Client Alert

NEPA Regulations Unravel

February 19, 2025

by Michael Drysdale and Alyssa Florack-Hess

Download as a PDF

Share this page

The National Environmental Policy Act, or NEPA,[1] is in the midst of a major judicial and regulatory shakeup. In the past three months, four major events have thrown the validity of NEPA regulations into doubt:

  1. On November 12, 2024, a panel at the D.C. Circuit Court of Appeals issued a bombshell ruling in Marin Audubon Society v. Federal Aviation Authority.[2] The majority opined that the regulations implementing NEPA -- first issued by the Council on Environmental Quality (CEQ) in the 1970s and the subject of thousands of cases of NEPA precedent -- are void in their entirety because the CEQ does not have rulemaking authority. This opinion was sufficiently alarming that all parties to the litigation sought panel reconsideration through en banc review;
  2. On January 20, 2025, the Trump Administration issued Executive Order 14154 “Unleashing American Energy,” which among other things directed the CEQ to evaluate rescinding the CEQ’s NEPA regulations;[3]
  3. On January 31, 2025, the D.C. Circuit denied en banc review of the Marin Audubon Society decision, with a majority of the judges reasoning that the portion of the opinion holding that CEQ regulations were void was likely dicta; and,
  4. On February 3, 2025, the District Court for the District of North Dakota adopted the reasoning of Marin Audubon Society and concluded that the CEQ NEPA regulations are invalid for “everyone” in Iowa v. CEQ.[4]

NEPA in a Nutshell

NEPA was the first major federal environmental statute and requires federal agencies to consider the environmental impacts of their proposed actions. Nearly all federal decisions that have the potential for physical impacts on the environment must satisfy NEPA requirements, which may come in the form of an environmental impact statement, an environmental assessment, or a determination that the action qualifies for a “categorical exclusion.” NEPA compliance can add years to project timelines and is a potent source of litigation risk.

The D.C. Circuit’s Decision in Marin Audubon Society

Marin Audubon Society involved a routine NEPA dispute, where environmental groups argued that federal agencies had been lax in regulating tour flights over national parks. The case seemed an unlikely one to result in a significant curtailment of the NEPA regulations. A key part of the parties’ disagreement was whether the agencies had complied with CEQ regulations, and while the court unanimously held the agencies had failed to meet NEPA’s requirements on other grounds, two of the three judges hearing the case went far beyond the arguments made by either side and ruled that CEQ never had the authority to issue binding regulations in the first place.

In doing so, the two judges, both appointed during the George H.W. Bush’s Administration,[5] answered a question neither side had asked or argued. The majority reasoned that a federal agency does not have the authority to issue binding law unless Congress explicitly delegates its legislative power, and while Congress has done so for many agencies, the majority determined that Congress merely intended for the CEQ to be an advisory committee. While several other circuit courts made similar holdings during the 1970s, this line of holdings ended with the Supreme Court’s 1979 ruling that CEQ’s NEPA regulations are “entitled to substantial deference” in Andrus v. Sierra Club,[6] after which essentially every court considered CEQ’s regulations to be authoritative law. However, in Marin Audubon Society, the D.C. Circuit dismissed this Supreme Court statement as a “stray remark,” reigniting an argument that has not been seen in decades.

The D.C. Circuit Denies En Banc Review

Shortly after the opinion was issued, all parties in the case petitioned for en banc rehearing before all 11 judges on the D.C. Circuit, with environmental groups describing their frustration that the November 12 decision had left them “worse off than if they had never brought this case” because of the court’s failure to consider the wide-reaching effects its novel answer would have or to limit those effects in any meaningful way. [7] Likewise, the federal agencies involved argued that en banc review was warranted to “address this question of exceptional importance.”[8]

On January 31, 2025, the D.C. Circuit denied the petitions for review, leaving its November 12 decision in place.[9] However, seven of the eleven judges on the D.C. Circuit provided a statement to explain their denial. The statement -- authored by Chief Judge Srinivasan, the dissenter in Marin Audubon Society -- agreed with the parties that the panel opinion violated the well-established rule that courts should not consider arguments not presented to them by the parties. The statement went on to conclude that there was nevertheless no cause to grant en banc rehearing, because the court had unanimously determined that the federal agencies had violated NEPA on completely separate grounds, and therefore the challenged portion of the opinion was “unnecessary to the panel’s disposition.”

The North Dakota District Court Invalidates NEPA Regulations

To the extent the D.C. Circuit’s January 31st en banc statement was intended to limit the fallout of the Marin Audubon Society panel opinion, it failed. Just four days later, the District Court of North Dakota issued its opinion in Iowa v. CEQ, which fully endorsed the Marin Audubon Society panel opinion’s reasoning and explicitly invalidated CEQ’s existing NEPA regulations nationwide. After reviewing additional briefing based on the Marin Audubon decision, the District Court ruled in favor of 21 state governments, vacating CEQ’s 2024 regulations.[10] The court’s decision rested in large part on its finding that the plain text of NEPA did not give CEQ authority to issue binding regulations and thus that President Carter’s Executive Order that federal agencies follow CEQ regulations exceeded Congress’ initial delegation of authority.[11]

NEPA Chaos Ahead

If the decision in Iowa v. CEQ is not overturned by the Eighth Circuit or Supreme Court, [12] there will be significant legal and practical implications for all federal agencies and any private actor doing a project that requires federal approvals. 

In short, CEQ’s existing regulations provide the playbook for compliance with the NEPA statute. The statute is short, broad, and vague[13] while the regulations are detailed and backed by 50 years of precedent. Federal agencies have historically relied on CEQ’s regulations, both to guide their procedures to comply with NEPA and to use as a defense that they have done so. Conversely, if an agency failed to follow CEQ’s regulations, environmental groups had a straightforward argument the agency had violated NEPA. Notably, CEQ’s issuance of the original regulations in 1978 contributed to ending a wave of lawsuits and conflicting court decisions about what agencies must do to comply with the statute. 

If Iowa v. CEQ is not overturned, agencies may still be able to argue that CEQ’s vacated regulations and precedent reflect a reasonable interpretation of NEPA’s mandate and thus that an action in compliance with CEQ’s rules should presumptively comply with the statute, but this is at best weakly persuasive. Executive Order 14154, issued on January 20, 2025, would undermine even this argument, leading to worsened chaos. The Executive Order called for the CEQ to propose rescinding its NEPA regulations by February 21, 2025. If these regulations are fully rescinded, it would effectively circumvent any possible appeals of Iowa v. CEQ and solidify the bombshell impacts of these recent cases as law.

These uncertainties are further compounded by the Supreme Court’s curtailment of deference to agency interpretations of statutes in last Term’s Loper Bright decision.[14] Without clear regulations to validate agency actions and with a general doubt about agency authority, agencies and project proponents are left to guess what decisions will survive judicial review. This cuts both ways. An agency with a favorable judicial draw is more likely to have its decisions upheld against challenges that the agency did not check all the NEPA boxes, and a judicial skeptic of agency action has greater freedom to hold that the agency’s decisions are unreasonable.

The Trump Administration almost certainly views the Marin Audubon Society and Iowa v. CEQ decisions as favorable developments in its assault on the “Administrative State.” Yet an important theme in the cases is the limitations in governance by Executive Order, and for both NEPA and other areas of law, they may be exemplars of the Law of Unintended Consequences.



[1] 42 U.S.C. §§ 4321 et seq.

[5] U.S. Court Appeals Dist. Columbia Circuit, Karen LeCraft Henderson, available at https://www.cadc.uscourts.gov/content/karen-lecraft-henderson; U.S. Court Appeals Dist. Columbia Circuit, A. Raymond Randolph, available at https://www.cadc.uscourts.gov/content/raymond-randolph.

[6] 442 U.S. 347 (1979), available at https://www.loc.gov/item/usrep442347/.

[7] The environmental groups’ November 27, 2024 petition is not publicly available but is accessible through the D.C. Circuit’s website after creating a PACER account at https://ecf.cadc.uscourts.gov/.

[8] The federal agencies’ December 5, 2024 petition for en banc rehearing is not publicly available but is accessible through the D.C. Circuit’s website after creating a PACER account at https://ecf.cadc.uscourts.gov/.

[9] This order is available at https://media.cadc.uscourts.gov/opinions/docs/2025/01/23-1067-2097987.pdf. The order also denied the environmental groups’ separate petition for a panel rehearing.

[10] The court limited its remedy to vacating the 2024 regulations because the case did not concern the previous 2020 regulations. ¶ 131. Despite noting that the 2020 regulations were likely also invalid for the same reasons, this remedy resulted in reinstating the 2020 regulations. Id.

[11] ¶ 36. The District Court provided an alternative basis for its decision “in the event another court decides CEQ has valid rule-making authority.” ¶ 62. The court additionally ruled that certain portions of the May 2024 regulations were arbitrary and capricious or otherwise exceeded CEQ’s authority under NEPA by changing the stated purpose of NEPA, requiring agencies to prioritize global effects over domestic interests, and requiring periodic review for all categorical exclusions.

[12] The Iowa v. CEQ decision reduces the likelihood that the Marin Audubon Society decision will be directly heard by the Supreme Court. Because of the uncertainty over whether the panel opinion sections on CEQ’s authority are dicta, the Court may choose to wait for the Iowa v. CEQ decision to work its way through appeals.

[13] The Supreme Court is currently reviewing the meaning of some of these vague statutory requirements in Seven County Infrastructure Coalition v. Eagle County, Colorado. After hearing oral arguments on December 10, 2024, the Court seems likely to provide additional guidance interpreting NEPA’s provisions related to the scope of review.

[14] Loper Bright Enterprises v. Raimondo, 144 S. Ct. 2244 (2024), available at https://www.supremecourt.gov/opinions/23pdf/22-451_7m58.pdf.

Firm Highlights

Insights

Ninth Circuit Splits California’s Climate Disclosure Laws: Scope 1 and 2 Reporting Proceeds; Scope 3 and SB 261 Likely Unconstitutional

Key Takeaways On November 9, 2026, the Ninth Circuit in Chamber of Commerce v. Sanchez allowed Scope 1 and Scope 2 greenhouse gas (GHG) emissions reporting under SB 253 to proceed but held that SB 253’s Scope 3 requirement, and SB 261 in its entirety, likely violate the First Amendment.1 U.S.-formed entities with total annual revenues above $1 billion that do business in California remain subject to Scope 1 and 2 reporting. First reports (or, for eligible entities, statements of non-reporting) were due November 10, 2026.2 Scope 3 reporting (scheduled to begin in 2027) and SB 261 climate-risk reporting are effectively on hold. Entities with revenues between $500 million and $1 billion, which were covered only by SB 261, currently have no reporting obligation under either law.3 The ruling addresses only preliminary injunctive relief; it is not a final judgment on the merits. If the district court finds the Scope 3 requirement non-severable, it could also enjoin Scope 1 and 2 reporting.4 Background SB 253 (the Climate Corporate Data Accountability Act) requires U.S.-formed entities with total annual revenues above $1 billion that do business in California to report Scope 1 and 2 emissions starting in 2026 and Scope 3 emissions starting in 2027, with penalties of up to $500,000 per reporting year.5 SB 261 (the Climate-Related Financial Risk Act) requires U.S.-formed entities with total annual revenues above $500 million that do business in California to publish biennial climate-related financial risk reports consistent with the Task Force on Climate-related Financial Disclosures (TCFD) framework, with penalties of up to $50,000 per reporting year.6 Business groups led by the U.S. Chamber of Commerce challenged both laws as compelled speech that violates the First Amendment. In August 2025, the district court denied their motions for preliminary injunctions. On November 18, 2025, the Ninth Circuit enjoined SB 261 pending appeal but declined to enjoin SB 253.7 The implementing regulation adopted by the California Air Resources Board (CARB) took effect on October 12, 2026, and set November 10, 2026, as the first Scope 1 and 2 reporting deadline.8 The Court’s Decision Scope 1 and Scope 2: Upheld for Now The panel held that Scope 1 and 2 disclosures are commercial speech because they compel disclosure of factual information about emissions from a company’s own operations and purchased energy—information that bears on capital transactions. Applying intermediate scrutiny, the court concluded that the requirements advance California’s substantial interests in reducing information asymmetries for investors and in reducing emissions and are no more extensive than necessary.9 The panel split 2–1 on this issue.10 Scope 3: Likely Unconstitutional The court held that Scope 3 disclosures concern diffuse third-party conduct across the value chain and are “insufficiently tethered” to the reporting entity’s own operations to qualify as commercial speech. Applying strict scrutiny, the court concluded that the requirement likely fails because (1) SB 253 does not require primary data, (2) the record did not show that companies’ proxy-based estimates would be more reliable than estimates the State could generate itself, and (3) the link to investor-relevant risk was too remote.11 SB 261: Likely Unconstitutional in Its Entirety The court held that SB 261 compels noncommercial speech because it requires “predictive and normative judgments” about a “politically fraught subject.” Even assuming California’s interests are compelling, the court reasoned that the law is likely not narrowly tailored because California could use less restrictive alternatives, such as incentives for voluntary disclosure.12 The panel was unanimous on Scope 3 and SB 261.13 Remand and Severability The Ninth Circuit did not enter injunctions itself. It reversed the denials of preliminary injunctive relief and remanded with instructions for the district court to enter relief consistent with the opinion and, for Scope 3, to decide severability first.14 SB 253 contains an express severability clause. If the district court nevertheless finds the Scope 3 requirement non-severable, it could also enjoin Scope 1 and 2 reporting.15 Current Status at a Glance Requirement Status after the Ruling Practical Effect SB 253 – Scope 1 and 2 emissions (entities with revenues above $1 billion) In effect; denial of preliminary injunction affirmed First reports were due November 10, 2026; CARB fee notices expected by December 10, 202616 SB 253 – Scope 3 emissions (scheduled to begin in 2027) Likely unconstitutional; remanded for severability ruling and entry of injunctive relief Not required while remand is pending; scope of CARB’s 2027 rulemaking uncertain17 SB 261 – climate-related financial risk reports (entities with revenues above $500 million) Likely unconstitutional in its entirety; enjoined pending appeal since November 18, 2025 No current reporting obligation; voluntary reports permitted18 What to Watch Any petition for panel rehearing or rehearing en banc (due 14 days after entry of judgment) and any petition for a writ of certiorari to the U.S. Supreme Court.19 The district court’s severability ruling and the scope of any preliminary injunctions it enters as to Scope 3 and SB 261.20 CARB’s response. As of the date of this alert, CARB has not issued a formal statement on the opinion.21 CARB had been developing a second rulemaking for reporting years 2027 and later, addressing Scope 3, assurance, deadlines, and reporting templates, and had proposed retaining November 10 as the annual deadline.​​​​​​​22 Recommended Actions Confirm coverage entity by entity. Revenue (gross receipts, based on the lesser of the two prior fiscal years) and “doing business in California” are determined separately for each entity; affiliates are not aggregated. Retain supporting California tax records for five years.23 If a covered entity has not filed, file promptly. Submit the Scope 1 and 2 report (or, if eligible, a statement of non-reporting) and document good-faith compliance efforts, which CARB must consider in assessing penalties.24 Calendar the fee cycle. CARB expects to issue fee notices by December 10, 2026, with payment due within 60 days after the notice; each day of nonpayment is a separate violation.​​​​​​​25 CARB’s August 2025 proposal set flat fees at $3,106 per SB 253 entity and $1,403 per SB 261 entity.26 Confirm the final amount when the CARB notice arrives. Prepare for 2027 Scope 1 and 2 reporting. Third-party assurance was not required for 2026, but CARB has signaled that it will require limited assurance of Scope 1 and 2 data for 2027 and later years.27 Engage assurance providers and strengthen internal data controls now. Pause, but preserve, Scope 3 and SB 261 workstreams. Maintain existing data and processes: the ruling is preliminary, and many multinational companies will still need Scope 3 and product-level emissions data under the EU’s Corporate Sustainability Reporting Directive (CSRD) and Carbon Border Adjustment Mechanism (CBAM).28 Companies may still publish SB 261 reports voluntarily.29 Review public statements. Continue to review voluntary climate disclosures for consistency with CARB filings and other regulatory reports. Considerations for Real Estate and Infrastructure Clients The following are practice recommendations, not statutory requirements: Control boundaries. Whether emissions from a building or data center fall within a landlord’s or a tenant’s Scope 1 or 2 inventory depends on the control approach applied under the GHG Protocol. Leases, colocation agreements, and powered-shell arrangements should specify which party has operational control for GHG reporting purposes. Data cooperation. Include obligations to deliver utility and energy data (with specified timing and format) and to cooperate with assurance providers, particularly where the landlord or operator holds the utility accounts. Transactions. In acquisitions and financings, diligence the target’s or borrower’s SB 253 compliance and fee payments, and consider representations and covenants on the accuracy of emissions data. Value-chain requests. Counterparty requests for Scope 3 data may slow, but those subject to CSRD will likely continue to make them. This alert is for general information only and is not legal advice. The law in this area is changing rapidly, and developments after November 18, 2026, may affect this analysis.  1 Chamber of Commerce v. Sanchez, No. 25-5327 (9th Cir. Nov. 9, 2026) 2 White & Case, California Climate Disclosure Laws: Ninth Circuit Finds SB 253 Scope 3 Requirements and SB 261 Likely Unconstitutional (Nov. 2026) 3 Legal 500, Ninth Circuit Approves California’s Core Carbon Emissions Reporting Rules (Nov. 2026) 4 White & Case, supra note 2. 5 Kirkland & Ellis, Ninth Circuit Rules on California’s Climate Disclosure Laws (Nov. 2026) 6 Simpson Thacher, California Climate Reporting Laws: Ninth Circuit Issues Partial Injunction (Nov. 2025) 7 White & Case, supra note 2. 8 Vinson & Elkins, OAL Approves CARB’s Initial Regulation (Oct. 2026) 9 White & Case, supra note 2. 10 Foley & Lardner, California Climate Disclosure Laws (Nov. 2026) 11 White & Case, supra note 2. 12 Chamber of Commerce, No. 25-5327. 13 Kirkland & Ellis, supra note 5. 14 Troutman Pepper Locke, Ninth Circuit Rules on Challenge to California’s Climate Disclosure Laws (Nov. 2026) 15 White & Case, supra note 2. 16 Davis Polk, Getting Ready for California SB 253’s November 10 Reporting Deadline (Oct. 2026) 17 Troutman Pepper Locke, supra note 14. 18 White & Case, supra note 2. 19 Id. 20 Troutman Pepper Locke, supra note 14. 21 Morgan Lewis, Ninth Circuit Reverses Lower Court (Nov. 2026) 22 Simpson Thacher, CARB Provides New Guidance on SB 253 Reporting (July 2026) 23 Davis Polk, supra note 16. 24 Id. 25 Id. 26 CARB, SB 253/261 Public Workshop Slides (Aug. 2025) 27 Vinson & Elkins, supra note 8. 28 O’Melveny, Is Your Company Still Required to Report Under California’s Climate Laws? (Nov. 2026) 29 White & Case, supra note 2.