Client Alert

New U.S. Government Review Process Effective March 22 for Information Communications Technology and Services from China, Russia and Other “Foreign Adversaries”

March 25, 2021

by Lawrence Ward, Rhona E. Schmidt, Dave Townsend, and T. Augustine Lo

Download as a PDF

Share this page

On January 19, 2021, one day before the transition to the new Biden Administration, the U.S. Department of Commerce published its interim final regulations (“Regulations”) that will allow the United States to review, block, mitigate, or allow U.S. business transactions relating to any non-U.S.-supplied information communications technology and services (collectively, “ICTS”).  Although the Biden Administration has ordered a temporary halt to review other pending regulations from the Trump Administration, that order did not include the Regulations, which are effective as of March 22.  Given the potentially broad effects of the Regulations on industry, potentially affecting up to 4.5 million U.S. firms by the Commerce Department’s own estimate, many observers had hoped the Biden Administration would at least delay implementation of the Regulations.

Under the Regulations, transactions for ICTS (“ICTS Transactions”) within six categories of products and services (as explained below) and that involve a supplier associated with a “foreign adversary” will be subject to special scrutiny by the Commerce Department and are more likely to result in certain blocking or mitigation measures.  Currently, the named foreign adversaries include China, Cuba, Iran, North Korea, Russia, and the government of Nicolas Maduro in Venezuela (“Maduro Regime”).1  However, the Commerce Department could add more countries to this list.  The Regulations are designed to deter and limit U.S. companies from dealing with any such named foreign adversaries to obtain ICTS.

However, the scope of the Regulations is not limited only to foreign adversaries.  As written, all ICTS Transactions within the six listed categories that involve any foreign interests are “covered” and are potentially subject to U.S. Government review.  This broad scope is consistent with the Commerce Department’s stated goal of addressing all potential risks to critical U.S. communications infrastructure from foreign sources, not just the risks posed by any identified foreign adversaries.  Even if the Commerce Department decides not to take action because a foreign adversary is not involved, the new review process could lead to some delays for certain ICTS Transactions with foreign vendors.  Even though the Regulations are effective as of March 22, 2021, the Regulations will retroactively cover such transactions that were pending, initiated, or completed on or after January 19, 2021.  Because of this broad scope, the Regulations could potentially impact U.S. companies (especially those that act as U.S. Government contractors) who rely on foreign suppliers in telecommunications, software-as-a-service (“SaaS”) products and software development, cloud computing and hosting services, and other ICTS industries.

Recently confirmed Secretary of Commerce Gina Raimondo has not thus far ordered a suspension of the Regulations as of the date of this update.  During her U.S. Senate confirmation hearing, Ms. Raimondo had promised to conduct a thorough review of the Regulations.  That review will now apparently take place concurrently with a broader review of the U.S. ICTS supply chain ordered by President Biden on February 24 under Executive Order 14017.  Given the multiple urgent challenges facing the Biden Administration, however, it is unclear how – and how far the Commerce Department will carry out the Regulations while the promised review is under way.

However, there are early indications that the Biden administration may take the Regulations seriously.  On March 17, the Commerce Department announced that it had issued subpoenas to several Chinese companies for potential review of their ICTS products under the Regulations.

Rationale for Regulations.

In its January 19 publication, the Commerce Department stated the Regulations are necessary to safeguard any ICTS being used in the United States, which is “critical to nearly every aspect of U.S. national security.”  In particular, the Commerce Department cited ICTS supplied from foreign adversaries as potentially creating vulnerabilities to critical U.S. infrastructure, consumer data, healthcare networks and health data, sensitive personal data, and proprietary research and development.  The Commerce Department contended that these potential vulnerabilities, if exploited by foreign adversaries, could undermine the confidentiality, integrity, and security of U.S. person data, allow covert data exfiltration to such foreign adversaries, and undermine the operation and profitability of U.S. businesses and critical infrastructure.

The Commerce Department issued the Regulations under Executive Order 13873 signed by President Trump on May 15, 2019 (“EO 13873”), which we summarized in the eUpdate.  EO 13873 had declared a national emergency relating to ICTS and had authorized the Commerce Department to name foreign adversaries and to take action to block such ICTS transactions or impose mitigating measures on such transactions if the Department assessed that they could undermine or threaten U.S. national security.  EO 13873 was predicated upon the International Emergency Economic Powers Act, the National Emergencies Act, and the President’s authority under the U.S. Constitution.

Foreign Adversaries.

The Regulations expressly define a foreign adversary to be a foreign government or non-government entity that has engaged in long-term patterns of conduct adverse to U.S. national security.  The Regulations also state that the U.S. Government considers China, Cuba, Iran, North Korea, Russia, and the Maduro Regime in Venezuela to be such foreign adversaries.  The Commerce Department can also designate additional foreign adversaries in the future based on information from U.S. intelligence, law enforcement, and national security agencies.

ICTS Transactions with any entity owned, controlled by, or subject to the jurisdiction of any such foreign adversary will be subject to heightened U.S. Government scrutiny under the Regulations.  Such official scrutiny will extend to any of the following entities or individuals associated with a foreign adversary:

  • Any person, wherever located, who acts as an agent, representative, or employee, or any person who acts in any other capacity at the order, request, or under the direction or control, of a foreign adversary or of a person whose activities are directly or indirectly supervised, directed, controlled, financed, or subsidized in whole or in majority part by a foreign adversary;
  • Any person, wherever located, who is a citizen or resident of a nation-state controlled by a foreign adversary;
  • Any corporation, partnership, association, or other organization organized under the laws of a nation-state controlled by a foreign adversary; or
  • Any corporation, partnership, association, or other organization, wherever organized or doing business, that is owned or controlled by a foreign adversary

Covered ICTS Transactions.

The scope of the Regulations turns on several broadly defined terms.  The Regulations will generally cover any ICTS Transaction that: (a) is pending, initiated, or completed on or after January 19, 2021; (b) has a U.S. nexus, (c) involves “any property in which any foreign country or a national thereof has an interest;” and (d) falls under one of six classes of such ICTS Transactions, as detailed below (each a “Covered ICTS Transaction”).  Transactions that are intended to evade or avoid EO 13873 also are subject to the Regulations.

Under the Regulations, “ICTS” includes any hardware, software, or other product or service, including cloud-computing services, primarily intended to fulfill or enable the function of information or data processing, storage, retrieval, or communication by electronic means (including electromagnetic, magnetic, and photonic), including through transmission, storage, or display.  Further, under the regulations, “ICTS Transactions” include “any acquisition, importation, transfer, installation, dealing in, or use of any [ICTS], including ongoing activities, such as managed services, data transmission, software updates, repairs, or the platforming or data hosting of applications for consumer download.”

Under the Regulations, the six classes of goods and services are as follows:

Critical Infrastructure.  ICTS used in critical infrastructure as identified in Presidential Policy Directive 21 – Critical Infrastructure Security and Resilience (2013).

Network Infrastructure.  ICTS that are “integral” to networks and network infrastructure, including wireless local area networks (“WLAN”), mobile networks, cable, core networking systems, and satellite payloads and operation.

Sensitive Personal Data.  ICTS that involve sensitive personal data of over one million U.S. persons at any point during the 12-month period before the ICTS Transaction, including internet hosting services and cloud based computing and storage.

Widely Distributed ICTS Hardware.  Internet-enabled cameras or monitoring systems, home networking devices, routers, modems, and drones, if more than one million units have been sold to U.S. persons over the 12-month period before the ICTS Transaction.

Software for Widely Distributed ICTS Products.  Software for Internet-based connection and communications that had over one million U.S. users at any point during the 12-month period before the ICTS Transaction, including desktop applications, mobile applications, gaming applications, and web-based applications.

Emerging Technologies.  ICTS involving the following: artificial intelligence and machine learning, quantum key distribution, quantum computing, drones, autonomous systems, or advanced robotics.

The Commerce Department said that the Regulations do not provide categorical exemptions from the scope of covered ICTS Transactions because broader coverage should better mitigate the potential risks to U.S. national security posed by ICTS Transactions.  However, the Regulations do provide some narrow carve-outs to reduce the potential burden on U.S. companies.  First, ICTS Transactions authorized under U.S. Government-industrial security programs are not included.  Second, any ICTS Transaction that is the subject of a pending or completed CFIUS review will not be included (but further ICTS Transactions by the parties after the CFIUS review could still be subject to the Regulations).  Furthermore, in its narrative explanation of the Regulations, the Commerce Department stated as a matter of policy that “ICTS Transactions solely involving personal hardware devices, such as handsets, do not warrant particular scrutiny.”

The Regulations also provide some affirmative examples of certain ICTS Transactions of particular concern.  For example, although a U.S. company may have sourced software from China or Russia in the past, even a mere software update provided on or after January 19, 2021 from those locations “may provide a foreign adversary an opportunity to engage in the types of activities that may threaten U.S. national security.”  Citing this scenario, the Commerce Department justified its decision not to provide any exclusions for ICTS purchased before the Regulations came into effect.

Review Process for Covered ICTS Transactions.

The Regulations create a review process for the Commerce Department to consider and potentially block or impose mitigating measures relating to ICTS Transactions, which generally should be completed within 180 days.  If the Commerce Department finds that a Covered ICTS Transaction “involves ICTS designed, developed, manufactured, or supplied by persons owned by, controlled by, or subject to the jurisdiction or direction of a foreign adversary,” and likely “poses an undue or unacceptable risk” to U.S. national security, the Commerce Department will begin interagency consultations with other U.S. Government agencies.  If the Commerce Department confirms the existence of undue risk to national security and actions are necessary to eliminate or reduce that threat, it will then issue an initial determination setting forth the reasons and proposed prohibition or mitigation measures.  Conversely, if the Commerce Department finds that a Covered ICTS Transaction does not involve a foreign adversary or does not otherwise pose a threat to U.S. national security, it may permit that transaction to move forward.  If there is an adverse initial determination, the affected parties will have 30 days to respond.  The Commerce Department then will conduct a second round of interagency consultations before issuing its final determination.

Under the Regulations, the Commerce Department can draw upon virtually any source of information that it deems appropriate to initiate an ICTS Transaction review and to reach its conclusion as to such transaction’s potential risk to U.S. national security.  The Regulations expressly provide that the Commerce Department may use information obtained from publicly available sources; U.S. intelligence, national security, and other federal agencies; parties to the transaction; U.S. state, local, or tribal governments; and foreign governments.  The Commerce Department is also empowered by the Regulations to require information from the parties to an ICTS Transaction.

In theory, this new Commerce Department review process could have a significant impact on U.S. companies that purchase ICTS from foreign suppliers based in any of the specified foreign adversaries.  However, because of the comprehensive sanctions administered by the Office of Foreign Assets Control (“OFAC”) in the U.S. Department of the Treasury that already bar almost all U.S. person business or importation of “services” from Cuba, Iran, North Korea, or persons controlled by the Maduro Regime in Venezuela, in practical terms, the new Regulations will fall mostly on commercial ICTS Transactions involving ICTS suppliers in two foreign adversary countries, China and Russia.

Licensing of Covered ICTS Transactions.

The January 19 announcement from the Commerce Department also stated that it will issue additional detailed regulations (“Licensing Regulations”) to create a pre-approval licensing process for ICTS Transactions within 60 days of the Regulations.  The stated purpose of such a pre-approval mechanism in the Licensing Regulations is to mitigate the potential legal uncertainties, delays, and risks created by the Regulations for U.S. buyers of foreign-supplied ICTS.  The Commerce Department said that the new process under the Licensing Regulations will be similar to the process used by the Committee on Foreign Investment in the United States (“CFIUS”) to scrutinize foreign acquisitions of or investment in a U.S. business.  Under the CFIUS Regulations in 31 CFR Part 800, parties can voluntarily disclose such a transaction to CFIUS, which then has a limited time to decide to whether to block, alter or allow a proposed acquisition of or investment in a U.S. business to protect U.S. national security interests.

The Licensing Regulations will include criteria by which parties to an ICTS Transaction can seek such licenses from the Commerce Department.  The Licensing Regulations will also create a fixed timeline of not longer than 120 days from acceptance of a license application to a Commerce Department decision on the disclosed transaction.

The strongest case for seeking a license under the Licensing Regulations will probably be a situation involving an ICTS vendor who is based in China or Russia, two of the named foreign adversaries in the Regulations, and where the parties to the transaction want to avoid any risk or uncertainty that the Commerce Department would unilaterally intervene in an ICTS Transaction of considerable value.  By bringing such a transaction directly to the notice of the Commerce Department and triggering a review under the Licensing Regulations at the outset of a notified ICTS Transaction, at least in theory, the parties should be able to preempt such an intervention and avoid any later delay or disruption of that transaction under the Regulations.  However, depending on how broadly the Commerce Department plans to interpret what will be considered Covered ICTS Transactions under the Regulations, there could also potentially be some circumstances to invoke that licensing mechanism even when neither China nor Russia is involved.

Conclusion.

Given their breadth and potentially severe impact on certain transactions, the Regulations are probably going to create a degree of palpable uncertainty for U.S. businesses that rely on global supply chains and foreign outsourcing, particularly in the telecommunications, home devices, and SaaS sectors (e.g., devices that will be connected to one another as part of the “Internet of Things” (“IOT”)).  Because IoT and many other technology sectors are so dependent upon computer software, many U.S. companies have come to rely on specialized outsourcing providers to develop such computer software.  Consequently, the global outsourcing provider industry has grown significantly over the past two decades.  Many of the largest outsourcing providers have substantial U.S. offices but are ultimately owned and controlled by parent entities in countries outside the United States, such as in India, China, Brazil, the Philippines, Russia, and elsewhere in eastern Europe.

A U.S. purchaser of ICTS will probably now need to conduct a new sort of due diligence when it selects any outside ICTS provider, even if that ICTS provider nominally appears to be a U.S. entity (e.g., the U.S. subsidiary of a foreign-based outsourcing parent company).  If the provider’s U.S. office is only serving as a convenient “face” for its foreign-based parent entity, and particularly if the bulk of the ICTS is actually to be provided by personnel of that foreign-based parent entity or any other foreign-based affiliate, a U.S. ICTS purchaser should know about that structure and should then take both that structure and the Regulations into account when considering whether to engage such a foreign-based ICTS provider.

The new Commerce Department review is clearly targeted at any ICTS sourced from China, Russia, and the other named foreign adversaries.  For example, a company that imports Chinese-origin products used for information or IoT communications might need to seek a Commerce Department license, or else it could otherwise risk that the Commerce Department might deem the importation  of such ICTS as being contrary to U.S. national security interests and thus be prohibited.  Likewise, a U.S. company that uses contractors in China or Russia for certain ICTS such as data hosting or software support could face risks under the Regulations.  As with the CFIUS regime, such a U.S. ICTS purchaser may make its business more reliable and predictable either by avoiding the use of such an ICTS supplier in a foreign adversary jurisdiction or, if it has a compelling reason to do so, then by seeking a Commerce Department license under the forthcoming Licensing Regulations. Failure to get such a license would risk that the Commerce Department could instead initiate its own later review and subsequently order an unwinding or reversal of an ICTS Transaction.

Moreover, U.S. ICTS purchasers will likely also want now to review and revise their “boilerplate” force majeure clauses that might now only refer to “export control” and “economic sanctions” laws and regulations.  Here, under the Regulations, the U.S. Government is imposing for the first time controls on the “import” or purchase of ICTS in the United States.  Most  such standard clauses in common U.S. contractual usage have not had to deal with regulatory barriers on “imports” or “services” that could affect dealing with foreign vendors in such a novel way.

Finally, U.S. ICTS purchasers and foreign ICTS vendors will want to watch carefully as the Commerce Department completes its promised review of the Regulations, including the various public comments that have been sent in, and to examine the new proposed Licensing Regulations that should be due out for public comment soon.  U.S. ICTS purchasers also should pay close attention to any further developments with respect to the subpoenas issued to Chinese companies on March 17 under the Regulations.  As they monitor these legal developments, U.S. ICTS purchasers may also want to begin consideration of alternative foreign ICTS vendors who will offer a lower risk profile in terms of potential negative outcomes, such as vendors who are clearly and unequivocally not connected to any of the named foreign adversary countries, most especially to China or Russia.  Foreign ICTS vendors, especially those in the designated foreign adversary countries, will also have to be prepared for more rigorous due diligence requests from their U.S. clients and to be prepared to undergo the Commerce Department’s scrutiny in line with the new Licensing Regulations, much as foreign investors have gradually but firmly adjusted to the reality of CFIUS national security reviews in the case of foreign investments or acquisitions in the United States.

# # # # #

Dorsey & Whitney’s National Security Group can assist companies with reviewing and analyzing the Regulations and, when issued, the Licensing Regulations, and their impact on any proposed ICTS Transaction.  Lawyers in Dorsey’s National Security Group have had decades of experience helping companies with complex national security related matters, including licenses from the Commerce Department and other approvals from CFIUS.


1 Consistent with the U.S. Government’s refusal to recognize Nicolas Maduro as the legitimate president of Venezuela, the Regulations deem the Maduro Regime but not all of Venezuela as a foreign adversary.

 

Firm Highlights

Insights

EPA Limits Title V Re-Litigation of NSR Permits

Overview On September 25, 2026, the U.S. Environmental Protection Agency (“EPA”) published a final rule that significantly limits the ability of third parties to use the Clean Air Act (“CAA”) Title V permitting process to revisit New Source Review (“NSR”) permitting decisions years after those decisions were made. The rule establishes that NSR permitting determinations generally must be challenged during the original permitting proceeding, thereby providing regulated sources with greater permitting certainty and finality for major capital projects. Published in the Federal Register titled Clarifying the Scope of “Applicable Requirements” Under State Operating Permit Programs and the Federal Operating Permit Program (Docket ID No. EPA-HQ-OAR-2023-0401), the rule amends 40 C.F.R. Parts 70 and 71 to codify EPA’s interpretation regarding when requirements established under other CAA programs may be reviewed, modified, or implemented through the Title V operating permit program. The rule becomes effective 30 days after publication. The rule addresses two principal issues: (1) the relationship between NSR preconstruction permitting and Title V operating permits, and (2) the treatment of the General Duty Clause under CAA section 112(r)(1). Most significantly, the rule provides greater certainty for sources navigating the NSR permitting process. EPA’s amendments are intended to ensure that NSR permitting decisions made through an approved public process are generally not revisited later through Title V permit proceedings. The rule responds to a circuit split between the U.S. Courts of Appeals for the Fifth and Tenth Circuits. In Environmental Integrity Project v. EPA, 969 F.3d 529 (5th Cir. 2020), the Fifth Circuit upheld EPA’s interpretation, concluding that it was consistent with the text, structure, and purpose of Title V. In contrast, the Tenth Circuit reached the opposite conclusion in Sierra Club v. EPA, 964 F.3d 882 (10th Cir. 2020), finding that the then-existing regulatory definition of “applicable requirement” did not support EPA’s position. By amending the regulatory language on which the Tenth Circuit relied and codifying the interpretation approved by the Fifth Circuit, EPA has established a nationwide framework governing the interaction between NSR and Title V. NSR and Title V: EPA Establishes a Uniform Nationwide Framework At the core of the rule is EPA’s effort to define the respective roles of NSR and Title V. The rule codifies the approach EPA has applied since 2017: once a source obtains an NSR permit under an EPA-approved permitting program, and that permit was issued following public notice with an opportunity for comment and judicial review, the permit establishes the NSR-related “applicable requirements” of the State Implementation Plan (“SIP”) or Federal Implementation Plan (“FIP”) for Title V purposes. Under this framework, Title V is not a vehicle for re-examining underlying NSR permitting decisions. EPA does not intend to use the Title V process to revisit applicability determinations, emissions calculations, control technology determinations, permit conditions, or other issues resolved through the NSR permitting process. This principle applies regardless of the stage of the Title V proceeding; whether the NSR permit was issued pursuant to a SIP or FIP; the type of NSR issue involved; or whether the NSR permit is incorporated into Title V sequentially or concurrently. Limited Exceptions EPA recognizes several circumstances in which NSR issues may still be reviewed through the Title V program: No NSR permit was issued at all; The permit was issued without public notice and an opportunity for comment and judicial review; or The issue involves substantive overlap between Title V and NSR requirements, such as the adequacy of monitoring provisions. As a result, the rule does not insulate unpermitted projects or foreclose review of matters that independently arise under Title V. Key Regulatory Amendments The rule revises the definition of “applicable requirement” in 40 C.F.R. §§ 70.2 and 71.2. Paragraph (1): Where an NSR permit is issued with public notice and an opportunity for comment and judicial review, the permit establishes and defines the applicable SIP or FIP requirements for Title V purposes. Paragraph (2): All NSR permit terms, including terms contained in minor NSR permits, constitute applicable requirements that must be incorporated into Title V permits. Paragraph (4): CAA section 112(r)(1) (the General Duty Clause) is expressly excluded from the definition of “applicable requirement,” while section 112(r)(7) Risk Management Program requirements remain included. EPA also amended 40 C.F.R. §§ 70.8 and 70.12 to clarify that alleged defects in requirements established outside the Title V process generally do not provide a basis for EPA objection to a Title V permit or for a Title V citizen petition. General Duty Clause Exclusion The rule also codifies EPA’s longstanding position that the General Duty Clause in CAA section 112(r)(1) is not an “applicable requirement” for Title V purposes. EPA points to several considerations supporting that conclusion, including the distinction between the General Duty Clause and Title V permit terms, the provision’s origins in the Occupational Safety and Health Act’s general duty clause, and the different enforcement structures applicable to the General Duty Clause and Title V permit requirements. Importantly, excluding section 112(r)(1) from the definition of “applicable requirement” does not eliminate EPA’s authority to enforce the General Duty Clause independently of the Title V program. The final rule instead clarifies that the General Duty Clause need not—and should not—be incorporated into Title V permits as an applicable requirement. Practical Implications for Regulated Sources Greater Finality for NSR Permits  For projects requiring PSD, nonattainment NSR, or minor NSR permits, the permitting process becomes the primary forum for resolving disputes regarding applicability determinations, emissions calculations, control technology requirements, offsets, and permit conditions. Once an NSR permit is issued through a qualifying public process, regulated sources should face substantially reduced risk that those same issues will be challenged years later through Title V permit proceedings. Reduced Risk of Collateral Permit Challenges Stakeholders have sometimes sought to use Title V permit issuance, renewal, revision, or citizen-petition proceedings to challenge underlying NSR determinations. The final rule makes clear that Title V is not the appropriate vehicle for challenging whether an applicable requirement was correctly established in the first instance. This should reduce the risk of permit delays and uncertainty associated with collateral challenges to previously issued NSR permits. The rule does not, however, eliminate all Title V challenges relating to an NSR permit. Challenges concerning the Title V permit itself—including whether it appropriately incorporates applicable requirements or contains adequate compliance provisions—remain possible. Increased Importance of the Initial NSR Proceeding Because Title V generally will not provide a second opportunity to challenge the substantive validity of an NSR determination, the administrative record developed during the NSR process becomes increasingly important. Permit applicants should ensure that applicability analyses, emissions calculations, control technology evaluations, modeling demonstrations, and supporting technical documentation are thoroughly developed during the original permitting proceeding. For significant projects, applicants may therefore have an additional incentive to identify and resolve potential permitting issues before the NSR permit is issued rather than assuming that unresolved issues can be addressed during a subsequent Title V proceeding. Potential Incentive for Broader Public Participation EPA also notes that permitting authorities may choose to provide public notice and an opportunity for comment for a broader range of NSR permits because permits issued through a qualifying public process receive the benefit of the finality framework established by the rule. Some permitting authorities may conclude that greater public participation at the NSR stage is preferable to uncertainty during subsequent Title V proceedings. Conclusion The final rule is principally a permitting-certainty measure. For sources that obtain NSR permits through a public process, EPA has substantially limited the ability of third parties to revisit underlying NSR determinations through the Title V program. As a result, regulated entities should benefit from greater finality regarding key permitting decisions, reduced risk of collateral permit challenges, and increased certainty when planning and implementing capital projects.

Insights

SEC Proposes Expansion of Investment Adviser Performance-Based Compensation Rule

On September 30, 2026, the Securities and Exchange Commission (the “SEC”) proposed amendments to Rule 205-3 under the Investment Advisers Act of 1940, as amended (the “Advisers Act”), which provides an exemption from the general prohibition under Section 205(a)(1) of the Advisers Act on registered investment advisers receiving performance-based compensation (the “Proposal”) so long as performance-based compensation is limited to “qualified clients”.1 Most notably for private fund sponsors, the Proposal would expand the definition of “qualified client” to include any investors that satisfy the “accredited investor” definition under Regulation D. The Proposal may also have implications for private fund managers that rely on exemptions from investment adviser registration under state law because certain state-level investment adviser registration exemptions incorporate or otherwise reference the federal qualified client definition. Expansion of the Qualified Client Definition Under the current Rule 205-3, an investor generally may qualify as a qualified client if, among other alternatives, the investor has at least $1.4 million under management with the adviser or has a net worth exceeding $2.7 million. These thresholds are higher than the financial thresholds applicable to many accredited investors under Regulation D. As a result, an investor may currently qualify as an accredited investor for purposes of investing in a private offering without qualifying as a qualified client for purposes of paying performance-based compensation. The Proposal would expand the qualified client definition to include any natural person or legal entity investor that satisfies the accredited investor definition under Regulation D. The Proposal would also remove the assets under management and net worth thresholds under the current Rule 205-3 qualified client test. For private funds relying on Section 3(c)(1) of the Investment Company Act of 1940, this change could reduce the need to apply a separate qualified client standard to investors that already qualify as accredited investors. Dorsey Observations and Next Steps If adopted as proposed, the expanded qualified client definition could be particularly significant for private fund managers. Most private fund offerings are already limited to accredited investors under Regulation D. However, the Proposal could expand the pool of prospective investors available to emerging private fund managers while reducing the regulatory burden associated with complying with Rule 205-3. The Proposal could also benefit advisers operating below the SEC registration threshold that rely on a state private fund adviser exemption. A number of states have adopted exemptions modeled on the North American Securities Administrators Association (“NASAA”) private fund adviser exemption, which may condition relief for advisers to certain funds relying on Section 3(c)(1) on each beneficial owner satisfying the federal qualified client definition. However, state requirements vary, and any effect of the Proposal would depend on the text of the applicable state exemption and how it incorporates Rule 205-3. Many emerging private fund managers may have a larger network of accredited investor relationships than qualified client relationships during the early stages of their investment advisory business. Currently, under Rule 205-3, private fund managers may receive performance-based compensation from investors who do not satisfy the qualified client definition if those investors were admitted to their private funds prior to registration with the SEC. Following registration with the SEC, however, managers may continue to permit investors that are not qualified clients to invest in future private funds but may not receive performance-based compensation from those investors with respect to such investments. In addition, because the net worth and assets under management thresholds for qualified client status are adjusted for inflation every five years, the pool of qualified client investors may diminish over time as previously eligible investors no longer satisfy the applicable thresholds. The Proposal could provide the dual benefit of greater flexibility for private fund managers to establish and maintain relationships with accredited investors as their businesses scale and they become registered with the SEC, and greater flexibility for certain accredited investors to participate in investment strategies that historically have been restricted to much larger institutional investors. Unless and until the Proposal is adopted, investment advisers should continue to comply with the existing qualified client requirements. If the Proposal is adopted, private fund sponsors should consider whether corresponding changes are appropriate for their subscription documents, investor questionnaires, and other offering materials. Advisers that are state-registered or rely on a state-level exemption should also consult the laws and regulations of each relevant jurisdiction before changing investor eligibility standards or performance-based compensation practices, because adoption of the federal amendments may not automatically modify state requirements. Comments on the Proposal will be due 60 days after publication in the Federal Register. 1 Investment Adviser Performance-Based Compensation Modernization, Investment Advisers Act Release No. IA-7022 (Sept. 30, 2026), available at https://www.sec.gov/rules-regulations/2026/09/s7-2026-28#33-11443proposed.

Insights

Energy Law: Month in Review - September 2026

Welcome to Dorsey’s Energy Law: Month in Review. We provide this update to our clients to identify significant developments in the previous month. Please reach out to any of the authors, listed above, to discuss these issues. Regulatory Developments Massachusetts Ratchets Up State and Local Regulation of AI Data Centers In early September, Governor Maura Healey of Massachusetts signed an executive order requiring that artificial intelligence data centers secure the approval of local communities as a precondition to proceeding with a given project. According to the terms of the order, data center developers will need to secure a “community benefits agreement” as a precondition to receiving permits from numerous state agencies, including the Department of Environmental Protection, the Energy Facilities Siting Board, and the Massachusetts Environmental Policy Act Office. Beyond requiring community benefits agreements, the order also mandates that developers mitigate utility costs to consumers, prohibits the use of nondisclosure agreements, and requires various state agencies to develop measures to limit data center impacts on the environment. North Carolina Regulators Decline Approval of Duke Energy Gas Turbine On September 18, 2026, North Carolina Utilities Commission (NCUC) denied Duke Energy’s application for a certificate of public convenience and necessity required to construct a gas-fueled combustion turbine at its Smith Energy Complex in North Carolina. The NCUC objected strongly to the $584 million price tag and noted that Duke appeared to be constructing the facility “based on anticipated data center customer additions.” The NCUC rejected that anticipated growth as “insufficiently reliable for the Commission to act at this point.” In rejecting Duke’s application, the NCUC also noted that Duke had signed the White House Ratepayer Protection Pledge, in which it represented that it would not shift data center costs to consumers. The NCUC observed that the record did not demonstrate how Duke “intends to adhere to its commitments under the Ratepayer Protection Pledge with regard to the Proposed Facility.” Notably, commission staff had actually supported the construction of the turbine, citing concerns about Duke’s reserve margins. The NCUC noted that it “understands the Public Staff’s expressed concerns,” but those concerns were outweighed by the NCUC’s reservations, including questions of demand. Department of Energy Approves Funds for Grid Improvement The U.S. Department of Energy (DOE) recently announced that it would fund 31 grid-improvement projects in 26 states. The funding initiative is part of the DOE’s “SPARK” initiative. The funding will include $1.9 billion in federal funding from DOE and $3.35 billion in recipient cost-sharing funding. The funds will go to projects designed to improve grid reliability and lower electricity costs. Recipients plan to reconductor over 1,500 miles of transmission lines and will deploy grid-enhancing technologies across approximately 21,000 miles. DOE stated that this initiative will make available over 23 additional gigawatts of electricity. Texas Moderates Rules Governing Data Center Interconnection The Texas Public Utility Commission adopted new regulations governing large-load interconnections. The rules impose a flat study fee of $100,000 for all proposed interconnections, which departs from the initial proposal to impose study fees using a tiered system based on project size. Additionally, the final rule eliminates the PUC’s previous proposal to impose a non-refundable interconnection fee of $50,000 per MW of contracted peak demand. The final rule also moderates the initially proposed regulations governing Electric Reliability Council of Texas (ERCOT) notifications for large-load customers’ non-utilized capacity. The proposed rules would have required notifying ERCOT within 30 days of missing a scheduled energization milestone by six months. The final rules, however, do not require informing ERCOT unless a scheduled energization milestone is missed by 24 months. FERC Denies TransAlta 202(c) Cost-Recovery Plan The Federal Energy Regulatory Commission (FERC) recently rejected TransAlta’s plan to recover $19.9 million in expenses stemming from a DOE order in which DOE prohibited TransAlta from retiring its coal-powered Centralia power plant. TransAlta had previously intended to retire the facility at the end of 2025. TransAlta’s cost recovery plan proposed spending an additional $23 million on repairs to continue operating the unit. FERC’s main objection had to do with geographic scope. TransAlta’s recovery plan called for recovering costs from California Independent System Operator (CAISO) and the Southwest Power Pool (SPP), but the DOE’s order requiring operation of the plant was designed to ensure reliability in the Northwest assessment area (Montana, Oregon, Washington, and parts of northern California and northern Idaho). Accordingly, FERC was unwilling to allow cost recovery from CAISO and SPP when the order that precipitated the additional costs only related to the Northwest assessment area. FERC informed TransAlta that it would only approve cost recovery from load-serving entities in the Northwest assessment area. FERC’s decision comes amid a rush of DOE emergency orders requiring the continued operation of coal-fired generating units. Litigation Appeals Court Upholds Washington Hydropower Plant With Caveats In a September 21, 2026, opinion, the Washington Court of Appeals largely upheld a Clean Water Act water quality certification by the Washington Department of Ecology for the Goldendale Energy Storage Project, a proposed pumped-water storage hydropower system adjacent to, but off-stream from, the Columbia River. A nonprofit (Columbia Riverkeeper) and the Confederated Tribes and Bands of the Yakama Nation appealed the certification, contending that it failed to impose necessary conditions and monitoring requirements to protect the water quality of the Columbia River. Most saliently, the plaintiffs argued that the project had the potential to leak 100 acre-feet of water per year into tributaries of the Columbia River. The Court of Appeals broadly rejected plaintiffs’ challenge to the state’s conclusion that “the project was designed not to leak.” That said, the Court of Appeals did reverse on one narrow issue. Specifically, the court determined that the state’s conclusion that “leakage from the project’s tunnels would be monitored and reported” was not supported by the evidence because the certification “does not explicitly require monitoring and reporting to determine whether there is any leakage.” Accordingly, the court remanded the matter to the state to impose monitoring and reporting requirements but otherwise affirmed the certification. Legislative Developments California Legislates Restrictions on Data Center Energy Use and Grid Costs On September 21, 2026, California Governor Gavin Newsom signed seven bills broadly regulating data centers in the state. SB 1168 directed the California Public Utilities Commission to assess the energy used by data centers. It also requires the PUC to pass costs of transmission and distribution upgrades and load increases on to data centers, rather than customers. SB 886 and SB 887 compel data centers to pay for infrastructure upgrade and generation costs, and wildfire mitigation costs, in addition to imposing environmental review. The statutes additionally increase local oversight of data centers. AB 1577 imposes a monthly reporting requirement that requires data centers to supply energy consumption and efficiency data to the California Energy Commission. AB 2383 contains incentives for data centers to use onsite clean energy generation. Finally, AB 2469 and AB 2619 require data center developments to assess water supply and develop a water scarcity plan. The statutes also mandate statewide water reporting as a precondition to obtaining and renewing business licenses.

Insights

The Supreme Court Update - October 8, 2026

On September 29, 2026, the Supreme Court granted certiorari in one case: Department of Homeland Security v. D.V.D., No. 26-426: This case concerns the Trump Administration’s “third-country removal” procedures, where immigrants are deported to countries not listed in the removal orders. In granting certiorari, the Court granted the Government’s application to stay a lower court decision halting the practice, which will allow third-country removals to continue pending resolution of the case. The issues presented are: (1) Whether the district court had jurisdiction over respondents’ claims; (2) whether the district court had authority to enter class-wide declaratory relief and APA vacatur under 8 U.S.C. § 1252(f)(1); (3) whether the Government’s guidance on third-country removals is unlawful under 8 U.S.C. § 1231(b), the due process clause, or FARRA/CAT and its implementing regulations; and (4) such other questions that the Government determines are appropriate for the proper disposition of the case. On October 1, 2026, the Court granted certiorari in three additional cases: Rhoney v. Barbosa da Cunha, No. 26-104: Immigration officials detained Ricardo Aparecido Barbosa da Cunha—a Brazilian citizen who had lived in the United States for approximately twenty years after entering without inspection—and denied him a bond hearing under 8 U.S.C. § 1225(b)(2)(A). The Second Circuit held that his detention was instead governed by § 1226(a), which permits release on bond, because § 1225(b)(2)(A)’s mandatory-detention requirement applies only to noncitizens apprehended while entering the country or shortly thereafter. The question presented is: Whether 8 U.S.C. § 1225(b)(2)(A) mandates the detention pending removal proceedings of aliens who, like Barbosa da Cunha, are present in the United States without having been admitted. Missionaries of St. John the Baptist, Inc. v. Frederic, No. 25-113: A Catholic religious organization sought to build a shrine to the Virgin Mary on land the organization owned adjacent to its church in Park Hills, Kentucky. Local zoning restrictions prohibited the proposed construction. The question presented is: Whether a land-use regulation that prohibits a religious institution from building a religious structure on its own property constitutes a “substantial burden” on religious exercise under the Substantial Burden Provision of the Religious Land Use and Institutionalized Persons Act, 42 U.S.C. § 2000cc(a). Marschner v. Marschner, No. 25-1349: Under the Uniformed Services Former Spouses’ Protection Act (“USFSPA”), a veteran’s longevity-based retirement pay can be divided in a divorce, but retirement pay based on disability and retirement pay that was waived to receive disability pay are indivisible. The question presented is: Does the USFSPA require state courts to refuse enforcement of indemnification provisions in a divorce settlement agreement?