.

Articles

Chemical Industry Update - July/August 2019

August 12, 2019

by Troy M. Keller, Dave Townsend, and T. Augustine Lo

Download as a PDF

Share this page

“I hope you still see fire inside of me.”
Jason Isbell, Molotov

We looked for a more optimistic sentiment in this month’s song lyric.  In recent issues, we have focused on legal trends that have been tough on the industry—like product liability, ESG pressures and chemical regulatory.  While it can be easy to be caught up in those negatives, we believe there is plenty of fire in the industry’s belly.

For one, the shale oil revolution seems to be receiving the regulatory support it needs to continue to provide low-cost raw materials and energy to fuel manufacturing.  Last month, the EPA finalized its strategy to repeal and replace the Obama administration’s Clean Power Plan.  And earlier this year, the President signed executive orders to make it easier to build oil and gas pipelines—and limit state ability to block them.  The result?  Even as new bans on single-use plastics emerge almost daily, major petrochemical construction are still being announced.

Another area of optimism is in technology policy trends.  The Chemical Industry has heard for a long time how digitalization is going to change the industry.  This Mckinsey article from 2017 arguably kicked things off, and while many of the value premises are still on the come (no self-driving trucks anytime soon, unfortunately), using data to improve manufacturing efficiencies is real, and laws are evolving to deal with this reality.  (See our article below on manufacturing process patents.)

Also, in terms of data’s impact, the EU’s primary chemical association, CEFIC, is said to be in discussions about the creation of a “Netflix of chemical data” that would allow regulators and companies to have access to studies and data on chemicals.  Getting jurisdictions around the world to buy into something like this would indeed have value, simplifying, and lessening the costs, of doing product registrations in the plethora of jurisdictions that have added chemical regulation regimes in recent months and years. We should note that the impacts of broader tech policy trends, like data privacy and possible breakup of the big tech platforms, remain highly relevant to companies with international footprints, like many in this industry.  We’ve been involved in some important local discussions on these issues.

As of the writing of this update, trade war dynamics have worsened, weighing heavily on industries that are at the level in the value chain where inputs and outputs cross borders multiple times before they leave the hands of industry players and head downstream to become consumer products.  The silver lining here? It is harder to find one, but at least the trends are maturing.  Industry has braced for the worst-case hard Brexit, and the steady escalations in the U.S.-China trade war are normalizing into a new reality.  At least USMCA (NAFTA II) feels a step closer as USTR and House Democrats claim to be working on compromise language on the key open items, including data privacy and labor.

New Caselaw on Diagnostic Patents and What it Means for Chemical Process Patents

Can you patent a method for monitoring chemical components or reactions based on observations of reactants or products?  Will such a patent stand up to third party challenges?  Fair questions these days in view of recent Supreme Court rulings and USPTO examination guidelines.  For the answers, we can take cues from the current state of subject matter eligibility law for diagnostic patents, an analog of chemical monitoring patents.

Categories of subject matter eligible for patent are set forth in 35 U.S.C. § 101 as “any new and useful process, machine, manufacture, or composition of matter, or any new and useful improvement thereof.”  However, these categories are limited by judicial exceptions applied by the courts, which include natural laws, abstract ideas, and natural phenomenon.  For example, claims that merely recite a generic use or observation of a natural law, abstract idea, or natural phenomenon are rejected as patent ineligible.  These judicial exceptions present popular ways for third parties to challenge issued patents.

Recently, the Court of Appeals for the Federal Circuit, which oversees patent appeals in the United States, denied a petition for an en banc rehearing for a diagnostic patent.  The denial included eight concurrences and dissents, each addressing the difficulty of following current Supreme Court guidance. Notably, nearly all of the concurrences and dissents requested clarification of subject matter eligibility guidelines from the Supreme Court or Congress.  In a dissenting opinion, Judge Moore stated that for parties advocating patent eligibility for purely diagnostic technologies “[y]our only hope lies with the Supreme Court or Congress.”

The good news is members of Congress heard the call and are working on a solution.  Senators Thom Tillis and Chris Coons have been working on a bipartisan bill to address uncertainty in subject matter eligibility.  The language of the proposed legislation seeks to remove the “new” requirement from subject matter eligibility and specifically abrogates judicially created exceptions to subject matter eligibility.  The legislation would pave the way for patenting purely diagnostic technologies.  In hearings that included the oft repeated theme that current subject matter eligibility guidelines are unworkable and against national interests, the proposed legislation received positive comments from the former director the USPTO and the former Chief Judge of the Federal Circuit.  The bill may be presented for a vote as early as this fall and offers the cleanest break from current precedent.

Notwithstanding the Federal Circuit’s pronouncement that purely diagnostic patents are not eligible for patent, all is not lost.  In another dissenting opinion, Judge Newman noted that claims having diagnostic limitations that also include treatment steps are eligible for patenting.  For example, claims directed testing for a specific genotype and then issuing a specific dosage of medication based on detecting the specific genotype have been upheld as patent eligible.  Moving patent claims from the realm of purely diagnostic to treatment based on the diagnostic can provide a patentable avenue for applicants.  In the immediate term, carefully crafting claims to avoid purely diagnosing or monitoring laws of nature or natural phenomena can provide patent eligible subject matter.  So the simple answer is yes, you can patent a method for monitoring chemical components or reactions based on observations of reactants or products, in certain instances.  And the future may hold some promise in view of Congress’s current efforts.

For more information, contact Nathan Orme.

U.S. - India Trade Friction Impacts Chemicals

The United States recently revoked preferential status for imports of chemicals and many other products originating from India and Turkey.  Effective in May (Turkey) and June (India), the Trump administration removed Turkey and India from the list of countries eligible for the Generalized System of Preferences (“GSP”). The removal of these countries from GSP means that many applicable tariff rates will increase from a preferential rate (Column 2) to the Most Favored Nation (“MFN”) rate (Column 1) that generally applies to imports under the Harmonized Tariff Schedule of the United States (“HTSUS”). In response, India moved forward with long-planned tariffs against goods from the United States, which India previously proposed as retaliation for the U.S. Section 232 tariffs on global imports of steel and aluminum.

The GSP changes undoubtedly will affect many U.S. chemical companies as many chemicals classified under HTSUS Chapters 28 and 29 are duty-free under the GSP, but subject to tariffs under the MFN rate. Indian-origin imports into the United States were $6.3 billion in 2018 under the GSP, more than any other GSP beneficiary, according to data published by the U.S. International Trade Commission. Turkish-origin imports into the United States were $1.9 billion in 2018 under the GSP, the fifth largest among GSP beneficiaries. In taking the action, the Trump administration cited India’s trade barriers and their detrimental effects on U.S. businesses. With respect to Turkey, the Trump administration cited Turkey’s growth and higher level of economic development, which it found sufficient to revoke Turkey’s GSP status.

For more information, contact Dave Townsend and Augustine Lo.

Labor Policy Trends & Updates

The National Labor Relations Board has issued a series of precedent-shifting rulings so far in 2019, many of which are specifically overturning rulings under the Obama Board.  In addition to the administrative rulings, the NLRB forecasted its intent to address certain key employer issues through the rulemaking process when it published its annual agenda in May 2019.  Typically, the NLRB relies on adjudication in individual cases to enforce the National Labor Relations Act.  Management and Union advocates criticize the unpredictability of this practice as the substantive law shifts with each change in administration.  In the May 22 announcement, Republican Chairman John Ring noted, “The agenda reflects the Board majority’s strong interest in continued rulemaking. Addressing these important topics through rulemaking allows the Board to consider and issue guidance in a clear and more comprehensive manner.”

The NLRB’s published agenda included both “short-term actions,” which are generally expected to occur within the coming year, and “long-term actions,” which are not expected to be completed this year. One key short-term action involves the standards for access to an employer’s private property.  The Obama-appointed NLRB created a loud outcry from employer advocates in its 2014's Purple Communications decision allowing workers to use their employers' email systems to discuss union business.  It is this decision that the current NLRB seeks to roll back in its proposed rulemaking.

On the list of long-term actions is the standard for determining when two unrelated entities are joint employers. The policy is expected to have a significant impact on gig economy businesses, franchise business models and companies that rely on contractors.

In September of 2018, the NLRB issued its notice of proposed rulemaking, proposing to reverse the Browning Ferris Industries (BFI) decision issued in 2015.  The NLRB received nearly 30,000 comments during the comment period. The BFI decision loosened the standard from “direct and immediate control” to “share or codetermine,” leading to joint employer findings that could be based solely on indirect or reserved control over employees – regardless of whether that control is ever exercised.  In late 2017, the NLRB returned to the “direct and immediate control” standard in Hy-Brand Industrial Contractors Ltd., but then reversed Hy-Brand only a few months later due to possible ethical concerns related to the representation of one of the parties in BFI by the former law firm of a board member.  Following this, the NLRB announced that it would engage in rulemaking to publish joint employer rules.

However, the BFI case was under appeal before the U.S. Court of Appeals for the District of Columbia Circuit when the NLRB announced its rulemaking intent. The D.C. Circuit ultimately ruled that the NLRB acted properly when it expanded its test for determining joint employment, but also said that courts are responsible for articulating the legal definition of “employer,” because the meaning of “employer” is defined by traditional principles of agency under common law.  This means that the NLRB must conform to the judiciary’s definitions.

In short, based on the D.C. Circuit’s ruling, the NLRB is permitted to apply its legal joint employer test in distinct situations, but it cannot fundamentally change the joint employer standard, whether by adjudication or rulemaking. Ultimately, unless the U.S. Supreme Court weighs in on the BFI case appeal, this issue will remain a subject of debate.

For more information, contact Rebecca J. Bernhard.

In Case You Missed It

California Privacy Law Update.  A number of amendments to the California Consumer Privacy Act are under consideration during this year’s legislative session that would significantly impact the treatment of data, customer loyalty programs and consumer request methods.

Trade Updates.  Our trade team comments on and summarizes the state of play this summer on trade dynamics between the U.S. and China.

Delaware Law Updates.  Delaware continues to promote the use of electronic signatures, making it clear that even transactional and M&A related documents are enforceable when delivered and signed electronically.

SEC Proposes Revisions to Business and Risk Factor Disclosures.  The proposal would reduce the number of specific disclosure requirements and move to a more principles-based approach.  Our eUpdate goes through some of the history and summarizes the significance of the proposed changes.

Notes from All Over

India Policy Update.  Several policy proposals to encourage foreign investment are working their way through India’s national budget discussions.  This memo from Cyril Amarchand covers some highlights.

Chemical Industries Association Sends Message to New Prime Minister.  Remember when Brexit felt like the most disruptive event out there impacting global trade?  Those were the good old days.  That said, Brexit remains huge for the chemical industry.  In a short press release, the UK’s chemical association (Chemical Industries Association) indicated the continuing importance of a Brexit deal to the industry.  We agree.  It’s relatively easy to move management and sales offices when conditions on the ground merit, but moving manufacturing facilities to avoid punitive taxes or tariffs is a different matter.  Without a Brexit deal, manufacturers will bear the brunt of the impact.

New York Looks to Lead in Green.  A few weeks ago, the State of New York passed into law the Climate Leadership and Community Protection Act that will require the state to have 100% renewable energy within 30 years.

Exxon Hit with Another Climate Change Lawsuit.  Following the case filed by the New York AG’s office last year and Texas cases earlier this year alleging Exxon misled investors about the impacts of climate change on its business, a derivative suit was filed in New Jersey last week making similar claims.

Amazon hit with 1,000 Proposition 65 Notices.  We have commented in prior issues about the amendments to Proposition 65 and how they facilitate claims against the platforms and the upstream providers.  Amazon has been hit hard as a result.

Corporate and M&A

Blue Bell Ice Cream and Board Oversight

Derivative suits claiming a failure of a board to maintain proper oversight are, at their core, about whether a board has overseen the implementation of sufficient internal controls and compliance measures.  These claims are usually hard to make stick.  But, in this decision, authored by Chief Justice Strine, the Delaware Supreme Court found enough in the pleadings to overturn a dismissal at the Chancery Court level and send it to trial.

The claims related to the outbreak of listeria in Blue Bell Ice Cream’s products, which the Department of Agriculture traced to all three of the company’s plants.  Three customers died between 2010 and 2015, and Blue Bell’s operations were materially disrupted.  The Chief Justice noted that the plaintiff had alleged “particularized facts that support a reasonable inference that the Blue Bell board failed to implement any system to monitor Blue Bell’s food safety performance or compliance.”  The allegations claimed that the Blue Bell board had no committee or particular process for food safety.

In the end, the case is a good reminder of the need for boards to be able to show how they are overseeing an effective compliance program.  One key takeaway is the importance of the record.  The board minutes and materials are the record looked at in these cases to find evidence as to whether the Board did its duty or not.  Cases like this reinforce the importance of including sufficient information about the Board’s deliberations to provide support in the event of an allegation that the Board hasn’t fulfilled its duty of care.

For more information, contact Troy Keller.

FTC Blocks Merger of Hydrogen Peroxide Producers

Antitrust has been much in the news of late, with big tech getting most of the headlines.  In the background, the FTC continues to actively review industry transactions.  Last year, it blocked Tronox’ proposed acquisition Cristal, leading to a settlement earlier this year.

Last week, the FTC announced it was taking action to block Evonik Industries AG’s proposed $625 million acquisition of PeroxyChem Holding Company. For most transactions in the Chemical industry, regulators tend to take the view that the relevant market is national or even global.  Here, the FTC took the position that the market for the relevant products was regional (Pacific Northwest) and argues that the merger would leave just one other Hydrogen Peroxide manufacturer in that region.  Interestingly, the FTC also pointed to a “history of strong interdependent behavior” among Hydrogen Peroxide suppliers and argued that the market was “vulnerable to coordination.”

Evonik has said they will fight the decision in court.

For more information, contact Troy Keller.

Firm Highlights

Insights

EPA Limits Title V Re-Litigation of NSR Permits

Overview On September 25, 2026, the U.S. Environmental Protection Agency (“EPA”) published a final rule that significantly limits the ability of third parties to use the Clean Air Act (“CAA”) Title V permitting process to revisit New Source Review (“NSR”) permitting decisions years after those decisions were made. The rule establishes that NSR permitting determinations generally must be challenged during the original permitting proceeding, thereby providing regulated sources with greater permitting certainty and finality for major capital projects. Published in the Federal Register titled Clarifying the Scope of “Applicable Requirements” Under State Operating Permit Programs and the Federal Operating Permit Program (Docket ID No. EPA-HQ-OAR-2023-0401), the rule amends 40 C.F.R. Parts 70 and 71 to codify EPA’s interpretation regarding when requirements established under other CAA programs may be reviewed, modified, or implemented through the Title V operating permit program. The rule becomes effective 30 days after publication. The rule addresses two principal issues: (1) the relationship between NSR preconstruction permitting and Title V operating permits, and (2) the treatment of the General Duty Clause under CAA section 112(r)(1). Most significantly, the rule provides greater certainty for sources navigating the NSR permitting process. EPA’s amendments are intended to ensure that NSR permitting decisions made through an approved public process are generally not revisited later through Title V permit proceedings. The rule responds to a circuit split between the U.S. Courts of Appeals for the Fifth and Tenth Circuits. In Environmental Integrity Project v. EPA, 969 F.3d 529 (5th Cir. 2020), the Fifth Circuit upheld EPA’s interpretation, concluding that it was consistent with the text, structure, and purpose of Title V. In contrast, the Tenth Circuit reached the opposite conclusion in Sierra Club v. EPA, 964 F.3d 882 (10th Cir. 2020), finding that the then-existing regulatory definition of “applicable requirement” did not support EPA’s position. By amending the regulatory language on which the Tenth Circuit relied and codifying the interpretation approved by the Fifth Circuit, EPA has established a nationwide framework governing the interaction between NSR and Title V. NSR and Title V: EPA Establishes a Uniform Nationwide Framework At the core of the rule is EPA’s effort to define the respective roles of NSR and Title V. The rule codifies the approach EPA has applied since 2017: once a source obtains an NSR permit under an EPA-approved permitting program, and that permit was issued following public notice with an opportunity for comment and judicial review, the permit establishes the NSR-related “applicable requirements” of the State Implementation Plan (“SIP”) or Federal Implementation Plan (“FIP”) for Title V purposes. Under this framework, Title V is not a vehicle for re-examining underlying NSR permitting decisions. EPA does not intend to use the Title V process to revisit applicability determinations, emissions calculations, control technology determinations, permit conditions, or other issues resolved through the NSR permitting process. This principle applies regardless of the stage of the Title V proceeding; whether the NSR permit was issued pursuant to a SIP or FIP; the type of NSR issue involved; or whether the NSR permit is incorporated into Title V sequentially or concurrently. Limited Exceptions EPA recognizes several circumstances in which NSR issues may still be reviewed through the Title V program: No NSR permit was issued at all; The permit was issued without public notice and an opportunity for comment and judicial review; or The issue involves substantive overlap between Title V and NSR requirements, such as the adequacy of monitoring provisions. As a result, the rule does not insulate unpermitted projects or foreclose review of matters that independently arise under Title V. Key Regulatory Amendments The rule revises the definition of “applicable requirement” in 40 C.F.R. §§ 70.2 and 71.2. Paragraph (1): Where an NSR permit is issued with public notice and an opportunity for comment and judicial review, the permit establishes and defines the applicable SIP or FIP requirements for Title V purposes. Paragraph (2): All NSR permit terms, including terms contained in minor NSR permits, constitute applicable requirements that must be incorporated into Title V permits. Paragraph (4): CAA section 112(r)(1) (the General Duty Clause) is expressly excluded from the definition of “applicable requirement,” while section 112(r)(7) Risk Management Program requirements remain included. EPA also amended 40 C.F.R. §§ 70.8 and 70.12 to clarify that alleged defects in requirements established outside the Title V process generally do not provide a basis for EPA objection to a Title V permit or for a Title V citizen petition. General Duty Clause Exclusion The rule also codifies EPA’s longstanding position that the General Duty Clause in CAA section 112(r)(1) is not an “applicable requirement” for Title V purposes. EPA points to several considerations supporting that conclusion, including the distinction between the General Duty Clause and Title V permit terms, the provision’s origins in the Occupational Safety and Health Act’s general duty clause, and the different enforcement structures applicable to the General Duty Clause and Title V permit requirements. Importantly, excluding section 112(r)(1) from the definition of “applicable requirement” does not eliminate EPA’s authority to enforce the General Duty Clause independently of the Title V program. The final rule instead clarifies that the General Duty Clause need not—and should not—be incorporated into Title V permits as an applicable requirement. Practical Implications for Regulated Sources Greater Finality for NSR Permits  For projects requiring PSD, nonattainment NSR, or minor NSR permits, the permitting process becomes the primary forum for resolving disputes regarding applicability determinations, emissions calculations, control technology requirements, offsets, and permit conditions. Once an NSR permit is issued through a qualifying public process, regulated sources should face substantially reduced risk that those same issues will be challenged years later through Title V permit proceedings. Reduced Risk of Collateral Permit Challenges Stakeholders have sometimes sought to use Title V permit issuance, renewal, revision, or citizen-petition proceedings to challenge underlying NSR determinations. The final rule makes clear that Title V is not the appropriate vehicle for challenging whether an applicable requirement was correctly established in the first instance. This should reduce the risk of permit delays and uncertainty associated with collateral challenges to previously issued NSR permits. The rule does not, however, eliminate all Title V challenges relating to an NSR permit. Challenges concerning the Title V permit itself—including whether it appropriately incorporates applicable requirements or contains adequate compliance provisions—remain possible. Increased Importance of the Initial NSR Proceeding Because Title V generally will not provide a second opportunity to challenge the substantive validity of an NSR determination, the administrative record developed during the NSR process becomes increasingly important. Permit applicants should ensure that applicability analyses, emissions calculations, control technology evaluations, modeling demonstrations, and supporting technical documentation are thoroughly developed during the original permitting proceeding. For significant projects, applicants may therefore have an additional incentive to identify and resolve potential permitting issues before the NSR permit is issued rather than assuming that unresolved issues can be addressed during a subsequent Title V proceeding. Potential Incentive for Broader Public Participation EPA also notes that permitting authorities may choose to provide public notice and an opportunity for comment for a broader range of NSR permits because permits issued through a qualifying public process receive the benefit of the finality framework established by the rule. Some permitting authorities may conclude that greater public participation at the NSR stage is preferable to uncertainty during subsequent Title V proceedings. Conclusion The final rule is principally a permitting-certainty measure. For sources that obtain NSR permits through a public process, EPA has substantially limited the ability of third parties to revisit underlying NSR determinations through the Title V program. As a result, regulated entities should benefit from greater finality regarding key permitting decisions, reduced risk of collateral permit challenges, and increased certainty when planning and implementing capital projects.

Insights

SEC Proposes Expansion of Investment Adviser Performance-Based Compensation Rule

On September 30, 2026, the Securities and Exchange Commission (the “SEC”) proposed amendments to Rule 205-3 under the Investment Advisers Act of 1940, as amended (the “Advisers Act”), which provides an exemption from the general prohibition under Section 205(a)(1) of the Advisers Act on registered investment advisers receiving performance-based compensation (the “Proposal”) so long as performance-based compensation is limited to “qualified clients”.1 Most notably for private fund sponsors, the Proposal would expand the definition of “qualified client” to include any investors that satisfy the “accredited investor” definition under Regulation D. The Proposal may also have implications for private fund managers that rely on exemptions from investment adviser registration under state law because certain state-level investment adviser registration exemptions incorporate or otherwise reference the federal qualified client definition. Expansion of the Qualified Client Definition Under the current Rule 205-3, an investor generally may qualify as a qualified client if, among other alternatives, the investor has at least $1.4 million under management with the adviser or has a net worth exceeding $2.7 million. These thresholds are higher than the financial thresholds applicable to many accredited investors under Regulation D. As a result, an investor may currently qualify as an accredited investor for purposes of investing in a private offering without qualifying as a qualified client for purposes of paying performance-based compensation. The Proposal would expand the qualified client definition to include any natural person or legal entity investor that satisfies the accredited investor definition under Regulation D. The Proposal would also remove the assets under management and net worth thresholds under the current Rule 205-3 qualified client test. For private funds relying on Section 3(c)(1) of the Investment Company Act of 1940, this change could reduce the need to apply a separate qualified client standard to investors that already qualify as accredited investors. Dorsey Observations and Next Steps If adopted as proposed, the expanded qualified client definition could be particularly significant for private fund managers. Most private fund offerings are already limited to accredited investors under Regulation D. However, the Proposal could expand the pool of prospective investors available to emerging private fund managers while reducing the regulatory burden associated with complying with Rule 205-3. The Proposal could also benefit advisers operating below the SEC registration threshold that rely on a state private fund adviser exemption. A number of states have adopted exemptions modeled on the North American Securities Administrators Association (“NASAA”) private fund adviser exemption, which may condition relief for advisers to certain funds relying on Section 3(c)(1) on each beneficial owner satisfying the federal qualified client definition. However, state requirements vary, and any effect of the Proposal would depend on the text of the applicable state exemption and how it incorporates Rule 205-3. Many emerging private fund managers may have a larger network of accredited investor relationships than qualified client relationships during the early stages of their investment advisory business. Currently, under Rule 205-3, private fund managers may receive performance-based compensation from investors who do not satisfy the qualified client definition if those investors were admitted to their private funds prior to registration with the SEC. Following registration with the SEC, however, managers may continue to permit investors that are not qualified clients to invest in future private funds but may not receive performance-based compensation from those investors with respect to such investments. In addition, because the net worth and assets under management thresholds for qualified client status are adjusted for inflation every five years, the pool of qualified client investors may diminish over time as previously eligible investors no longer satisfy the applicable thresholds. The Proposal could provide the dual benefit of greater flexibility for private fund managers to establish and maintain relationships with accredited investors as their businesses scale and they become registered with the SEC, and greater flexibility for certain accredited investors to participate in investment strategies that historically have been restricted to much larger institutional investors. Unless and until the Proposal is adopted, investment advisers should continue to comply with the existing qualified client requirements. If the Proposal is adopted, private fund sponsors should consider whether corresponding changes are appropriate for their subscription documents, investor questionnaires, and other offering materials. Advisers that are state-registered or rely on a state-level exemption should also consult the laws and regulations of each relevant jurisdiction before changing investor eligibility standards or performance-based compensation practices, because adoption of the federal amendments may not automatically modify state requirements. Comments on the Proposal will be due 60 days after publication in the Federal Register. 1 Investment Adviser Performance-Based Compensation Modernization, Investment Advisers Act Release No. IA-7022 (Sept. 30, 2026), available at https://www.sec.gov/rules-regulations/2026/09/s7-2026-28#33-11443proposed.

Insights

Energy Law: Month in Review - September 2026

Welcome to Dorsey’s Energy Law: Month in Review. We provide this update to our clients to identify significant developments in the previous month. Please reach out to any of the authors, listed above, to discuss these issues. Regulatory Developments Massachusetts Ratchets Up State and Local Regulation of AI Data Centers In early September, Governor Maura Healey of Massachusetts signed an executive order requiring that artificial intelligence data centers secure the approval of local communities as a precondition to proceeding with a given project. According to the terms of the order, data center developers will need to secure a “community benefits agreement” as a precondition to receiving permits from numerous state agencies, including the Department of Environmental Protection, the Energy Facilities Siting Board, and the Massachusetts Environmental Policy Act Office. Beyond requiring community benefits agreements, the order also mandates that developers mitigate utility costs to consumers, prohibits the use of nondisclosure agreements, and requires various state agencies to develop measures to limit data center impacts on the environment. North Carolina Regulators Decline Approval of Duke Energy Gas Turbine On September 18, 2026, North Carolina Utilities Commission (NCUC) denied Duke Energy’s application for a certificate of public convenience and necessity required to construct a gas-fueled combustion turbine at its Smith Energy Complex in North Carolina. The NCUC objected strongly to the $584 million price tag and noted that Duke appeared to be constructing the facility “based on anticipated data center customer additions.” The NCUC rejected that anticipated growth as “insufficiently reliable for the Commission to act at this point.” In rejecting Duke’s application, the NCUC also noted that Duke had signed the White House Ratepayer Protection Pledge, in which it represented that it would not shift data center costs to consumers. The NCUC observed that the record did not demonstrate how Duke “intends to adhere to its commitments under the Ratepayer Protection Pledge with regard to the Proposed Facility.” Notably, commission staff had actually supported the construction of the turbine, citing concerns about Duke’s reserve margins. The NCUC noted that it “understands the Public Staff’s expressed concerns,” but those concerns were outweighed by the NCUC’s reservations, including questions of demand. Department of Energy Approves Funds for Grid Improvement The U.S. Department of Energy (DOE) recently announced that it would fund 31 grid-improvement projects in 26 states. The funding initiative is part of the DOE’s “SPARK” initiative. The funding will include $1.9 billion in federal funding from DOE and $3.35 billion in recipient cost-sharing funding. The funds will go to projects designed to improve grid reliability and lower electricity costs. Recipients plan to reconductor over 1,500 miles of transmission lines and will deploy grid-enhancing technologies across approximately 21,000 miles. DOE stated that this initiative will make available over 23 additional gigawatts of electricity. Texas Moderates Rules Governing Data Center Interconnection The Texas Public Utility Commission adopted new regulations governing large-load interconnections. The rules impose a flat study fee of $100,000 for all proposed interconnections, which departs from the initial proposal to impose study fees using a tiered system based on project size. Additionally, the final rule eliminates the PUC’s previous proposal to impose a non-refundable interconnection fee of $50,000 per MW of contracted peak demand. The final rule also moderates the initially proposed regulations governing Electric Reliability Council of Texas (ERCOT) notifications for large-load customers’ non-utilized capacity. The proposed rules would have required notifying ERCOT within 30 days of missing a scheduled energization milestone by six months. The final rules, however, do not require informing ERCOT unless a scheduled energization milestone is missed by 24 months. FERC Denies TransAlta 202(c) Cost-Recovery Plan The Federal Energy Regulatory Commission (FERC) recently rejected TransAlta’s plan to recover $19.9 million in expenses stemming from a DOE order in which DOE prohibited TransAlta from retiring its coal-powered Centralia power plant. TransAlta had previously intended to retire the facility at the end of 2025. TransAlta’s cost recovery plan proposed spending an additional $23 million on repairs to continue operating the unit. FERC’s main objection had to do with geographic scope. TransAlta’s recovery plan called for recovering costs from California Independent System Operator (CAISO) and the Southwest Power Pool (SPP), but the DOE’s order requiring operation of the plant was designed to ensure reliability in the Northwest assessment area (Montana, Oregon, Washington, and parts of northern California and northern Idaho). Accordingly, FERC was unwilling to allow cost recovery from CAISO and SPP when the order that precipitated the additional costs only related to the Northwest assessment area. FERC informed TransAlta that it would only approve cost recovery from load-serving entities in the Northwest assessment area. FERC’s decision comes amid a rush of DOE emergency orders requiring the continued operation of coal-fired generating units. Litigation Appeals Court Upholds Washington Hydropower Plant With Caveats In a September 21, 2026, opinion, the Washington Court of Appeals largely upheld a Clean Water Act water quality certification by the Washington Department of Ecology for the Goldendale Energy Storage Project, a proposed pumped-water storage hydropower system adjacent to, but off-stream from, the Columbia River. A nonprofit (Columbia Riverkeeper) and the Confederated Tribes and Bands of the Yakama Nation appealed the certification, contending that it failed to impose necessary conditions and monitoring requirements to protect the water quality of the Columbia River. Most saliently, the plaintiffs argued that the project had the potential to leak 100 acre-feet of water per year into tributaries of the Columbia River. The Court of Appeals broadly rejected plaintiffs’ challenge to the state’s conclusion that “the project was designed not to leak.” That said, the Court of Appeals did reverse on one narrow issue. Specifically, the court determined that the state’s conclusion that “leakage from the project’s tunnels would be monitored and reported” was not supported by the evidence because the certification “does not explicitly require monitoring and reporting to determine whether there is any leakage.” Accordingly, the court remanded the matter to the state to impose monitoring and reporting requirements but otherwise affirmed the certification. Legislative Developments California Legislates Restrictions on Data Center Energy Use and Grid Costs On September 21, 2026, California Governor Gavin Newsom signed seven bills broadly regulating data centers in the state. SB 1168 directed the California Public Utilities Commission to assess the energy used by data centers. It also requires the PUC to pass costs of transmission and distribution upgrades and load increases on to data centers, rather than customers. SB 886 and SB 887 compel data centers to pay for infrastructure upgrade and generation costs, and wildfire mitigation costs, in addition to imposing environmental review. The statutes additionally increase local oversight of data centers. AB 1577 imposes a monthly reporting requirement that requires data centers to supply energy consumption and efficiency data to the California Energy Commission. AB 2383 contains incentives for data centers to use onsite clean energy generation. Finally, AB 2469 and AB 2619 require data center developments to assess water supply and develop a water scarcity plan. The statutes also mandate statewide water reporting as a precondition to obtaining and renewing business licenses.

Insights

The Supreme Court Update - October 8, 2026

On September 29, 2026, the Supreme Court granted certiorari in one case: Department of Homeland Security v. D.V.D., No. 26-426: This case concerns the Trump Administration’s “third-country removal” procedures, where immigrants are deported to countries not listed in the removal orders. In granting certiorari, the Court granted the Government’s application to stay a lower court decision halting the practice, which will allow third-country removals to continue pending resolution of the case. The issues presented are: (1) Whether the district court had jurisdiction over respondents’ claims; (2) whether the district court had authority to enter class-wide declaratory relief and APA vacatur under 8 U.S.C. § 1252(f)(1); (3) whether the Government’s guidance on third-country removals is unlawful under 8 U.S.C. § 1231(b), the due process clause, or FARRA/CAT and its implementing regulations; and (4) such other questions that the Government determines are appropriate for the proper disposition of the case. On October 1, 2026, the Court granted certiorari in three additional cases: Rhoney v. Barbosa da Cunha, No. 26-104: Immigration officials detained Ricardo Aparecido Barbosa da Cunha—a Brazilian citizen who had lived in the United States for approximately twenty years after entering without inspection—and denied him a bond hearing under 8 U.S.C. § 1225(b)(2)(A). The Second Circuit held that his detention was instead governed by § 1226(a), which permits release on bond, because § 1225(b)(2)(A)’s mandatory-detention requirement applies only to noncitizens apprehended while entering the country or shortly thereafter. The question presented is: Whether 8 U.S.C. § 1225(b)(2)(A) mandates the detention pending removal proceedings of aliens who, like Barbosa da Cunha, are present in the United States without having been admitted. Missionaries of St. John the Baptist, Inc. v. Frederic, No. 25-113: A Catholic religious organization sought to build a shrine to the Virgin Mary on land the organization owned adjacent to its church in Park Hills, Kentucky. Local zoning restrictions prohibited the proposed construction. The question presented is: Whether a land-use regulation that prohibits a religious institution from building a religious structure on its own property constitutes a “substantial burden” on religious exercise under the Substantial Burden Provision of the Religious Land Use and Institutionalized Persons Act, 42 U.S.C. § 2000cc(a). Marschner v. Marschner, No. 25-1349: Under the Uniformed Services Former Spouses’ Protection Act (“USFSPA”), a veteran’s longevity-based retirement pay can be divided in a divorce, but retirement pay based on disability and retirement pay that was waived to receive disability pay are indivisible. The question presented is: Does the USFSPA require state courts to refuse enforcement of indemnification provisions in a divorce settlement agreement?