LITIGATION AND DISPUTES

DC Circuit Upholds Refund Order for Midwest Utility Customers
On June 5, the D.C. Circuit Court of Appeals upheld the Federal Energy Regulatory Commission (FERC)’s refund orders against a group of transmission companies in the Midcontinent Independent System Operator (MISO). The court had ruled in 2022 that the companies were required to refund customers for years of overcharges on electricity delivery rates, but the companies again challenged the calculation of the refund. Rejecting the companies' argument that federal law limits refunds to a single 15-month period, the court found that FERC is authorized to order retroactive multi-year refunds when the agency is following court orders to correct previous faulty orders.

Ohio Supreme Court Rules Utilities Lawfully Recovered $115 Million in Coal Plant Costs
The Ohio Supreme Court unanimously ruled that three utilities were lawfully reimbursed for $115 million spent in 2020 to keep two aging Ohio coal plants operating. Critics argued the plants should have shut down when power prices were too low to cover operating costs. But the court found that a strategy of continuous operation was "prudent and reasonable" in compliance with a 2019 state law. The court affirmed the Public Utilities Commission of Ohio (PUCO)’s decision to issue the reimbursements. Opponents have signaled they will continue to challenge further PUCO audits on the issue.

DC Circ. Rejects PJM Transmission Owners' Bid to Change Grid-Planning Rules
On June 6, a federal appeals court upheld FERC’s rejection of a proposal that would have let PJM Interconnection (PJM) make planning decisions without approval from its member utilities. FERC had rejected the proposed changes to PJM’s operating agreement based on its determination that eight provisions were “not just and reasonable.” Rejecting PJM’s argument that FERC should have only considered whether the entire package was “just and reasonable” when PJM had presented it as an all-or-nothing package, the court affirmed FERC’s decision, leaving PJM's current governance structure in place.

D.C. Court Orders DOE to Restore $82 Million in Clean Energy Grants
A federal judge in Washington, D.C. ordered the Department of Energy (DOE) to reinstate $82.1 million in clean energy grants that it had cancelled in October 2025 to 11 projects in New York, Oregon, Connecticut, Minnesota, and Colorado. The judge found that the cancellations likely targeted projects in states that voted Democratic in the 2024 presidential election, violating constitutional equal protection and First Amendment guarantees. The ruling follows a January 2026 case in which DOE reversed $27.6 million in similar grant cancellations without contesting that the primary reason for cancellation had been the projects’ location in states that voted for former Vice President Kamala Harris in 2024.

REGULATORY DEVELOPMENTS

FERC Approves New Fast-Track Transmission Access for Data Centers in the Midwest and Plains
On June 5, federal energy regulators approved a new program allowing large electricity users in the Southwest Power Pool (SPP)’s 17-state region to be served by the grid far more quickly. The Conditional High Impact Large Load Service (CHILLS) program creates a new transmission service, allowing large customers to connect to the grid for up to 7 years before necessary longer-term upgrades are completed, subject to condition that their power can be cut during grid emergencies to maintain SPP’s grid reliability.

FERC Tells Grid Operators to Update Rules for Connecting Large Electricity Users
On June 18, FERC ordered six regional grid operators, including MISO and SPP, to update their rules for connecting large electricity users like data centers to the power grid, rejecting a one-size-fits-all national rule. Each grid operator must show its current rules are reasonably tailored to large loads or revise them within 60 days. Although FERC issued orders specific to each operator, all operators are expected to satisfy general principles ensuring that existing customers won’t be subject to higher bills, that new large demand facilities can be co-located with generation facilities, and that transmission services remain efficient.

FERC Approves Fast-Track Interconnection Process for Large Power Projects in PJM
FERC also approved PJM’s new expedited process allowing up to 10 large power projects per year to connect to the grid in approximately 10 months. To qualify, a project must generate at least 250 megawatts and have support from the applicable state's permitting authority to come online within three years. FERC rejected objections from several utilities and state regulators, finding the program is not unfairly biased towards utilities and that concerns about delays to other projects were too speculative. Projects may be selected as early as October 2026, with the program set to expire at the end of 2027.

New York Announces Initiatives to Support Nuclear Energy
Various agencies and utilities in New York launched initiatives in June to support Governor Hochul’s goal of generating 5 GW of new sources of nuclear energy to increase in-state generation and reliability. The New York Power Authority issued a Request for Qualifications, calling for experienced developers to present plans to deliver at least 1 GW of nuclear power in Upstate New York. Meanwhile, the New York Public Service Commission (NYPSC) established a Nuclear Reliability Backbone Process to investigate and facilitate pathways for generating 4 GW of nuclear energy. The NYPSC requested public comments on the initiative by August 10 and plans to draft a corresponding report policy options by November 11.

DOE Commits $850 Million to New and Modernized Coal Power Plants
On June 4, DOE announced it would issue two separate grants totaling $850 million for 17 coal-related projects using authority from the Defense Production Act. The funding targets include two brand-new coal plants in Alaska and West Virginia, which would be the first new U.S. coal plants built since 2013. Money will also go towards constructing a new coal export terminal in California and to upgrade existing plants in Arizona, Arkansas, Indiana, Kentucky, Maryland, North Carolina, North Dakota, Oklahoma, Puerto Rico, Tennessee, West Virginia, and Wisconsin. Opponents continue to challenge whether the funding is permissible under federal law.

DOE Orders Florida Municipal Utility to Keep Coal Plant Running
Citing concerns about future electricity demand from potential data centers, DOE also ordered Orlando's municipal utility to keep a 465 MW coal-fired power plant operating despite existing plans to convert the plant to natural gas. The order lasts through September 1, 2026, and directs the utility to file necessary tariff revisions to recover compliance costs. Similar orders at other plants around the country are being challenged in court and seem likely to follow in Florida given that a recent federal reliability assessment had just rated the state as having only "normal risk" for power shortages.


LEGISLATIVE DEVELOPMENTS

New Jersey Governor Mikie Sherrill signed three bills meant to make energy bills more affordable. A796 requires “large-load data centers,” defined as data centers with at least 100 MW in load, to pay for their own energy use and associated grid infrastructure. The legislation also incentivizes data centers to bring lost cost renewable energy onto the grid. A5188 requires a Certificate of Public Convenience and Necessity (CPCN) for supplemental transmission projects. Supplemental transmission projects are typically designed to replace outdated transmission lines and are planned outside PJM’s process and previously did not require a CPCN. Supplemental transmission projects totaled $14.7 billion from 2008 to 2025, amounting to 79% of ratepayers’ transmission expense. A2757 mandates that New Jersey utilities join a regional transmission organization (RTO). This removes New Jersey utilities’ entitlement to a financial incentive offered by FERC for utilities to voluntarily join an RTO.

Firm Highlights

Insights

Ninth Circuit Splits California’s Climate Disclosure Laws: Scope 1 and 2 Reporting Proceeds; Scope 3 and SB 261 Likely Unconstitutional

Key Takeaways On November 9, 2026, the Ninth Circuit in Chamber of Commerce v. Sanchez allowed Scope 1 and Scope 2 greenhouse gas (GHG) emissions reporting under SB 253 to proceed but held that SB 253’s Scope 3 requirement, and SB 261 in its entirety, likely violate the First Amendment.1 U.S.-formed entities with total annual revenues above $1 billion that do business in California remain subject to Scope 1 and 2 reporting. First reports (or, for eligible entities, statements of non-reporting) were due November 10, 2026.2 Scope 3 reporting (scheduled to begin in 2027) and SB 261 climate-risk reporting are effectively on hold. Entities with revenues between $500 million and $1 billion, which were covered only by SB 261, currently have no reporting obligation under either law.3 The ruling addresses only preliminary injunctive relief; it is not a final judgment on the merits. If the district court finds the Scope 3 requirement non-severable, it could also enjoin Scope 1 and 2 reporting.4 Background SB 253 (the Climate Corporate Data Accountability Act) requires U.S.-formed entities with total annual revenues above $1 billion that do business in California to report Scope 1 and 2 emissions starting in 2026 and Scope 3 emissions starting in 2027, with penalties of up to $500,000 per reporting year.5 SB 261 (the Climate-Related Financial Risk Act) requires U.S.-formed entities with total annual revenues above $500 million that do business in California to publish biennial climate-related financial risk reports consistent with the Task Force on Climate-related Financial Disclosures (TCFD) framework, with penalties of up to $50,000 per reporting year.6 Business groups led by the U.S. Chamber of Commerce challenged both laws as compelled speech that violates the First Amendment. In August 2025, the district court denied their motions for preliminary injunctions. On November 18, 2025, the Ninth Circuit enjoined SB 261 pending appeal but declined to enjoin SB 253.7 The implementing regulation adopted by the California Air Resources Board (CARB) took effect on October 12, 2026, and set November 10, 2026, as the first Scope 1 and 2 reporting deadline.8 The Court’s Decision Scope 1 and Scope 2: Upheld for Now The panel held that Scope 1 and 2 disclosures are commercial speech because they compel disclosure of factual information about emissions from a company’s own operations and purchased energy—information that bears on capital transactions. Applying intermediate scrutiny, the court concluded that the requirements advance California’s substantial interests in reducing information asymmetries for investors and in reducing emissions and are no more extensive than necessary.9 The panel split 2–1 on this issue.10 Scope 3: Likely Unconstitutional The court held that Scope 3 disclosures concern diffuse third-party conduct across the value chain and are “insufficiently tethered” to the reporting entity’s own operations to qualify as commercial speech. Applying strict scrutiny, the court concluded that the requirement likely fails because (1) SB 253 does not require primary data, (2) the record did not show that companies’ proxy-based estimates would be more reliable than estimates the State could generate itself, and (3) the link to investor-relevant risk was too remote.11 SB 261: Likely Unconstitutional in Its Entirety The court held that SB 261 compels noncommercial speech because it requires “predictive and normative judgments” about a “politically fraught subject.” Even assuming California’s interests are compelling, the court reasoned that the law is likely not narrowly tailored because California could use less restrictive alternatives, such as incentives for voluntary disclosure.12 The panel was unanimous on Scope 3 and SB 261.13 Remand and Severability The Ninth Circuit did not enter injunctions itself. It reversed the denials of preliminary injunctive relief and remanded with instructions for the district court to enter relief consistent with the opinion and, for Scope 3, to decide severability first.14 SB 253 contains an express severability clause. If the district court nevertheless finds the Scope 3 requirement non-severable, it could also enjoin Scope 1 and 2 reporting.15 Current Status at a Glance Requirement Status after the Ruling Practical Effect SB 253 – Scope 1 and 2 emissions (entities with revenues above $1 billion) In effect; denial of preliminary injunction affirmed First reports were due November 10, 2026; CARB fee notices expected by December 10, 202616 SB 253 – Scope 3 emissions (scheduled to begin in 2027) Likely unconstitutional; remanded for severability ruling and entry of injunctive relief Not required while remand is pending; scope of CARB’s 2027 rulemaking uncertain17 SB 261 – climate-related financial risk reports (entities with revenues above $500 million) Likely unconstitutional in its entirety; enjoined pending appeal since November 18, 2025 No current reporting obligation; voluntary reports permitted18 What to Watch Any petition for panel rehearing or rehearing en banc (due 14 days after entry of judgment) and any petition for a writ of certiorari to the U.S. Supreme Court.19 The district court’s severability ruling and the scope of any preliminary injunctions it enters as to Scope 3 and SB 261.20 CARB’s response. As of the date of this alert, CARB has not issued a formal statement on the opinion.21 CARB had been developing a second rulemaking for reporting years 2027 and later, addressing Scope 3, assurance, deadlines, and reporting templates, and had proposed retaining November 10 as the annual deadline.​​​​​​​22 Recommended Actions Confirm coverage entity by entity. Revenue (gross receipts, based on the lesser of the two prior fiscal years) and “doing business in California” are determined separately for each entity; affiliates are not aggregated. Retain supporting California tax records for five years.23 If a covered entity has not filed, file promptly. Submit the Scope 1 and 2 report (or, if eligible, a statement of non-reporting) and document good-faith compliance efforts, which CARB must consider in assessing penalties.24 Calendar the fee cycle. CARB expects to issue fee notices by December 10, 2026, with payment due within 60 days after the notice; each day of nonpayment is a separate violation.​​​​​​​25 CARB’s August 2025 proposal set flat fees at $3,106 per SB 253 entity and $1,403 per SB 261 entity.26 Confirm the final amount when the CARB notice arrives. Prepare for 2027 Scope 1 and 2 reporting. Third-party assurance was not required for 2026, but CARB has signaled that it will require limited assurance of Scope 1 and 2 data for 2027 and later years.27 Engage assurance providers and strengthen internal data controls now. Pause, but preserve, Scope 3 and SB 261 workstreams. Maintain existing data and processes: the ruling is preliminary, and many multinational companies will still need Scope 3 and product-level emissions data under the EU’s Corporate Sustainability Reporting Directive (CSRD) and Carbon Border Adjustment Mechanism (CBAM).28 Companies may still publish SB 261 reports voluntarily.29 Review public statements. Continue to review voluntary climate disclosures for consistency with CARB filings and other regulatory reports. Considerations for Real Estate and Infrastructure Clients The following are practice recommendations, not statutory requirements: Control boundaries. Whether emissions from a building or data center fall within a landlord’s or a tenant’s Scope 1 or 2 inventory depends on the control approach applied under the GHG Protocol. Leases, colocation agreements, and powered-shell arrangements should specify which party has operational control for GHG reporting purposes. Data cooperation. Include obligations to deliver utility and energy data (with specified timing and format) and to cooperate with assurance providers, particularly where the landlord or operator holds the utility accounts. Transactions. In acquisitions and financings, diligence the target’s or borrower’s SB 253 compliance and fee payments, and consider representations and covenants on the accuracy of emissions data. Value-chain requests. Counterparty requests for Scope 3 data may slow, but those subject to CSRD will likely continue to make them. This alert is for general information only and is not legal advice. The law in this area is changing rapidly, and developments after November 18, 2026, may affect this analysis.  1 Chamber of Commerce v. Sanchez, No. 25-5327 (9th Cir. Nov. 9, 2026) 2 White & Case, California Climate Disclosure Laws: Ninth Circuit Finds SB 253 Scope 3 Requirements and SB 261 Likely Unconstitutional (Nov. 2026) 3 Legal 500, Ninth Circuit Approves California’s Core Carbon Emissions Reporting Rules (Nov. 2026) 4 White & Case, supra note 2. 5 Kirkland & Ellis, Ninth Circuit Rules on California’s Climate Disclosure Laws (Nov. 2026) 6 Simpson Thacher, California Climate Reporting Laws: Ninth Circuit Issues Partial Injunction (Nov. 2025) 7 White & Case, supra note 2. 8 Vinson & Elkins, OAL Approves CARB’s Initial Regulation (Oct. 2026) 9 White & Case, supra note 2. 10 Foley & Lardner, California Climate Disclosure Laws (Nov. 2026) 11 White & Case, supra note 2. 12 Chamber of Commerce, No. 25-5327. 13 Kirkland & Ellis, supra note 5. 14 Troutman Pepper Locke, Ninth Circuit Rules on Challenge to California’s Climate Disclosure Laws (Nov. 2026) 15 White & Case, supra note 2. 16 Davis Polk, Getting Ready for California SB 253’s November 10 Reporting Deadline (Oct. 2026) 17 Troutman Pepper Locke, supra note 14. 18 White & Case, supra note 2. 19 Id. 20 Troutman Pepper Locke, supra note 14. 21 Morgan Lewis, Ninth Circuit Reverses Lower Court (Nov. 2026) 22 Simpson Thacher, CARB Provides New Guidance on SB 253 Reporting (July 2026) 23 Davis Polk, supra note 16. 24 Id. 25 Id. 26 CARB, SB 253/261 Public Workshop Slides (Aug. 2025) 27 Vinson & Elkins, supra note 8. 28 O’Melveny, Is Your Company Still Required to Report Under California’s Climate Laws? (Nov. 2026) 29 White & Case, supra note 2.

News

Dorsey Practices and Attorneys Recognized by Legal 500 Greater China 2027

Legal 500 Greater China 2027 recognized Dorsey & Whitney LLP in five practice areas across China (Mainland) and Hong Kong SAR and recommended six Dorsey attorneys. The Firm’s litigation practice in China advanced from Tier 4 to Tier 3 among foreign firms. Dorsey received the following practice recognitions in the 2027 edition: China — Leading Firm: Dispute Resolution: Litigation (Foreign Firms) China — Leading Firm: Insurance (Foreign Firms) China — Leading Firm: Regulatory/Compliance (Foreign Firms) Hong Kong — Leading Firm: Intellectual Property Hong Kong — Firms to Watch: Capital Markets (Equity) Leading Firm in China for Dispute Resolution: Litigation (Foreign Firms) Recommended Lawyers: Ray Liu and Janet Wong Dorsey’s litigation team excels in managing high-stake China-related cross-border disputes and legal proceedings in the United States, Hong Kong, Europe, and other jurisdictions. Its work spans an extensive array of industries including banking and finance, insurance, TMT, manufacturing, biotechnology, and life sciences. The improved ranking this year highlights the continued market recognition, the strength of our team, the quality of our client service, and our continued commitment to deliver exceptional results. Leading Firm in China for Insurance (Foreign Firms) Recommended Lawyer: Ray Liu Dorsey’s Beijing-based insurance team works with colleagues in the United States and Europe on a broad range of insurance-related disputes, with a particular focus on general liability and product liability litigation. The team also frequently advises on war risk insurance, all-risk insurance, insurance regulatory matters, and reinsurance issues, and assists major Chinese insurance companies with outbound investments, and regulatory compliance related disputes. Leading Firm in China for Regulatory/Compliance (Foreign Firms) Recommended Lawyers: Ray Liu and Karen Yiqin Fan Dorsey’s China team regularly advises on export controls, economic sanctions, national security/CFIUS, trade compliance, capital markets, and financial regulatory compliance. The team also counsels clients on data privacy, employment compliance, corporate investigations, and foreign entity of concern (FEOC) requirements under the Inflation Reduction Act (IRA) and the One Big Beautiful Bill Act (OBBBA). Leading Firm in Hong Kong for Intellectual Property Recommended Lawyers: Janet Wong and Lilian Shi Dorsey’s Greater China IP team advises multinational and local clients on the protection, management, enforcement, and commercialization of intellectual property assets across Greater China and globally. The team develops and manages global IP portfolios, advises on brand protection and anti-counterfeiting strategies, and handles contentious IP matters, including trademark infringement, copyright, trade secret, company name, and domain name disputes. The team also advises on IP-related transactions and commercialization, including IP due diligence, acquisitions and divestitures of IP rights, technology transfers, licensing and franchising arrangements, and supply, distribution, and manufacturing arrangements. Firms to Watch in Hong Kong for Capital Markets (Equity) Recommended Lawyers: Rachel Han and Megan Penick Dorsey’s Hong Kong and U.S. capital markets teams work seamlessly together on initial public offerings and placings in Hong Kong, along with initial public offerings, follow-on and secondary offerings, cross-border financings, and PIPE investments in the United States, and transactions in other international financial centers. The team also advises listed companies on ongoing compliance and regulatory matters in both Hong Kong and the United States. Drawing on Dorsey’s multidisciplinary capabilities, the Hong Kong capital markets team provides complementary advice on international sanctions and U.S. export control regulations.