.

Client Alert

Energy Law: Month in Review - December 2024

January 8, 2025

Download as a PDF

Share this page

AUTHORS

Welcome to Dorsey’s Energy Law: Month in Review. We provide this update to our clients to identify significant developments in the previous month. Please reach out to any of the authors, listed above, to discuss these issues.

Table of Contents

LITIGATION AND DISPUTES

Judge Rules 2023 Law Giving Incumbent Indiana Utilities Right of First Refusal to Transmission Projects Likely Unconstitutional
A federal judge in Indiana concluded that Indiana’s law giving preference to incumbent utilities for new transmission projects likely impermissibly discriminates against out-of-state economic interests in violation of the U.S. Constitution’s dormant commerce clause. The Indiana law allows companies that already own transmission facilities physically in Indiana to avoid competition when constructing or upgrading transmission lines. The court reasoned that the law functionally requires transmission developers to become Indiana “residents” by establishing in-state presences before being able to compete for new projects awarded by the Midcontinent Independent System Operator (MISO). The judge’s decision prevents the Indiana Utility Regulatory Commission from implementing the law while the litigation proceeds.

Supreme Court Allows Coal-Ash Regulations to Go Into Effect
The U.S. Supreme Court recently denied a request to stay the effectiveness of Environmental Protection Agency (EPA) coal-ash regulations while the Court considers challenges to the regulations. The D.C. Circuit upheld the regulations on November 1. The new rules regulate legacy coal-ash leachate, requiring owners of inactive facilities to monitor groundwater and take remedial measures, even after the ash itself has been removed. The Court did not elaborate on its reasons for denying the stay.

FERC Approves $6.6 Million Settlement Following Fraudulent Recommendation to Repair Local Transmission Line
The Federal Energy Regulatory Commission (FERC) approved a $6.6 million settlement with Public Service Electric & Gas (PSE&G) due to PSE&G fraudulently misrepresenting the need to rebuild a transmission line. Although the transmission line was one of the oldest in the area and had valid needs for replacement to ensure enhanced capacity, PSE&G exaggerated the presence of steel loss caused by corrosion and deliberately concealed other information from PJM to bolster its recommendation for the $546 million project. FERC determined that the project was still justified given the age of the line and projected demands in the area but that PSE&G should face penalties for misleading PJM and violating FERC rules requiring participants to provide “accurate and factual information.”

REGULATORY DEVELOPMENTS

U.S. Treasury Releases Final Regulations for Clean Energy Investment Tax Credit
In accordance with the Inflation Reduction Act, the U.S. Treasury Department issued its final update to the regulations for Internal Revenue Code Section 48, which provides a tax credit equal to between 6% and 30% of a qualifying renewable energy project’s value. The most notable change in the regulations is the broadening of the definition of “energy property” to allow innovative renewable energy technologies to qualify for the credit. Revised after public comment on the proposed rules released in November 2023, this definition will allow costs spent on essential upgrades to be considered in the calculation of the Section 48 credit. The final regulations also: (1) broaden the definition of “energy project” so multiple parties who own part of a large project can qualify for the credit, (2) clarify that owners of underground geothermal coils may claim the credit if they own at least one heat pump, and (3) allow owners of offshore wind farms to claim the credit for subsea cables.

MISO Approves $21.9B Transmission Plan
The MISO board approved “Tranche 2.1,” a $21.9 billion long-range transmission plan centered on a 1,800 mile 765-kV backbone across the Midwest region and estimated to produce $23-$72 billion in net benefits over the next 20 years. The plan builds on the $10.3 billion Tranche 1 plan, approved in mid-2022, and currently advancing through state permitting processes. Tranche 2.1 is intended to improve congestion, handle load growth, avoid capacity costs, and improve reliability with shifting generation resources. MISO also approved $6.7 billion in local projects and new joint interconnection projects with the Southwest Power Pool.

Illinois Commission Approves 3-year Grid Plans Costing Over $1.5 Billion to Meet State Law to Increase Clean Energy Supply
On December 19, the Illinois Commerce Commission (ICC) approved a 2024-2027 grid plan for Commonwealth Edison (ComEd), which included $1.5 billion in distribution-system investments and an 11% rate increase. The ICC also approved a plan for Ameren Illinois (Ameren), which included $83 million in distribution-system investments and a 7% rate increase. ComEd and Ameren filed these plans in compliance with a 2021 Illinois law requiring the state’s largest investor-owned electric utilities to file grid plans proposing distribution-system investments designed to accelerate progress towards state clean energy goals. The utilities’ initial proposals were rejected in 2023 after the ICC found they did not meet consumer affordability and effectiveness requirements.

NERC Adopts New Standards to Address Extreme Weather and Cybersecurity
The North American Electric Reliability Corp. (NERC) adopted two new standards to improve extreme-weather reliability by requiring transmission-planning entities to meet 11 requirements to prepare for extreme-temperature events and mandating that balancing authorities perform energy-reliability assessments to plan for energy emergencies. NERC also updated standards to strengthen cybersecurity for critical infrastructure and improve risk identification. All standards are subject to regulatory approval from FERC.

Office of the U.S. Trade Representative Increases Tariffs up to 50% on Chinese Solar Energy Components
Starting January 1, the Section 301 tariff rate increased from 25% to 50% for solar wafers and polysilicon imported from China and from 0% to 25% for certain tungsten products. The tariff hikes are one of a series of increases from the Biden Administration, who described the tariffs as responding to harmful Chinese forced technology transfer practices like cyber theft and industrial espionage while also complementing domestic investments made for clean energy supply chains.

FERC Rejects PJM Proposal to Alter Planning Process for Expanding Transmission Facilities
FERC rejected a proposal by PJM and PJM transmission owners to alter the planning processes for expanding transmission facilities by granting transmission owners more control over planning. FERC stated that the amendment would have impermissibly reduced PJM’s independence from transmission owners in violation of FERC’s Order No. 2000. State regulators had protested that the change would have given transmission owners veto power over Federal Power Act Section 205 filings and resulted in transmission owners having undue influence over PJM’s planning processes. One FERC Commissioner stated that he would support moving the planning process out of its current location in the operating agreement but that PJM still needed to have exclusive responsibility over the protocol.

DOE Considers Funding and Expediting Expansion in 3 Electric Transmission Corridors
The Department of Energy (DOE) began accepting public comment on its efforts to designate three new National Interest Electric Transmission Corridors (NIETCs) to prevent power outages that would harm consumers through increased federal funding and expedited grid expansion. The three corridors are the Lake Erie-Canada Corridor primarily in Pennsylvania, the Southwestern Grid Connector Corridor primarily in Colorado and New Mexico, and the Tribal Energy Access Corridor in the Dakotas, Nebraska, and five Tribal Reservations. DOE identified a need for federal support in these corridors to support interconnection with Canada, meet future demand and generation growth, and facilitate clean energy and economic development.

Firm Highlights

Insights

Ninth Circuit Splits California’s Climate Disclosure Laws: Scope 1 and 2 Reporting Proceeds; Scope 3 and SB 261 Likely Unconstitutional

Key Takeaways On November 9, 2026, the Ninth Circuit in Chamber of Commerce v. Sanchez allowed Scope 1 and Scope 2 greenhouse gas (GHG) emissions reporting under SB 253 to proceed but held that SB 253’s Scope 3 requirement, and SB 261 in its entirety, likely violate the First Amendment.1 U.S.-formed entities with total annual revenues above $1 billion that do business in California remain subject to Scope 1 and 2 reporting. First reports (or, for eligible entities, statements of non-reporting) were due November 10, 2026.2 Scope 3 reporting (scheduled to begin in 2027) and SB 261 climate-risk reporting are effectively on hold. Entities with revenues between $500 million and $1 billion, which were covered only by SB 261, currently have no reporting obligation under either law.3 The ruling addresses only preliminary injunctive relief; it is not a final judgment on the merits. If the district court finds the Scope 3 requirement non-severable, it could also enjoin Scope 1 and 2 reporting.4 Background SB 253 (the Climate Corporate Data Accountability Act) requires U.S.-formed entities with total annual revenues above $1 billion that do business in California to report Scope 1 and 2 emissions starting in 2026 and Scope 3 emissions starting in 2027, with penalties of up to $500,000 per reporting year.5 SB 261 (the Climate-Related Financial Risk Act) requires U.S.-formed entities with total annual revenues above $500 million that do business in California to publish biennial climate-related financial risk reports consistent with the Task Force on Climate-related Financial Disclosures (TCFD) framework, with penalties of up to $50,000 per reporting year.6 Business groups led by the U.S. Chamber of Commerce challenged both laws as compelled speech that violates the First Amendment. In August 2025, the district court denied their motions for preliminary injunctions. On November 18, 2025, the Ninth Circuit enjoined SB 261 pending appeal but declined to enjoin SB 253.7 The implementing regulation adopted by the California Air Resources Board (CARB) took effect on October 12, 2026, and set November 10, 2026, as the first Scope 1 and 2 reporting deadline.8 The Court’s Decision Scope 1 and Scope 2: Upheld for Now The panel held that Scope 1 and 2 disclosures are commercial speech because they compel disclosure of factual information about emissions from a company’s own operations and purchased energy—information that bears on capital transactions. Applying intermediate scrutiny, the court concluded that the requirements advance California’s substantial interests in reducing information asymmetries for investors and in reducing emissions and are no more extensive than necessary.9 The panel split 2–1 on this issue.10 Scope 3: Likely Unconstitutional The court held that Scope 3 disclosures concern diffuse third-party conduct across the value chain and are “insufficiently tethered” to the reporting entity’s own operations to qualify as commercial speech. Applying strict scrutiny, the court concluded that the requirement likely fails because (1) SB 253 does not require primary data, (2) the record did not show that companies’ proxy-based estimates would be more reliable than estimates the State could generate itself, and (3) the link to investor-relevant risk was too remote.11 SB 261: Likely Unconstitutional in Its Entirety The court held that SB 261 compels noncommercial speech because it requires “predictive and normative judgments” about a “politically fraught subject.” Even assuming California’s interests are compelling, the court reasoned that the law is likely not narrowly tailored because California could use less restrictive alternatives, such as incentives for voluntary disclosure.12 The panel was unanimous on Scope 3 and SB 261.13 Remand and Severability The Ninth Circuit did not enter injunctions itself. It reversed the denials of preliminary injunctive relief and remanded with instructions for the district court to enter relief consistent with the opinion and, for Scope 3, to decide severability first.14 SB 253 contains an express severability clause. If the district court nevertheless finds the Scope 3 requirement non-severable, it could also enjoin Scope 1 and 2 reporting.15 Current Status at a Glance Requirement Status after the Ruling Practical Effect SB 253 – Scope 1 and 2 emissions (entities with revenues above $1 billion) In effect; denial of preliminary injunction affirmed First reports were due November 10, 2026; CARB fee notices expected by December 10, 202616 SB 253 – Scope 3 emissions (scheduled to begin in 2027) Likely unconstitutional; remanded for severability ruling and entry of injunctive relief Not required while remand is pending; scope of CARB’s 2027 rulemaking uncertain17 SB 261 – climate-related financial risk reports (entities with revenues above $500 million) Likely unconstitutional in its entirety; enjoined pending appeal since November 18, 2025 No current reporting obligation; voluntary reports permitted18 What to Watch Any petition for panel rehearing or rehearing en banc (due 14 days after entry of judgment) and any petition for a writ of certiorari to the U.S. Supreme Court.19 The district court’s severability ruling and the scope of any preliminary injunctions it enters as to Scope 3 and SB 261.20 CARB’s response. As of the date of this alert, CARB has not issued a formal statement on the opinion.21 CARB had been developing a second rulemaking for reporting years 2027 and later, addressing Scope 3, assurance, deadlines, and reporting templates, and had proposed retaining November 10 as the annual deadline.​​​​​​​22 Recommended Actions Confirm coverage entity by entity. Revenue (gross receipts, based on the lesser of the two prior fiscal years) and “doing business in California” are determined separately for each entity; affiliates are not aggregated. Retain supporting California tax records for five years.23 If a covered entity has not filed, file promptly. Submit the Scope 1 and 2 report (or, if eligible, a statement of non-reporting) and document good-faith compliance efforts, which CARB must consider in assessing penalties.24 Calendar the fee cycle. CARB expects to issue fee notices by December 10, 2026, with payment due within 60 days after the notice; each day of nonpayment is a separate violation.​​​​​​​25 CARB’s August 2025 proposal set flat fees at $3,106 per SB 253 entity and $1,403 per SB 261 entity.26 Confirm the final amount when the CARB notice arrives. Prepare for 2027 Scope 1 and 2 reporting. Third-party assurance was not required for 2026, but CARB has signaled that it will require limited assurance of Scope 1 and 2 data for 2027 and later years.27 Engage assurance providers and strengthen internal data controls now. Pause, but preserve, Scope 3 and SB 261 workstreams. Maintain existing data and processes: the ruling is preliminary, and many multinational companies will still need Scope 3 and product-level emissions data under the EU’s Corporate Sustainability Reporting Directive (CSRD) and Carbon Border Adjustment Mechanism (CBAM).28 Companies may still publish SB 261 reports voluntarily.29 Review public statements. Continue to review voluntary climate disclosures for consistency with CARB filings and other regulatory reports. Considerations for Real Estate and Infrastructure Clients The following are practice recommendations, not statutory requirements: Control boundaries. Whether emissions from a building or data center fall within a landlord’s or a tenant’s Scope 1 or 2 inventory depends on the control approach applied under the GHG Protocol. Leases, colocation agreements, and powered-shell arrangements should specify which party has operational control for GHG reporting purposes. Data cooperation. Include obligations to deliver utility and energy data (with specified timing and format) and to cooperate with assurance providers, particularly where the landlord or operator holds the utility accounts. Transactions. In acquisitions and financings, diligence the target’s or borrower’s SB 253 compliance and fee payments, and consider representations and covenants on the accuracy of emissions data. Value-chain requests. Counterparty requests for Scope 3 data may slow, but those subject to CSRD will likely continue to make them. This alert is for general information only and is not legal advice. The law in this area is changing rapidly, and developments after November 18, 2026, may affect this analysis.  1 Chamber of Commerce v. Sanchez, No. 25-5327 (9th Cir. Nov. 9, 2026) 2 White & Case, California Climate Disclosure Laws: Ninth Circuit Finds SB 253 Scope 3 Requirements and SB 261 Likely Unconstitutional (Nov. 2026) 3 Legal 500, Ninth Circuit Approves California’s Core Carbon Emissions Reporting Rules (Nov. 2026) 4 White & Case, supra note 2. 5 Kirkland & Ellis, Ninth Circuit Rules on California’s Climate Disclosure Laws (Nov. 2026) 6 Simpson Thacher, California Climate Reporting Laws: Ninth Circuit Issues Partial Injunction (Nov. 2025) 7 White & Case, supra note 2. 8 Vinson & Elkins, OAL Approves CARB’s Initial Regulation (Oct. 2026) 9 White & Case, supra note 2. 10 Foley & Lardner, California Climate Disclosure Laws (Nov. 2026) 11 White & Case, supra note 2. 12 Chamber of Commerce, No. 25-5327. 13 Kirkland & Ellis, supra note 5. 14 Troutman Pepper Locke, Ninth Circuit Rules on Challenge to California’s Climate Disclosure Laws (Nov. 2026) 15 White & Case, supra note 2. 16 Davis Polk, Getting Ready for California SB 253’s November 10 Reporting Deadline (Oct. 2026) 17 Troutman Pepper Locke, supra note 14. 18 White & Case, supra note 2. 19 Id. 20 Troutman Pepper Locke, supra note 14. 21 Morgan Lewis, Ninth Circuit Reverses Lower Court (Nov. 2026) 22 Simpson Thacher, CARB Provides New Guidance on SB 253 Reporting (July 2026) 23 Davis Polk, supra note 16. 24 Id. 25 Id. 26 CARB, SB 253/261 Public Workshop Slides (Aug. 2025) 27 Vinson & Elkins, supra note 8. 28 O’Melveny, Is Your Company Still Required to Report Under California’s Climate Laws? (Nov. 2026) 29 White & Case, supra note 2.

News

Dorsey Practices and Attorneys Recognized by Legal 500 Greater China 2027

Legal 500 Greater China 2027 recognized Dorsey & Whitney LLP in five practice areas across China (Mainland) and Hong Kong SAR and recommended six Dorsey attorneys. The Firm’s litigation practice in China advanced from Tier 4 to Tier 3 among foreign firms. Dorsey received the following practice recognitions in the 2027 edition: China — Leading Firm: Dispute Resolution: Litigation (Foreign Firms) China — Leading Firm: Insurance (Foreign Firms) China — Leading Firm: Regulatory/Compliance (Foreign Firms) Hong Kong — Leading Firm: Intellectual Property Hong Kong — Firms to Watch: Capital Markets (Equity) Leading Firm in China for Dispute Resolution: Litigation (Foreign Firms) Recommended Lawyers: Ray Liu and Janet Wong Dorsey’s litigation team excels in managing high-stake China-related cross-border disputes and legal proceedings in the United States, Hong Kong, Europe, and other jurisdictions. Its work spans an extensive array of industries including banking and finance, insurance, TMT, manufacturing, biotechnology, and life sciences. The improved ranking this year highlights the continued market recognition, the strength of our team, the quality of our client service, and our continued commitment to deliver exceptional results. Leading Firm in China for Insurance (Foreign Firms) Recommended Lawyer: Ray Liu Dorsey’s Beijing-based insurance team works with colleagues in the United States and Europe on a broad range of insurance-related disputes, with a particular focus on general liability and product liability litigation. The team also frequently advises on war risk insurance, all-risk insurance, insurance regulatory matters, and reinsurance issues, and assists major Chinese insurance companies with outbound investments, and regulatory compliance related disputes. Leading Firm in China for Regulatory/Compliance (Foreign Firms) Recommended Lawyers: Ray Liu and Karen Yiqin Fan Dorsey’s China team regularly advises on export controls, economic sanctions, national security/CFIUS, trade compliance, capital markets, and financial regulatory compliance. The team also counsels clients on data privacy, employment compliance, corporate investigations, and foreign entity of concern (FEOC) requirements under the Inflation Reduction Act (IRA) and the One Big Beautiful Bill Act (OBBBA). Leading Firm in Hong Kong for Intellectual Property Recommended Lawyers: Janet Wong and Lilian Shi Dorsey’s Greater China IP team advises multinational and local clients on the protection, management, enforcement, and commercialization of intellectual property assets across Greater China and globally. The team develops and manages global IP portfolios, advises on brand protection and anti-counterfeiting strategies, and handles contentious IP matters, including trademark infringement, copyright, trade secret, company name, and domain name disputes. The team also advises on IP-related transactions and commercialization, including IP due diligence, acquisitions and divestitures of IP rights, technology transfers, licensing and franchising arrangements, and supply, distribution, and manufacturing arrangements. Firms to Watch in Hong Kong for Capital Markets (Equity) Recommended Lawyers: Rachel Han and Megan Penick Dorsey’s Hong Kong and U.S. capital markets teams work seamlessly together on initial public offerings and placings in Hong Kong, along with initial public offerings, follow-on and secondary offerings, cross-border financings, and PIPE investments in the United States, and transactions in other international financial centers. The team also advises listed companies on ongoing compliance and regulatory matters in both Hong Kong and the United States. Drawing on Dorsey’s multidisciplinary capabilities, the Hong Kong capital markets team provides complementary advice on international sanctions and U.S. export control regulations.