Client Alert

Lucia: The End of SEC ALJs?

June 26, 2018

Download as a PDF

Share this page

The Supreme Court resolved the question of whether SEC ALJs must be appointed in accord with the Constitution’s Appointments Clause, holding that their retention is subject to the provision. Thus the Court held that Petitioner Raymond J. Lucia is entitled to a new hearing before a different ALJ appointed in accord with the Constitution. Raymond J. Lucia, vs. Securities and Exchange Commission, No. 17-130 (June 21, 2018). The Court’s ruling leaves unresolved, however, more issues than it resolved concerning the constitutionality of ALJs, the appropriate remedies for a violation of the Clause and ultimately the question which sparked the controversy that resulted in the case – venue selection for SEC enforcement actions. Indeed, in the wake of the Court's decision, the SEC ordered a halt to all of its administrative proceedings for thirty days or until further ordered. The Order was entered on June 23, 2018.

The Court’s opinion

The Court’s ruling is a straight forward application of Frytag v. Commissioner, 501 U.S. 869 (1991).  The Constitution’s Appointments Clause, Article II, §2, Cl. 2, provides that only the President, a court of law, or a head of a department can appoint Officers of the United States.  The question considered by the Court is whether SEC ALJs are Officers within the meaning of the clause.  Those who are must be appointed in accord with the Clause, here by the SEC since it is considered a department head for this purpose.

Two prior decisions by the Court provided the guideposts for resolving this question, according to the opinion authored by Justice Kagan and joined by six other Justices.  First, in U.S. v. Germaine, 99 U.S. 508 (1879) the Court found that civil surgeons – doctors retained to perform certain exams – held “temporary rather than continuing and permanent” positions.  The position must be established by law.  Temporary positions were deemed not sufficient. 

Second, Buckley v. Valeo,  424 U.S. 1 (1976)(per curiam) held that members of a federal commission were Officers within the meaning of the Clause after concluding that they exercised “significant authority” under the laws of the United States.  While the “significant authority” test requires an analysis of the powers exercised by the person and may need refinement as urged by amicus who defended the decision below following the confession of error by the Solicitor General who joined with Petitioner in challenging the ALJ appointment here, that is not required now, according to the Court.  This is because in Frytag  “we applied the unadorned ‘significant authority’ test to adjudicative officials who are near-carbon copies of the Commission’s ALJs.”  Frytag “says everything necessary to decide this case.”  

Frytag considered whether special trial judges at the Tax Court were Officials under the Clause. The authority of those judges was a function of the matter before them.  In major matters, they would preside over the hearing and prepare findings and an opinion for a regular Tax Court judge. The STJs could not issue the final ruling. For other matters the STJs could issue a final ruling.  

The case in Frytag involved a major matter.  The Court held that the STJs were in fact Officers for purposes of the Appointments Clause.  The ruling is based on two key considerations.  First, citing Germaine, the Court found that the positions were established by law and permanent.  Second, following Buckley, the Court concluded that the position requires the exercise of significant authority.  This is because STJs were required to take testimony, conduct trials, rule on the admissibility of evidence and enforce compliance with discovery orders.  Carrying out those obligations requires the exercise of significant authority.  The fact that in the major case before the Court the STJ could not enter the final decision was not dispositive.  Rather, the Court found that STJs were Officers under the Appointments Clause.  Since it is undisputed that SEC ALJs have virtually identical authority, they are Officers and must be appointed in accord with the Clause.  Although there are some differences between the authority of an SEC ALJ and an STJ as amicus argued, they are not significant and do not detract from the conclusion that Frytag resolves this case. 

The appropriate remedy for “an adjudication tainted with an appointments violation is a new ‘hearing before a properly appointed’ official,” the Court concluded.  In this regard, the Court held that the SEC ALJ who presided over the initial hearing cannot conduct the new proceeding even if properly appointed.  This is because the remedies in these cases are designed in part to create incentives for persons to present these challenges and those are aided by directing that a different, properly appointed official, preside at the new hearing.  Accordingly, to “cure the constitutional error, another ALJ (or the Commission itself) must hold the new hearing to which Lucia is entitled.”   The Court declined to consider the validity of the SEC’s November 30, 2017 order that sought to “ratify” the appointment of its ALJs. 

Justice Thomas, joined by Justice Gorsuch, concurred.  In his opinion, the Justice noted that the Court’s opinion discusses what is “sufficient to make someone an officer of the United States, [but] our precedents have never clearly defined what is necessary.” (emphasis original).  “To the Founders, this term [Officer] encompassed all federal civil officials with responsibility for an ongoing statutory duty.”  (Internal citations omitted).   Viewed in this context SEC ALJs “easily qualify as ‘Officers of the United States’ . . . the importance or significance of their statutory duties is irrelevant...”  

Justice Breyer concurred in the judgment but dissented in part in an opinion joined by Justices Ginsburg and Sotomayor.  While Justice Breyer agrees that the SEC did not properly appoint its ALJs, the case should have been resolved on statutory grounds and the constitutional issue avoided since its resolution was unnecessary. 

This case could be resolved by considering the dictates of the Administrative Procedure Act or APA. That statute, enacted in 1946, provided in part that each agency could retain as many Administrative Law Judges as necessary for hearings governed by the Act.  That Act does not provide that the Commission can simply delegate its power to appoint its administrative law judges to the staff.  The APA requires a published order or rule for delegation.  Here the SEC did not publish such an order or rule.  Its effort to delegate the authority to hire ALJs to its staff is thus invalid.

A second reason for avoiding the constitutional issue   stems from the Court’s prior ruling in Free Enterprise Fund v. Public Company Accounting Oversight Board,  561 U.S. 477 (2010).  That case considered the statutory provisions protecting members of the PCAOB from removal without cause.  There the “Court held that the Executive Vesting Clause of the Constitution, Art. II, §1 (‘[t]he executive Power shall be vested in the President of the United States of America’), forbade Congress from providing members of the board with ‘multilevel protections from removal’ by the President,” quoting Free Enterprise Fund, 561 U.S. at 484.  This is because Congress cannot limit the authority of the President by providing two levels of employment protection.   In resolving this question the Court stated that members of the Board are Officers of the United States, although the “significance of that fact to the Court’s analysis is not entirely clear,” according to Justice Breyer.  

The APA also provides protections from removal for ALJs.  Those provisions were viewed as important parts of the APA since they provided them with insulation from the political processes. This is because prior to the Act, hearing officers were subject to their agency which created issues regarding their independence.  

“If the Free Enterprise Fund  Court’s holding applies equally to the administrative law judges – and I stress the ‘if’ – then to hold that the administrative law judges are ‘Officers of the United States’ is, perhaps,  to hold that their removal protections are unconstitutional. This would risk transforming administrative law judges from independent adjudicators into dependent decision makers, serving at the pleasure of the Commission.”   (emphasis original).  At the same time, the Court in Free Enterprise “disagreed [with my dissent stating this point] saying that ‘none of the positions” such as ALJs identified in the dissent are “similarly situated to the Board.”  

Viewed in this context, a holding that ALJs are Officers could come into conflict with the Free Enterprise Fund’s limitation on the “for cause” protections from removal.  In that event, the decision of Congress to provide those protections would be called into question.  Yet under the Appointments Clause Congress’ intent is important.  Its determination on this point would suggest that in fact, SEC ALJs are not Officers as the Court ruled.  It is because of these issues that the Solicitor General urged the Court to consider this question.  The Court declined. 

Finally, there is no reason that the new hearing ordered in this case has to be presided over by a different ALJ, according to Justice Breyer.  

Justice Sotomayor dissented in an opinion joined by Justice Ginsburg.  The Court’s jurisprudence in this area offers little guidance, the Justice noted.  “To provide guidance to Congress and the Executive Branch, I would hold that one requisite component of ‘significant authority’ is the ability to make final, binding decisions on behalf of the Government.  Accordingly, a person who merely addresses and provides recommendations to an officer would not herself qualify as an officer.”   While SEC ALJs have “extensive powers,”  “I would hold that Commission ALJs are not officers because they lack final decision-making authority.”   In addition, “I share Justice Breyer’s concerns regarding the Court’s choice of remedy...”  

Comment 

Lucia resolves the one question the Court agreed to hear in granting certiorari.  It leaves unresolved, however, more questions than it actually resolves, ultimately casting a pall of uncertainty over the Commission’s administrative hearing process that undoubtedly will spawn more litigation.  It could be years before the ultimate validity of SEC ALJ’s is resolved. 

To be sure, the Court did, in fact, resolve the question of whether the Commission’s ALJs must be appointed in accord with the dictates of the Constitution’s Appointments Clause. SEC ALJs are in fact Officers within the meaning of the Appointments Clause the Court concluded.  Therefore they must be appointed by the Commission.  If there was any doubt that simply directing the staff to hire the ALJs is not permissible, Justice Breyer’s opinion puts the question to rest. Indeed, that procedure seems to undercut the very purpose of the APA as detailed by the Justice which, in part was to try and separate and insulate the hearing process to help ensure fairness.  Permitting the staff to select the ALJs while having the staff prosecute the hearings over which they preside is more than the appearance of unfairness in a system already tinged with questions about due process. 

In resolving the Appointments Clause question the Court refused to consider the related question presented by the Solicitor General and Justice Breyer regarding the employment protections afforded SEC ALJs under the APA in view of Free Enterprise Fund.  As Justice Breyer points out, Free Enterprise Fund at least suggests that PCAOB members are in fact Appointment Clause Officers, although that determination was not crucial to the holding of the case.  If in fact, that suggestion is correct then it would indicate that the APA employment protections afforded to SEC ALJs are contrary to the dictates of the Constitution’s Vesting Clause.  That suggestion, however, is at odds with the statement in Free Enterprise Fund that it’s holding does not impact ALJs.  At the same time, the fact that Congress provided those protections to ALJs seems to undercut the Court’s conclusion in Lucia as well as Freytag.   It was to avoid this difficulty that the Solicitor General, as well as Justice Breyer and those who joined his opinion, urged the Court to consider the question along with the Appointments Clause issue. 

The Court also specified the remedy for Petitioner. That question received no attention in the lower court and little in the briefing process.   In doing so it sidestepped the issue of ratification presented by the SEC’s November 2017 order. Whether that process constitutes a proper remedy for what has been held to be a clear constitutional error is thus an open question.  

Finally, the critical question which launched Lucia and a host of other similar cases is not even mentioned – venue.  It was the Commission’s decision to largely move its enforcement actions “in-house” rather than filing cases in federal district court which spawned Lucia and a number of other cases challenging those decisions.  Thus, while Mr. Lucia and his firm “won” in terms of the case, after years of litigation they are no closer to their actual goal.  It is perhaps the ultimate irony of the case that while Petitioners sought to escape a hearing in front of an administrative law judge by “winning” they now have the right to a new hearing before another administrative law judge. 

Viewed in this context Lucia presents the ultimate “ground hog day” experience – an opportunity to go round and round to nowhere.  The venue selection issue which launched Lucia has not been addressed.  And, while the one issue about the Appointments Clause has been resolved, as Justice Breyer points out there are other significant questions awaiting resolution.  As Justice Breyer stated, “By considering each question in isolation, the Court risks . . . unraveling, step-by-step, the foundations of the Federal Government’s administrative adjudication system as it has existed for decades, and perhaps of the merit-based civil-service system in general. And the Court risks doing so without considering the potential consequences.”   Absent   an effective remedy, all future SEC administrative proceedings will be at risk which could bring about Justice Breyer’s prediction. The Commission's order halting all administrative proceedings seems to acknowledge this fact.  

Firm Highlights

Insights

Energy Law: Month in Review - September 2026

Welcome to Dorsey’s Energy Law: Month in Review. We provide this update to our clients to identify significant developments in the previous month. Please reach out to any of the authors, listed above, to discuss these issues. Regulatory Developments Massachusetts Ratchets Up State and Local Regulation of AI Data Centers In early September, Governor Maura Healey of Massachusetts signed an executive order requiring that artificial intelligence data centers secure the approval of local communities as a precondition to proceeding with a given project. According to the terms of the order, data center developers will need to secure a “community benefits agreement” as a precondition to receiving permits from numerous state agencies, including the Department of Environmental Protection, the Energy Facilities Siting Board, and the Massachusetts Environmental Policy Act Office. Beyond requiring community benefits agreements, the order also mandates that developers mitigate utility costs to consumers, prohibits the use of nondisclosure agreements, and requires various state agencies to develop measures to limit data center impacts on the environment. North Carolina Regulators Decline Approval of Duke Energy Gas Turbine On September 18, 2026, North Carolina Utilities Commission (NCUC) denied Duke Energy’s application for a certificate of public convenience and necessity required to construct a gas-fueled combustion turbine at its Smith Energy Complex in North Carolina. The NCUC objected strongly to the $584 million price tag and noted that Duke appeared to be constructing the facility “based on anticipated data center customer additions.” The NCUC rejected that anticipated growth as “insufficiently reliable for the Commission to act at this point.” In rejecting Duke’s application, the NCUC also noted that Duke had signed the White House Ratepayer Protection Pledge, in which it represented that it would not shift data center costs to consumers. The NCUC observed that the record did not demonstrate how Duke “intends to adhere to its commitments under the Ratepayer Protection Pledge with regard to the Proposed Facility.” Notably, commission staff had actually supported the construction of the turbine, citing concerns about Duke’s reserve margins. The NCUC noted that it “understands the Public Staff’s expressed concerns,” but those concerns were outweighed by the NCUC’s reservations, including questions of demand. Department of Energy Approves Funds for Grid Improvement The U.S. Department of Energy (DOE) recently announced that it would fund 31 grid-improvement projects in 26 states. The funding initiative is part of the DOE’s “SPARK” initiative. The funding will include $1.9 billion in federal funding from DOE and $3.35 billion in recipient cost-sharing funding. The funds will go to projects designed to improve grid reliability and lower electricity costs. Recipients plan to reconductor over 1,500 miles of transmission lines and will deploy grid-enhancing technologies across approximately 21,000 miles. DOE stated that this initiative will make available over 23 additional gigawatts of electricity. Texas Moderates Rules Governing Data Center Interconnection The Texas Public Utility Commission adopted new regulations governing large-load interconnections. The rules impose a flat study fee of $100,000 for all proposed interconnections, which departs from the initial proposal to impose study fees using a tiered system based on project size. Additionally, the final rule eliminates the PUC’s previous proposal to impose a non-refundable interconnection fee of $50,000 per MW of contracted peak demand. The final rule also moderates the initially proposed regulations governing Electric Reliability Council of Texas (ERCOT) notifications for large-load customers’ non-utilized capacity. The proposed rules would have required notifying ERCOT within 30 days of missing a scheduled energization milestone by six months. The final rules, however, do not require informing ERCOT unless a scheduled energization milestone is missed by 24 months. FERC Denies TransAlta 202(c) Cost-Recovery Plan The Federal Energy Regulatory Commission (FERC) recently rejected TransAlta’s plan to recover $19.9 million in expenses stemming from a DOE order in which DOE prohibited TransAlta from retiring its coal-powered Centralia power plant. TransAlta had previously intended to retire the facility at the end of 2025. TransAlta’s cost recovery plan proposed spending an additional $23 million on repairs to continue operating the unit. FERC’s main objection had to do with geographic scope. TransAlta’s recovery plan called for recovering costs from California Independent System Operator (CAISO) and the Southwest Power Pool (SPP), but the DOE’s order requiring operation of the plant was designed to ensure reliability in the Northwest assessment area (Montana, Oregon, Washington, and parts of northern California and northern Idaho). Accordingly, FERC was unwilling to allow cost recovery from CAISO and SPP when the order that precipitated the additional costs only related to the Northwest assessment area. FERC informed TransAlta that it would only approve cost recovery from load-serving entities in the Northwest assessment area. FERC’s decision comes amid a rush of DOE emergency orders requiring the continued operation of coal-fired generating units. Litigation Appeals Court Upholds Washington Hydropower Plant With Caveats In a September 21, 2026, opinion, the Washington Court of Appeals largely upheld a Clean Water Act water quality certification by the Washington Department of Ecology for the Goldendale Energy Storage Project, a proposed pumped-water storage hydropower system adjacent to, but off-stream from, the Columbia River. A nonprofit (Columbia Riverkeeper) and the Confederated Tribes and Bands of the Yakama Nation appealed the certification, contending that it failed to impose necessary conditions and monitoring requirements to protect the water quality of the Columbia River. Most saliently, the plaintiffs argued that the project had the potential to leak 100 acre-feet of water per year into tributaries of the Columbia River. The Court of Appeals broadly rejected plaintiffs’ challenge to the state’s conclusion that “the project was designed not to leak.” That said, the Court of Appeals did reverse on one narrow issue. Specifically, the court determined that the state’s conclusion that “leakage from the project’s tunnels would be monitored and reported” was not supported by the evidence because the certification “does not explicitly require monitoring and reporting to determine whether there is any leakage.” Accordingly, the court remanded the matter to the state to impose monitoring and reporting requirements but otherwise affirmed the certification. Legislative Developments California Legislates Restrictions on Data Center Energy Use and Grid Costs On September 21, 2026, California Governor Gavin Newsom signed seven bills broadly regulating data centers in the state. SB 1168 directed the California Public Utilities Commission to assess the energy used by data centers. It also requires the PUC to pass costs of transmission and distribution upgrades and load increases on to data centers, rather than customers. SB 886 and SB 887 compel data centers to pay for infrastructure upgrade and generation costs, and wildfire mitigation costs, in addition to imposing environmental review. The statutes additionally increase local oversight of data centers. AB 1577 imposes a monthly reporting requirement that requires data centers to supply energy consumption and efficiency data to the California Energy Commission. AB 2383 contains incentives for data centers to use onsite clean energy generation. Finally, AB 2469 and AB 2619 require data center developments to assess water supply and develop a water scarcity plan. The statutes also mandate statewide water reporting as a precondition to obtaining and renewing business licenses.

Insights

EPA Limits Title V Re-Litigation of NSR Permits

Overview On September 25, 2026, the U.S. Environmental Protection Agency (“EPA”) published a final rule that significantly limits the ability of third parties to use the Clean Air Act (“CAA”) Title V permitting process to revisit New Source Review (“NSR”) permitting decisions years after those decisions were made. The rule establishes that NSR permitting determinations generally must be challenged during the original permitting proceeding, thereby providing regulated sources with greater permitting certainty and finality for major capital projects. Published in the Federal Register titled Clarifying the Scope of “Applicable Requirements” Under State Operating Permit Programs and the Federal Operating Permit Program (Docket ID No. EPA-HQ-OAR-2023-0401), the rule amends 40 C.F.R. Parts 70 and 71 to codify EPA’s interpretation regarding when requirements established under other CAA programs may be reviewed, modified, or implemented through the Title V operating permit program. The rule becomes effective 30 days after publication. The rule addresses two principal issues: (1) the relationship between NSR preconstruction permitting and Title V operating permits, and (2) the treatment of the General Duty Clause under CAA section 112(r)(1). Most significantly, the rule provides greater certainty for sources navigating the NSR permitting process. EPA’s amendments are intended to ensure that NSR permitting decisions made through an approved public process are generally not revisited later through Title V permit proceedings. The rule responds to a circuit split between the U.S. Courts of Appeals for the Fifth and Tenth Circuits. In Environmental Integrity Project v. EPA, 969 F.3d 529 (5th Cir. 2020), the Fifth Circuit upheld EPA’s interpretation, concluding that it was consistent with the text, structure, and purpose of Title V. In contrast, the Tenth Circuit reached the opposite conclusion in Sierra Club v. EPA, 964 F.3d 882 (10th Cir. 2020), finding that the then-existing regulatory definition of “applicable requirement” did not support EPA’s position. By amending the regulatory language on which the Tenth Circuit relied and codifying the interpretation approved by the Fifth Circuit, EPA has established a nationwide framework governing the interaction between NSR and Title V. NSR and Title V: EPA Establishes a Uniform Nationwide Framework At the core of the rule is EPA’s effort to define the respective roles of NSR and Title V. The rule codifies the approach EPA has applied since 2017: once a source obtains an NSR permit under an EPA-approved permitting program, and that permit was issued following public notice with an opportunity for comment and judicial review, the permit establishes the NSR-related “applicable requirements” of the State Implementation Plan (“SIP”) or Federal Implementation Plan (“FIP”) for Title V purposes. Under this framework, Title V is not a vehicle for re-examining underlying NSR permitting decisions. EPA does not intend to use the Title V process to revisit applicability determinations, emissions calculations, control technology determinations, permit conditions, or other issues resolved through the NSR permitting process. This principle applies regardless of the stage of the Title V proceeding; whether the NSR permit was issued pursuant to a SIP or FIP; the type of NSR issue involved; or whether the NSR permit is incorporated into Title V sequentially or concurrently. Limited Exceptions EPA recognizes several circumstances in which NSR issues may still be reviewed through the Title V program: No NSR permit was issued at all; The permit was issued without public notice and an opportunity for comment and judicial review; or The issue involves substantive overlap between Title V and NSR requirements, such as the adequacy of monitoring provisions. As a result, the rule does not insulate unpermitted projects or foreclose review of matters that independently arise under Title V. Key Regulatory Amendments The rule revises the definition of “applicable requirement” in 40 C.F.R. §§ 70.2 and 71.2. Paragraph (1): Where an NSR permit is issued with public notice and an opportunity for comment and judicial review, the permit establishes and defines the applicable SIP or FIP requirements for Title V purposes. Paragraph (2): All NSR permit terms, including terms contained in minor NSR permits, constitute applicable requirements that must be incorporated into Title V permits. Paragraph (4): CAA section 112(r)(1) (the General Duty Clause) is expressly excluded from the definition of “applicable requirement,” while section 112(r)(7) Risk Management Program requirements remain included. EPA also amended 40 C.F.R. §§ 70.8 and 70.12 to clarify that alleged defects in requirements established outside the Title V process generally do not provide a basis for EPA objection to a Title V permit or for a Title V citizen petition. General Duty Clause Exclusion The rule also codifies EPA’s longstanding position that the General Duty Clause in CAA section 112(r)(1) is not an “applicable requirement” for Title V purposes. EPA points to several considerations supporting that conclusion, including the distinction between the General Duty Clause and Title V permit terms, the provision’s origins in the Occupational Safety and Health Act’s general duty clause, and the different enforcement structures applicable to the General Duty Clause and Title V permit requirements. Importantly, excluding section 112(r)(1) from the definition of “applicable requirement” does not eliminate EPA’s authority to enforce the General Duty Clause independently of the Title V program. The final rule instead clarifies that the General Duty Clause need not—and should not—be incorporated into Title V permits as an applicable requirement. Practical Implications for Regulated Sources Greater Finality for NSR Permits  For projects requiring PSD, nonattainment NSR, or minor NSR permits, the permitting process becomes the primary forum for resolving disputes regarding applicability determinations, emissions calculations, control technology requirements, offsets, and permit conditions. Once an NSR permit is issued through a qualifying public process, regulated sources should face substantially reduced risk that those same issues will be challenged years later through Title V permit proceedings. Reduced Risk of Collateral Permit Challenges Stakeholders have sometimes sought to use Title V permit issuance, renewal, revision, or citizen-petition proceedings to challenge underlying NSR determinations. The final rule makes clear that Title V is not the appropriate vehicle for challenging whether an applicable requirement was correctly established in the first instance. This should reduce the risk of permit delays and uncertainty associated with collateral challenges to previously issued NSR permits. The rule does not, however, eliminate all Title V challenges relating to an NSR permit. Challenges concerning the Title V permit itself—including whether it appropriately incorporates applicable requirements or contains adequate compliance provisions—remain possible. Increased Importance of the Initial NSR Proceeding Because Title V generally will not provide a second opportunity to challenge the substantive validity of an NSR determination, the administrative record developed during the NSR process becomes increasingly important. Permit applicants should ensure that applicability analyses, emissions calculations, control technology evaluations, modeling demonstrations, and supporting technical documentation are thoroughly developed during the original permitting proceeding. For significant projects, applicants may therefore have an additional incentive to identify and resolve potential permitting issues before the NSR permit is issued rather than assuming that unresolved issues can be addressed during a subsequent Title V proceeding. Potential Incentive for Broader Public Participation EPA also notes that permitting authorities may choose to provide public notice and an opportunity for comment for a broader range of NSR permits because permits issued through a qualifying public process receive the benefit of the finality framework established by the rule. Some permitting authorities may conclude that greater public participation at the NSR stage is preferable to uncertainty during subsequent Title V proceedings. Conclusion The final rule is principally a permitting-certainty measure. For sources that obtain NSR permits through a public process, EPA has substantially limited the ability of third parties to revisit underlying NSR determinations through the Title V program. As a result, regulated entities should benefit from greater finality regarding key permitting decisions, reduced risk of collateral permit challenges, and increased certainty when planning and implementing capital projects.

Insights

The Supreme Court Update - October 8, 2026

On September 29, 2026, the Supreme Court granted certiorari in one case: Department of Homeland Security v. D.V.D., No. 26-426: This case concerns the Trump Administration’s “third-country removal” procedures, where immigrants are deported to countries not listed in the removal orders. In granting certiorari, the Court granted the Government’s application to stay a lower court decision halting the practice, which will allow third-country removals to continue pending resolution of the case. The issues presented are: (1) Whether the district court had jurisdiction over respondents’ claims; (2) whether the district court had authority to enter class-wide declaratory relief and APA vacatur under 8 U.S.C. § 1252(f)(1); (3) whether the Government’s guidance on third-country removals is unlawful under 8 U.S.C. § 1231(b), the due process clause, or FARRA/CAT and its implementing regulations; and (4) such other questions that the Government determines are appropriate for the proper disposition of the case. On October 1, 2026, the Court granted certiorari in three additional cases: Rhoney v. Barbosa da Cunha, No. 26-104: Immigration officials detained Ricardo Aparecido Barbosa da Cunha—a Brazilian citizen who had lived in the United States for approximately twenty years after entering without inspection—and denied him a bond hearing under 8 U.S.C. § 1225(b)(2)(A). The Second Circuit held that his detention was instead governed by § 1226(a), which permits release on bond, because § 1225(b)(2)(A)’s mandatory-detention requirement applies only to noncitizens apprehended while entering the country or shortly thereafter. The question presented is: Whether 8 U.S.C. § 1225(b)(2)(A) mandates the detention pending removal proceedings of aliens who, like Barbosa da Cunha, are present in the United States without having been admitted. Missionaries of St. John the Baptist, Inc. v. Frederic, No. 25-113: A Catholic religious organization sought to build a shrine to the Virgin Mary on land the organization owned adjacent to its church in Park Hills, Kentucky. Local zoning restrictions prohibited the proposed construction. The question presented is: Whether a land-use regulation that prohibits a religious institution from building a religious structure on its own property constitutes a “substantial burden” on religious exercise under the Substantial Burden Provision of the Religious Land Use and Institutionalized Persons Act, 42 U.S.C. § 2000cc(a). Marschner v. Marschner, No. 25-1349: Under the Uniformed Services Former Spouses’ Protection Act (“USFSPA”), a veteran’s longevity-based retirement pay can be divided in a divorce, but retirement pay based on disability and retirement pay that was waived to receive disability pay are indivisible. The question presented is: Does the USFSPA require state courts to refuse enforcement of indemnification provisions in a divorce settlement agreement?

Insights

SEC Proposes Expansion of Investment Adviser Performance-Based Compensation Rule

On September 30, 2026, the Securities and Exchange Commission (the “SEC”) proposed amendments to Rule 205-3 under the Investment Advisers Act of 1940, as amended (the “Advisers Act”), which provides an exemption from the general prohibition under Section 205(a)(1) of the Advisers Act on registered investment advisers receiving performance-based compensation (the “Proposal”) so long as performance-based compensation is limited to “qualified clients”.1 Most notably for private fund sponsors, the Proposal would expand the definition of “qualified client” to include any investors that satisfy the “accredited investor” definition under Regulation D. The Proposal may also have implications for private fund managers that rely on exemptions from investment adviser registration under state law because certain state-level investment adviser registration exemptions incorporate or otherwise reference the federal qualified client definition. Expansion of the Qualified Client Definition Under the current Rule 205-3, an investor generally may qualify as a qualified client if, among other alternatives, the investor has at least $1.4 million under management with the adviser or has a net worth exceeding $2.7 million. These thresholds are higher than the financial thresholds applicable to many accredited investors under Regulation D. As a result, an investor may currently qualify as an accredited investor for purposes of investing in a private offering without qualifying as a qualified client for purposes of paying performance-based compensation. The Proposal would expand the qualified client definition to include any natural person or legal entity investor that satisfies the accredited investor definition under Regulation D. The Proposal would also remove the assets under management and net worth thresholds under the current Rule 205-3 qualified client test. For private funds relying on Section 3(c)(1) of the Investment Company Act of 1940, this change could reduce the need to apply a separate qualified client standard to investors that already qualify as accredited investors. Dorsey Observations and Next Steps If adopted as proposed, the expanded qualified client definition could be particularly significant for private fund managers. Most private fund offerings are already limited to accredited investors under Regulation D. However, the Proposal could expand the pool of prospective investors available to emerging private fund managers while reducing the regulatory burden associated with complying with Rule 205-3. The Proposal could also benefit advisers operating below the SEC registration threshold that rely on a state private fund adviser exemption. A number of states have adopted exemptions modeled on the North American Securities Administrators Association (“NASAA”) private fund adviser exemption, which may condition relief for advisers to certain funds relying on Section 3(c)(1) on each beneficial owner satisfying the federal qualified client definition. However, state requirements vary, and any effect of the Proposal would depend on the text of the applicable state exemption and how it incorporates Rule 205-3. Many emerging private fund managers may have a larger network of accredited investor relationships than qualified client relationships during the early stages of their investment advisory business. Currently, under Rule 205-3, private fund managers may receive performance-based compensation from investors who do not satisfy the qualified client definition if those investors were admitted to their private funds prior to registration with the SEC. Following registration with the SEC, however, managers may continue to permit investors that are not qualified clients to invest in future private funds but may not receive performance-based compensation from those investors with respect to such investments. In addition, because the net worth and assets under management thresholds for qualified client status are adjusted for inflation every five years, the pool of qualified client investors may diminish over time as previously eligible investors no longer satisfy the applicable thresholds. The Proposal could provide the dual benefit of greater flexibility for private fund managers to establish and maintain relationships with accredited investors as their businesses scale and they become registered with the SEC, and greater flexibility for certain accredited investors to participate in investment strategies that historically have been restricted to much larger institutional investors. Unless and until the Proposal is adopted, investment advisers should continue to comply with the existing qualified client requirements. If the Proposal is adopted, private fund sponsors should consider whether corresponding changes are appropriate for their subscription documents, investor questionnaires, and other offering materials. Advisers that are state-registered or rely on a state-level exemption should also consult the laws and regulations of each relevant jurisdiction before changing investor eligibility standards or performance-based compensation practices, because adoption of the federal amendments may not automatically modify state requirements. Comments on the Proposal will be due 60 days after publication in the Federal Register. 1 Investment Adviser Performance-Based Compensation Modernization, Investment Advisers Act Release No. IA-7022 (Sept. 30, 2026), available at https://www.sec.gov/rules-regulations/2026/09/s7-2026-28#33-11443proposed.