vacates Solar Farm Permit in Macon Township
A subsidiary of Invenergy, Mustang Mile Solar Energy LLC, recently applied for a special use permit and amendment to a zoning ordinance for its proposed industrial-scale solar farm in Michigan. The local advisory planning commission concluded the project’s site plan failed to meet all zoning ordinance standards, but the Macon Township Board of Trustees rejected the planning commission’s recommendation. Landowners challenged the zoning ordinance changes and permit issuance. On review, a Michigan district court, the Lenawee Circuit Court, affirmed the township’s decision. But on October 6, 2025, the Michigan Court of Appeals reversed. The appeals court vacated the special use permit. The court explained that the district court had incorrectly concluded that the advisory planning commission had recommended approving the permit, when in fact it had not. The court also concluded that the township board failed to sufficiently explain its decision and to reconcile its decision with the planning commission’s recommendation. Concurrently, the appeals court issued a separate decision upholding amendments that Macon Township had made to its zoning ordinance.

REGULATORY DEVELOPMENTS

Senate Confirms FERC Republican Nominees David LaCerte and Laura Swett; Trump Taps Swett as FERC Chair
The U.S. Senate recently confirmed President Donald Trump’s Republican selections for the Federal Energy Regulatory Commission (FERC): Laura Swett and David LaCerte. Swett was most recently energy regulatory counsel at Vinson & Elkins LLP and previously served as senior legal and policy advisor to former FERC Chairman Kevin McIntyre and Commissioner Bernard McNamee. Her term will expire June 30, 2030. LaCerte was principal White House liaison, senior advisor to the Office of Personnel Management director, and special counsel at Baker Botts LLP. His term will expire June 30, 2026. The new confirmations give FERC a full complement of five commissioners and Republicans a 3-2 majority. 

Of the confirmed nominees, Trump has tapped Swett as the new FERC Chair. Swett would replace David Rosner, a Democrat whom Trump named acting chair in August following the departure of former Chairman Mark Christie. Commenting on agency independence at the confirmation hearings, Swett stated that FERC’s independence “is exactly what Congress directed” when it moved the agency out of the U.S. Department of Energy (DOE)’s jurisdiction in 1977, and that she “will not exceed the jurisdiction that Congress has given the agency.” 

Minnesota PUC Approves $6.2 billion Private Equity Sale of Allete 
On October 3, 2025, the Minnesota Public Utilities Commission (MPUC) approved a $6.2 billion sale of ALLETE, Inc., to BlackRock’s subsidiary Global Infrastructure Partners, and a Canadian pension fund, the Canada Pension Plan Investment Board. ALLETE argued in its application for approval of the sale that it needed financing for aging infrastructure and to transition to a carbon-free energy system, particularly to replace two coal-fired units Minnesota Power plans to retire. According to ALLETE, the deal will bring about $200 million in ratepayer benefits. An Administrative Law Judge recommended denying the approval, citing the risks to ratepayers and ALLETE’s long-term financial health. But the Commission found the deal in the public interest due in part to several “unprecedented” conditions. Such conditions include requiring investors to fund Allete’s $5 billion, 5-year capital plan and provide $50 million for firm clean power. Allete also agreed to freeze its base rates for a year, reduce its Return on Equity (ROE) until the utility’s next rate case, and to cap ROE at 9.78% through 2030.

FERC Directs MISO to Better Analyze Merchant Transmission Projects like Grain Belt Express


On October 16, 2025, FERC partially granted Invenergy Transmission LLC (Invenergy)’s complaint against the Midcontinent Independent System Operator, Inc. (MISO), regarding development of Invenergy’s Grain Belt Express (GBX), Docket No. EL22-83-000. The project is an approximately 800-mile high-voltage direct current (HVDC) transmission line spanning Kansas, Missouri, Illinois and Indiana, that will add around 5,000-MW of U.S. energy delivery capacity. But the GBX has faced significant legal and political challenges; just three months ago, the DOE pulled a $4.9 billion conditional loan guarantee slated for the project. Invenergy’s complaint at FERC argued that MISO did not properly implement its rules when it rejected the company’s bid to have the GBX considered in MISO’s two most recent tranches of transmission projects under the MISO Transmission Expansion Plan (MTEP), and that MISO’s tariff—the Open Access Transmission, Energy and Operating Reserve Markets Tariff—is insufficiently clear as to how and when it incorporates merchant transmission projects into planning models. FERC’s order directs MISO to better account for merchant transmission projects like GBX in its grid expansion planning process; however, FERC denied the complaint in part, concluding that Invenergy had not met its burden of demonstrating why MISO’s tariff and MTEP analyses are unreasonable and unjust.

FERC Rejects NV Energy Plan to Allow Penalty-Free Withdrawal from Interconnection Queue

On October 20, 2025, FERC rejected NV Energy’s request for permission to let pending interconnection customers withdraw their interconnection requests without paying a penalty and with immediate return of their commercial deposit. NV Energy had requested the waiver to remove projects from its interconnection queue rendered unviable because of the Trump administration’s revocation of certain clean energy tax credits. The withdrawals would also make way for other resource types. In mid-October, NV Energy had 69 projects totaling about 23.1-GW in its interconnection queue, with geothermal projects growing 30% in the last three months. FERC concluded the waiver was “not limited in scope because it is not limited to a discrete number of interconnection customers with a demonstrated need for relief.” 

DOE Cancels $700M in Battery and Manufacturing Project Grants 

The DOE’s Office of Manufacturing and Energy Supply Chains canceled over $700M in battery and manufacturing project grants this month. The battery grant cancellations are part of the agency’s larger cancellation of $7.6 billion in funding for clean energy projects. DOE based the cancellations on the failure of the battery projects to “adequately advance the nation’s energy needs,” align with the Congressional budget framework, and generally provide a return on investment. Developers affected by the grant recessions likely include ICL Specialty Products, which had received a $197 million grant for a new battery plant in St. Louis, Missouri, and American Battery Technology, which had received a $57.7 million grant for its lithium mine and refinery in Esmeralda County, Nevada, among others. 

Groups Challenge MISO Cost Allocation Plan for Running Coal-Fired Power Plant Past its Retirement Date 

The 1,560-MW coal-fired J.H. Campbell plant in West Olive, Michigan, is facing legal and regulatory hurdles as it continues to run past its retirement date. Using its powers under the Federal Power Act and citing the need for capacity retention and resource adequacy, the DOE ordered the Campbell power plant’s continued operation for a 90-day energy emergency in May of this year. In August, FERC approved MISO’s preliminary cost-recovery plan for the owners of the Campbell power plant to recover their compliance costs associated with the extended emergency operations; the Campbell power plant owners themselves have not yet asked to recover costs. FERC is now facing a final decision on MISO’s cost-recovery plan itself, Docket No. EL25-90. Industrial, business and environmental groups argued this month that FERC should reject the plan because ratepayers should not have to bear the cost of DOE’s decision to continue operating a coal-fired power plant; a demand-based, instead of an energy-based load ratio as MISO has proposed, would better comport with cost-causation principles.

West Virginia PSC Says Pole Owners Must Replace Old Utility Poles 

The West Virginia Public Service Commission (WVPSC) recently got ahead of the pole-replacement debate—an issue concurrently before the Federal Communications Commission—and declared it is the sole responsibility of the pole owner, “not the responsibility of the attaching company,” to pay for pole replacement. The WVPSC is concerned about the timely completion of broadband expansion projects in the state that are funded in part by federal funds limited to particular fiscal years of spending. Utility poles that have been “red tagged” for replacement in West Virginia must now be replaced by whoever owns them, not the utility that is paying to use them.

PUC of Texas Approves Entergy’s 500-kV SETEX Transmission Project

On October 2, 2025, the Public Utility Commission of Texas (PUCT) approved the route and authorized Entergy Texas to move forward with its Southeast Texas Area Reliability Project (SETEX). SETEX is a 145-mile, 500-kV transmission line that will cross Lake Livingston and is estimated to cost $1.4 billion. The selected route had the lowest estimated cost and affected the fewest number of habitable structures. At the same hearing, the PUCT also selected six projects to receive $381 million from the Texas Energy Fund’s Outside ERCOT Grant Program. The goal of these projects is to harden transmission and distribution lines to build reliability and resiliency in response to extreme weather events. 

California Governor Newsom Vetoes Energy Bill on Virtual Power Plants 

California Governor Gavin Newsom signed into law several energy bills recently passed by the California legislature, including bipartisan legislation that would extend the state’s cap-and-trade program and enable the Western regional Extended Day-Ahead Market (EDAM). But this month, he vetoed AB 740. The California legislature’s passage of AB 740 would have required the state to adopt a virtual power plant (VPP) deployment plan. Trade and environmental organizations supported the bill, arguing VPPs could save Californians $750 million per year in electricity system costs and provide more than 7,500-MW of energy capacity. Governor Newsom cited financial strains on the state energy commission as the basis for vetoing AB 740.

Firm Highlights

News

Dorsey Practices and Attorneys Recognized by Legal 500 Greater China 2027

Legal 500 Greater China 2027 recognized Dorsey & Whitney LLP in five practice areas across China (Mainland) and Hong Kong SAR and recommended six Dorsey attorneys. The Firm’s litigation practice in China advanced from Tier 4 to Tier 3 among foreign firms. Dorsey received the following practice recognitions in the 2027 edition: China — Leading Firm: Dispute Resolution: Litigation (Foreign Firms) China — Leading Firm: Insurance (Foreign Firms) China — Leading Firm: Regulatory/Compliance (Foreign Firms) Hong Kong — Leading Firm: Intellectual Property Hong Kong — Firms to Watch: Capital Markets (Equity) Leading Firm in China for Dispute Resolution: Litigation (Foreign Firms) Recommended Lawyers: Ray Liu and Janet Wong Dorsey’s litigation team excels in managing high-stake China-related cross-border disputes and legal proceedings in the United States, Hong Kong, Europe, and other jurisdictions. Its work spans an extensive array of industries including banking and finance, insurance, TMT, manufacturing, biotechnology, and life sciences. The improved ranking this year highlights the continued market recognition, the strength of our team, the quality of our client service, and our continued commitment to deliver exceptional results. Leading Firm in China for Insurance (Foreign Firms) Recommended Lawyer: Ray Liu Dorsey’s Beijing-based insurance team works with colleagues in the United States and Europe on a broad range of insurance-related disputes, with a particular focus on general liability and product liability litigation. The team also frequently advises on war risk insurance, all-risk insurance, insurance regulatory matters, and reinsurance issues, and assists major Chinese insurance companies with outbound investments, and regulatory compliance related disputes. Leading Firm in China for Regulatory/Compliance (Foreign Firms) Recommended Lawyers: Ray Liu and Karen Yiqin Fan Dorsey’s China team regularly advises on export controls, economic sanctions, national security/CFIUS, trade compliance, capital markets, and financial regulatory compliance. The team also counsels clients on data privacy, employment compliance, corporate investigations, and foreign entity of concern (FEOC) requirements under the Inflation Reduction Act (IRA) and the One Big Beautiful Bill Act (OBBBA). Leading Firm in Hong Kong for Intellectual Property Recommended Lawyers: Janet Wong and Lilian Shi Dorsey’s Greater China IP team advises multinational and local clients on the protection, management, enforcement, and commercialization of intellectual property assets across Greater China and globally. The team develops and manages global IP portfolios, advises on brand protection and anti-counterfeiting strategies, and handles contentious IP matters, including trademark infringement, copyright, trade secret, company name, and domain name disputes. The team also advises on IP-related transactions and commercialization, including IP due diligence, acquisitions and divestitures of IP rights, technology transfers, licensing and franchising arrangements, and supply, distribution, and manufacturing arrangements. Firms to Watch in Hong Kong for Capital Markets (Equity) Recommended Lawyers: Rachel Han and Megan Penick Dorsey’s Hong Kong and U.S. capital markets teams work seamlessly together on initial public offerings and placings in Hong Kong, along with initial public offerings, follow-on and secondary offerings, cross-border financings, and PIPE investments in the United States, and transactions in other international financial centers. The team also advises listed companies on ongoing compliance and regulatory matters in both Hong Kong and the United States. Drawing on Dorsey’s multidisciplinary capabilities, the Hong Kong capital markets team provides complementary advice on international sanctions and U.S. export control regulations.

Insights

Ninth Circuit Splits California’s Climate Disclosure Laws: Scope 1 and 2 Reporting Proceeds; Scope 3 and SB 261 Likely Unconstitutional

Key Takeaways On November 9, 2026, the Ninth Circuit in Chamber of Commerce v. Sanchez allowed Scope 1 and Scope 2 greenhouse gas (GHG) emissions reporting under SB 253 to proceed but held that SB 253’s Scope 3 requirement, and SB 261 in its entirety, likely violate the First Amendment.1 U.S.-formed entities with total annual revenues above $1 billion that do business in California remain subject to Scope 1 and 2 reporting. First reports (or, for eligible entities, statements of non-reporting) were due November 10, 2026.2 Scope 3 reporting (scheduled to begin in 2027) and SB 261 climate-risk reporting are effectively on hold. Entities with revenues between $500 million and $1 billion, which were covered only by SB 261, currently have no reporting obligation under either law.3 The ruling addresses only preliminary injunctive relief; it is not a final judgment on the merits. If the district court finds the Scope 3 requirement non-severable, it could also enjoin Scope 1 and 2 reporting.4 Background SB 253 (the Climate Corporate Data Accountability Act) requires U.S.-formed entities with total annual revenues above $1 billion that do business in California to report Scope 1 and 2 emissions starting in 2026 and Scope 3 emissions starting in 2027, with penalties of up to $500,000 per reporting year.5 SB 261 (the Climate-Related Financial Risk Act) requires U.S.-formed entities with total annual revenues above $500 million that do business in California to publish biennial climate-related financial risk reports consistent with the Task Force on Climate-related Financial Disclosures (TCFD) framework, with penalties of up to $50,000 per reporting year.6 Business groups led by the U.S. Chamber of Commerce challenged both laws as compelled speech that violates the First Amendment. In August 2025, the district court denied their motions for preliminary injunctions. On November 18, 2025, the Ninth Circuit enjoined SB 261 pending appeal but declined to enjoin SB 253.7 The implementing regulation adopted by the California Air Resources Board (CARB) took effect on October 12, 2026, and set November 10, 2026, as the first Scope 1 and 2 reporting deadline.8 The Court’s Decision Scope 1 and Scope 2: Upheld for Now The panel held that Scope 1 and 2 disclosures are commercial speech because they compel disclosure of factual information about emissions from a company’s own operations and purchased energy—information that bears on capital transactions. Applying intermediate scrutiny, the court concluded that the requirements advance California’s substantial interests in reducing information asymmetries for investors and in reducing emissions and are no more extensive than necessary.9 The panel split 2–1 on this issue.10 Scope 3: Likely Unconstitutional The court held that Scope 3 disclosures concern diffuse third-party conduct across the value chain and are “insufficiently tethered” to the reporting entity’s own operations to qualify as commercial speech. Applying strict scrutiny, the court concluded that the requirement likely fails because (1) SB 253 does not require primary data, (2) the record did not show that companies’ proxy-based estimates would be more reliable than estimates the State could generate itself, and (3) the link to investor-relevant risk was too remote.11 SB 261: Likely Unconstitutional in Its Entirety The court held that SB 261 compels noncommercial speech because it requires “predictive and normative judgments” about a “politically fraught subject.” Even assuming California’s interests are compelling, the court reasoned that the law is likely not narrowly tailored because California could use less restrictive alternatives, such as incentives for voluntary disclosure.12 The panel was unanimous on Scope 3 and SB 261.13 Remand and Severability The Ninth Circuit did not enter injunctions itself. It reversed the denials of preliminary injunctive relief and remanded with instructions for the district court to enter relief consistent with the opinion and, for Scope 3, to decide severability first.14 SB 253 contains an express severability clause. If the district court nevertheless finds the Scope 3 requirement non-severable, it could also enjoin Scope 1 and 2 reporting.15 Current Status at a Glance Requirement Status after the Ruling Practical Effect SB 253 – Scope 1 and 2 emissions (entities with revenues above $1 billion) In effect; denial of preliminary injunction affirmed First reports were due November 10, 2026; CARB fee notices expected by December 10, 202616 SB 253 – Scope 3 emissions (scheduled to begin in 2027) Likely unconstitutional; remanded for severability ruling and entry of injunctive relief Not required while remand is pending; scope of CARB’s 2027 rulemaking uncertain17 SB 261 – climate-related financial risk reports (entities with revenues above $500 million) Likely unconstitutional in its entirety; enjoined pending appeal since November 18, 2025 No current reporting obligation; voluntary reports permitted18 What to Watch Any petition for panel rehearing or rehearing en banc (due 14 days after entry of judgment) and any petition for a writ of certiorari to the U.S. Supreme Court.19 The district court’s severability ruling and the scope of any preliminary injunctions it enters as to Scope 3 and SB 261.20 CARB’s response. As of the date of this alert, CARB has not issued a formal statement on the opinion.21 CARB had been developing a second rulemaking for reporting years 2027 and later, addressing Scope 3, assurance, deadlines, and reporting templates, and had proposed retaining November 10 as the annual deadline.​​​​​​​22 Recommended Actions Confirm coverage entity by entity. Revenue (gross receipts, based on the lesser of the two prior fiscal years) and “doing business in California” are determined separately for each entity; affiliates are not aggregated. Retain supporting California tax records for five years.23 If a covered entity has not filed, file promptly. Submit the Scope 1 and 2 report (or, if eligible, a statement of non-reporting) and document good-faith compliance efforts, which CARB must consider in assessing penalties.24 Calendar the fee cycle. CARB expects to issue fee notices by December 10, 2026, with payment due within 60 days after the notice; each day of nonpayment is a separate violation.​​​​​​​25 CARB’s August 2025 proposal set flat fees at $3,106 per SB 253 entity and $1,403 per SB 261 entity.26 Confirm the final amount when the CARB notice arrives. Prepare for 2027 Scope 1 and 2 reporting. Third-party assurance was not required for 2026, but CARB has signaled that it will require limited assurance of Scope 1 and 2 data for 2027 and later years.27 Engage assurance providers and strengthen internal data controls now. Pause, but preserve, Scope 3 and SB 261 workstreams. Maintain existing data and processes: the ruling is preliminary, and many multinational companies will still need Scope 3 and product-level emissions data under the EU’s Corporate Sustainability Reporting Directive (CSRD) and Carbon Border Adjustment Mechanism (CBAM).28 Companies may still publish SB 261 reports voluntarily.29 Review public statements. Continue to review voluntary climate disclosures for consistency with CARB filings and other regulatory reports. Considerations for Real Estate and Infrastructure Clients The following are practice recommendations, not statutory requirements: Control boundaries. Whether emissions from a building or data center fall within a landlord’s or a tenant’s Scope 1 or 2 inventory depends on the control approach applied under the GHG Protocol. Leases, colocation agreements, and powered-shell arrangements should specify which party has operational control for GHG reporting purposes. Data cooperation. Include obligations to deliver utility and energy data (with specified timing and format) and to cooperate with assurance providers, particularly where the landlord or operator holds the utility accounts. Transactions. In acquisitions and financings, diligence the target’s or borrower’s SB 253 compliance and fee payments, and consider representations and covenants on the accuracy of emissions data. Value-chain requests. Counterparty requests for Scope 3 data may slow, but those subject to CSRD will likely continue to make them. This alert is for general information only and is not legal advice. The law in this area is changing rapidly, and developments after November 18, 2026, may affect this analysis.  1 Chamber of Commerce v. Sanchez, No. 25-5327 (9th Cir. Nov. 9, 2026) 2 White & Case, California Climate Disclosure Laws: Ninth Circuit Finds SB 253 Scope 3 Requirements and SB 261 Likely Unconstitutional (Nov. 2026) 3 Legal 500, Ninth Circuit Approves California’s Core Carbon Emissions Reporting Rules (Nov. 2026) 4 White & Case, supra note 2. 5 Kirkland & Ellis, Ninth Circuit Rules on California’s Climate Disclosure Laws (Nov. 2026) 6 Simpson Thacher, California Climate Reporting Laws: Ninth Circuit Issues Partial Injunction (Nov. 2025) 7 White & Case, supra note 2. 8 Vinson & Elkins, OAL Approves CARB’s Initial Regulation (Oct. 2026) 9 White & Case, supra note 2. 10 Foley & Lardner, California Climate Disclosure Laws (Nov. 2026) 11 White & Case, supra note 2. 12 Chamber of Commerce, No. 25-5327. 13 Kirkland & Ellis, supra note 5. 14 Troutman Pepper Locke, Ninth Circuit Rules on Challenge to California’s Climate Disclosure Laws (Nov. 2026) 15 White & Case, supra note 2. 16 Davis Polk, Getting Ready for California SB 253’s November 10 Reporting Deadline (Oct. 2026) 17 Troutman Pepper Locke, supra note 14. 18 White & Case, supra note 2. 19 Id. 20 Troutman Pepper Locke, supra note 14. 21 Morgan Lewis, Ninth Circuit Reverses Lower Court (Nov. 2026) 22 Simpson Thacher, CARB Provides New Guidance on SB 253 Reporting (July 2026) 23 Davis Polk, supra note 16. 24 Id. 25 Id. 26 CARB, SB 253/261 Public Workshop Slides (Aug. 2025) 27 Vinson & Elkins, supra note 8. 28 O’Melveny, Is Your Company Still Required to Report Under California’s Climate Laws? (Nov. 2026) 29 White & Case, supra note 2.